Printable · GCSE Foundation · ages 14-16
Probability worksheet — GCSE Foundation
Fifteen questions across the probability statements at Foundation tier. Choose the non-calculator filter to rehearse Paper 1, which counts for a third of the marks.
Calculator
Answer key: Probability worksheet — GCSE Foundation
MathsUKwww.geekhero.co.uk
- (a) 753 — The estimate from 2000 spins is the most reliable, since it comes from the largest sample size, so the best estimate of the probability is 0.251. Over a further 3000 spins, the expected number landing on green is 3000 × 0.251 = 753. Writing 1050 is wrong because 3000 × 0.350 = 1050 uses the estimate from only 20 spins, the LEAST reliable of the three. Writing 870 is wrong because 3000 × 0.290 = 870 uses the estimate from 200 spins rather than the more reliable 2000-spin estimate. Writing 750 is wrong because 3000 × 0.25 = 750 ignores the recorded data completely and simply assumes each of the 4 colours is equally likely. The best estimate is 753 expected green spins.
- (d) 0.420 — Method: use the relative frequency worked out from the larger number of trials as the best estimate of the probability, since a bigger sample tends to sit closer to the true probability. Working: 84 out of 200 drops land open end up, so the relative frequency from the total is 84 ÷ 200 = 0.420. Answer: 0.420. Watch out: writing down 0.650 comes from 13 ÷ 20, using only the first, much smaller sample instead of the total. Writing down 0.535 comes from averaging 0.650 and 0.420, treating the 20-drop run and the 200-drop run as equally reliable instead of using the larger sample on its own. And writing down 0.580 comes from 1 − 0.420, working out the probability that the bottle top lands the other way up instead of open end up.
- (b) 24/125 — On the fiction branch, 160 − 112 = 48 books were returned late. None of the non-fiction books were late, so the total number of late books is 48, out of 250 books altogether: 48/250 = 24/125. Writing 3/10 is wrong because it divides the 48 late fiction books by the fiction total (160) instead of the whole library total (250). Writing 56/125 is wrong because 112/250 simplifies to 56/125, and 112 is the number of fiction books returned ON TIME, not late. Writing 9/25 is wrong because 90/250 simplifies to 9/25, and 90 is simply the number of non-fiction books, which has nothing to do with late returns. The probability is 24/125.
- (b) 4 — With 150 rolls and probability 1/6 for each number, the expected count is 150 ÷ 6 = 25. Comparing each actual count with 25: 1 is 22 (3 below), 2 is 27 (2 above), 3 is 24 (1 below), 4 is 34 (9 above), 5 is 21 (4 below) and 6 is 22 (3 below). Number 4 is furthest above its expected count, so it is the most over-represented. Number 2 is also above its expected count, but by only 2, far less than 4's 9. Number 3's count of 24 is below the expected 25, so it is under-represented, not over. Number 6's count of 22 is also below the expected 25, so it too is under-represented.
- (b) 50% — The total number of customers who bought a cake is 54 + 21 = 75, combining both hot-drink and non-hot-drink customers. As a percentage of all 150 customers, this is (75 ÷ 150) × 100 = 50%. Choosing 36% comes from only counting the hot-drink customers who bought a cake, (54 ÷ 150) × 100 = 36%, and forgetting the 21 non-hot-drink customers who also bought a cake. Choosing 14% comes from only counting the non-hot-drink customers who bought a cake, (21 ÷ 150) × 100 = 14%, and forgetting the 54 hot-drink customers who also bought a cake. Choosing 60% comes from dividing by the hot-drink total of 90 instead of the grand total of 150, (54 ÷ 90) × 100 = 60%.
- (b) 500 — Method: when a dice is known to be fair, the theoretical probability is the best thing to work from, and the more trials there are the closer the results tend to it. Working: for a fair dice the probability of a six is 1/6, so the expected number of sixes in 3000 rolls is 3000 × 1 ÷ 6 = 500. The class experiment gave a relative frequency of 14/60, but 60 trials is far too few to overturn a known theoretical value, and the school's 3000 rolls will tend towards 1/6 in any case. Answer: about 500 sixes. The distractors: 700 comes from using the class relative frequency instead of the theory, 3000 × 14 ÷ 60 = 700; 600 comes from splitting the difference between the two, since 1/6 is about 0.167 and 14/60 is about 0.233, whose mean is 0.2, and 3000 × 0.2 = 600; 2500 uses 5/6 instead of 1/6 and counts the rolls expected not to be a six.
- (b) 40% — 32 out of the 80 people chose Coffee, so the percentage is (32 ÷ 80) × 100 = 40%. Choosing 32% comes from treating 32 as if it were already a percentage out of 100, instead of dividing by the actual total of 80 people surveyed. Choosing 25% comes from using the Tea row instead of the Coffee row, (20 ÷ 80) × 100 = 25%. Choosing 20% comes from using the Juice row instead of the Coffee row, (16 ÷ 80) × 100 = 20%.
