Printable · GCSE Foundation · ages 14-16
Geometry and measures worksheet — GCSE Foundation
Fifteen questions across the geometry and measures statements at Foundation tier. Choose the non-calculator filter to rehearse Paper 1, which counts for a third of the marks.
Calculator
Answer key: Geometry and measures worksheet — GCSE Foundation
MathsUKwww.geekhero.co.uk
- (b) x = 5 — Every point on a vertical line has the same x-coordinate, so the equation of a vertical line through (5, 2) is x = 5. "y = 5" mixes up the coordinates, using the x-value of 5 to write a y-equation. "y = 2" is the equation of the horizontal line through (5, 2), not the vertical one. "x = 2" uses the correct letter but the wrong coordinate, the y-value of 2 instead of the x-value of 5.
- (b) 21 — Both legs of the journey are on the same bearing, 070°, so the ship travels in one straight line the whole way and the distances simply add: 12 + 9 = 21 km. A candidate who subtracts instead of adding gets 12 − 9 = 3 km. A candidate who multiplies the two distances gets 12 × 9 = 108. A candidate who assumes the ship changed direction and treats the two legs as the sides of a right-angled triangle works out √(12² + 9²) = √225 = 15 km — but the bearing does not change, so there is no triangle and no hypotenuse to find. Because the ship stays on one straight line, the total distance is 21 km.
- (d) 6√3 cm — Method: AB lies alongside the 30° angle at A and AC is the hypotenuse, so the ratio needed is cosine: cos 30° = AB ÷ AC. Working: the exact value of cos 30° is √3/2, so AB = 12 × √3 ÷ 2, and half of 12 is 6. Answer: AB = 6√3 cm, which is about 10.4 cm. Using sine by mistake gives 12 × 1/2 = 6 cm, which is the length of BC rather than AB. Using tan 30° = 1/√3 gives 12 ÷ √3, which is 4√3 cm. Remembering cos 30° as √3 rather than as √3 halved gives 12√3 cm, longer than the hypotenuse and so impossible.
- (b) y-axis — A point lies on the y-axis when its x-coordinate is 0; here the x-coordinate of (0, −5) is 0, so it lies on the y-axis. "x-axis" would need the y-coordinate to be 0 instead, which is not the case here. "the origin" is the single point (0, 0), not a whole axis, and this point is not (0, 0). "both axes" would only be true for the origin itself, where both coordinates are 0.
- (c) 56.52 cm² — Sector area = (45 ÷ 360) × 3.14 × 12² = 0.125 × 3.14 × 144 = 56.52 cm². (4.71 cm² comes from forgetting to square the radius; 452.16 cm² comes from finding the area of the whole circle and forgetting the angle fraction; 9.42 cm² comes from using the arc length formula instead of the sector area formula.)
- (c) 150 minutes — There are 60 minutes in an hour, so 2.5 hours is 2.5 × 60 = 150 minutes. Multiplying by 100 instead of 60, as if hours worked like a decimal metric unit, gives 250 minutes. Converting only the whole 2 hours and forgetting the extra 0.5 hours gives 120 minutes. Treating the 0.5 as 50 minutes, out of 100, instead of 30 minutes, out of 60, gives 170 minutes.
- (a) radius — The distance from the centre O to any point on the circle is the radius. The diameter is the distance right across the circle, through the centre, from one side to the other — twice the radius, not the same measurement. The circumference is the total distance around the circle, not from the centre. A chord is a line joining two points on the circle that does not have to pass through the centre at all.
- (d) 1 kg — First find the total mass in grams: 4 × 250 = 1000 g. Then convert to kilograms by dividing by 1000: 1000 ÷ 1000 = 1 kg. Finding the correct total in grams but forgetting to divide by 1000 gives 1000 kg. Adding the number of packs to the pack mass instead of multiplying, 4 + 250 = 254 g, gives 0.254 kg. Dividing the pack mass by the number of packs instead of multiplying, 250 ÷ 4 = 62.5 g, gives 0.0625 kg.
- (d) 452.16 cm² — Area = πr². Substitute r = 12: area = 3.14 × 12² = 3.14 × 144 = 452.16 cm².
- (d) (11, 0.75) — Add the moves to the starting point one component at a time. x: 12.5 + (−3.75) + 2.25 = 11; y: −4.25 + 6.5 + (−1.5) = 0.75, giving (11, 0.75). (8.75, 2.25) stops after the first move only and never applies the second vector. (6.5, 3.75) comes from subtracting the second vector instead of adding it. (0.75, 11) comes from swapping the final x-coordinate and y-coordinate.
- (b) 10.5 — Method: multiply the drawing length by the scale factor to get the real length. Working: 7 cm × 1.5 = 10.5 m. A student who answers 8.5 has added the scale factor to the drawing length instead of multiplying (7 + 1.5). A student who answers 14 has rounded the scale factor up to 2 before multiplying. A student who answers 3.5 has divided the drawing length by 2 instead of multiplying it by 1.5. Answer: 10.5 m.
- (a) 6 — A cuboid has six faces in total: a top, a bottom, a front, a back, and two ends — each one is a rectangle in the net, giving six rectangles altogether. Choosing 3 counts only the three PAIRS of congruent rectangles (top/bottom, front/back, two ends) rather than all six individual faces. Choosing 5 forgets one face, as if the net were missing its lid. Choosing 12 is the number of edges of a cuboid, not the number of rectangles in its net.
- (c) 151,200 cm² — First find the area in m²: 4.2 × 3.6 = 15.12 m². To convert m² to cm², multiply by 10,000, since 1 m² = 100 cm × 100 cm = 10,000 cm²: 15.12 × 10,000 = 151,200 cm². 15.12 cm² gives the area in m² without converting the units at all. 1,512 cm² multiplies by 100 instead of 10,000, treating the conversion as if it were for a single length rather than an area. 15,120 cm² multiplies by 1,000 instead of 10,000.
- (b) 10 cm — Arc length = (angle ÷ 360) × 2 × π × r, so 15.7 = (90 ÷ 360) × 2 × 3.14 × r = 1.57r, giving r = 15.7 ÷ 1.57 = 10 cm. (2.5 cm comes from forgetting the angle fraction and dividing by 2π alone; 20 cm comes from leaving out the factor of 2 in the arc length formula before dividing; 5 cm comes from dividing the arc length by π alone, ignoring both the angle fraction and the factor of 2.)
- (d) 7.7 m — The horizontal distance is adjacent to the 50° angle and the zip wire is the hypotenuse, so horizontal distance = 12 × cos 50° = 12 × 0.6428... = 7.71...≈ 7.7 m. "9.2 m" uses the sine ratio instead of cosine, 12 × sin 50° = 9.19...≈ 9.2 m, which actually finds the vertical drop of the zip wire, not the horizontal distance. "15.7 m" comes from dividing by the sine ratio instead of multiplying by the cosine ratio, 12 ÷ sin 50° = 15.66...≈ 15.7 m, both the wrong operation and the wrong ratio. "12.0 m" simply uses the length of the zip wire itself as the horizontal distance, ignoring the angle of 50° altogether.