- (c) 0.37 — Method: pool the two runs into one combined set of results, then find the relative frequency of red across all of the spins together. Working: total reds = 16 + 21 = 37. Total spins = 40 + 60 = 100. Relative frequency = 37 ÷ 100 = 0.37. Answer: 0.37. Watch out: writing down 0.40 uses only the first run, 16 ÷ 40, and throws away the extra evidence from the second 60 spins. Writing down 0.35 uses only the second run, 21 ÷ 60, and throws away the first run instead. And writing down 0.375 averages the two runs' separate rates, (0.40 + 0.35) ÷ 2, which treats a run of 40 spins and a run of 60 spins as equally weighted, when pooling the actual counts gives the larger run its fair share of influence.
- (c) 170 — 68% of the 250 packets germinated: 250 × 0.68 = 170. Using the complement, the 32% that did NOT germinate, gives 250 × 0.32 = 80. Shifting the decimal point, using 0.068 instead of 0.68, gives 250 × 0.068 = 17. Rounding 68% up to 70% before multiplying gives 250 × 0.70 = 175.
- (d) 140 — 90 pupils were in Year 8 on the coach branch. The minibus branch has 200 − 150 = 50 pupils, and all of them are Year 8 too, so the total number of Year 8 pupils is 90 + 50 = 140. Writing 90 alone is wrong because it only counts the coach's Year 8 pupils and misses the minibus ones. Writing 60 is wrong because that is the number of Year 9 pupils on the coach (150 − 90 = 60), not Year 8 at all. Writing 50 alone is wrong because it only counts the minibus pupils and misses the coach's Year 8 pupils. The total is 140.
- (b) Organiser favoured — expected pay-out is under £1 — The expected pay-out per game is the prize times the probability of winning: £4 × 1/5 = £0.80. The expected income per game is the £1 entry fee, which the organiser collects regardless of the result. Since £0.80 is less than £1, the game favours the organiser, because the expected pay-out is under £1. The claim that the game favours the player, because the pay-out is over £1, is wrong on both counts — the pay-out is not over £1, and it is the organiser who benefits. The claim that the organiser is favoured because the pay-out is over £1 reaches the right side but the wrong reason: £0.80 is under £1, not over it. The claim that the two expected amounts are equal is also wrong: £0.80 and £1 are different amounts, so the game is not fair to both sides.
- (b) 8,100 — First find the total number of alerts sent in the month: 1,500 × 30 = 45,000. Then apply the probability of a 'STOP' reply: 45,000 × 0.18 = 8,100. Stopping after finding only one day's expected replies, 1,500 × 0.18 = 270, forgets to scale up to the whole month. Multiplying the number of days by the probability instead of by the daily total of alerts gives 30 × 0.18 = 5.4, which rounds to 5. Shifting the decimal point in the probability, using 0.018 instead of 0.18, gives 45,000 × 0.018 = 810.
- (b) £100 — Over 250 games, the expected total winnings are 250 × (1/5) × £12 = £600, since a player wins on 1 of the 5 equally likely sections. The total cost of playing is 250 × £2 = £500. The players' expected profit is the winnings minus the cost: £600 − £500 = £100. Writing £500 is wrong because that is only the total cost of playing, without any winnings included. Writing £600 is wrong because that is only the total expected winnings, without subtracting what was paid to play. Writing £2,500 is wrong because it assumes a win on every single game (250 × £12 = £3,000) instead of using the 1-in-5 probability, then subtracts the cost: £3,000 − £500 = £2,500. The players' expected profit over the 250 games is £100.
- (b) 0.55 — Method: it is easier to find the probability that Ffion wins NEITHER stage, then subtract that from 1. Working: P(lose stage 1) = 1 − 0.4 = 0.6, and P(lose stage 2) = 1 − 0.25 = 0.75. P(neither) = 0.6 × 0.75 = 0.45. P(at least one) = 1 − 0.45 = 0.55. Answer: 0.55. Watch out: adding the two win probabilities, 0.4 + 0.25 = 0.65, treats winning both as impossible and overcounts — that is not how independent probabilities combine. Multiplying the two win probabilities, 0.4 × 0.25 = 0.1, gives the probability of winning BOTH stages, not at least one. And stopping at 0.45, the probability of winning neither stage, forgets the final step of subtracting from 1.
- (b) 57/100 — Pooling both trials: total heads = 24 + 33 = 57, total flips = 40 + 60 = 100, so the combined relative frequency is 57/100, which is already in its simplest form since 57 and 100 share no common factor. Averaging the two separate relative frequencies instead, (24/40 + 33/60) ÷ 2 = (0.6 + 0.55) ÷ 2 = 0.575 = 23/40, treats the two trials as equally weighted even though Ben made more flips, which is not correct. Using only Leah's data gives 24/40 = 3/5. Using only Ben's data gives 33/60 = 11/20.
Build your own mix at the worksheet builder.