Printable · GCSE Foundation · ages 14-16
Probability worksheet — GCSE Foundation
Fifteen questions across the probability statements at Foundation tier. Choose the non-calculator filter to rehearse Paper 1, which counts for a third of the marks.
Calculator
Answer key: Probability worksheet — GCSE Foundation
MathsUKwww.geekhero.co.uk
- (c) 102 — Method: turn the past record into a relative frequency, then use it as an estimate of the probability of rain and multiply by the number of days being predicted for. Working: relative frequency of rain = 70 ÷ 250 = 0.28. Expected rainy days in 365 days = 365 × 0.28 = 102.2, which rounds to about 102 days. Answer: about 102 days. Watch out: writing down 48 swaps which number is the sample and which is the target, working out 70 ÷ 365 × 250 instead of 70 ÷ 250 × 365. Writing down 70 just repeats the original count of rainy days without scaling it up to the new, longer period at all. And writing down 110 comes from rounding the relative frequency to 0.3 before multiplying, 365 × 0.3 = 109.5, when 70 ÷ 250 is exactly 0.28 and needs no rounding at all.
- (c) 100 — There are 3 even numbers on a fair dice (2, 4 and 6), so the probability of landing on an even number is 3/6 = 1/2, and 300 × 1/2 = 150. The probability of landing on a six is 1/6, so 300 × 1/6 = 50. The dice is expected to land on an even number 150 − 50 = 100 more times than on a six. Writing 50 is wrong because that is just the expected number of sixes on its own, without comparing it to the expected number of evens. Writing 150 is wrong because that is just the expected number of evens on its own, without subtracting the sixes. Writing 200 is wrong because it adds the two expected frequencies together (150 + 50 = 200) instead of finding the difference between them. The dice is expected to land on an even number 100 more times than on a six.
- (a) 6.75% — Finishing, retiring and being disqualified are exhaustive, so the three percentages sum to 100%: 100% − 68.5% − 24.75% = 6.75%. Adding the two given percentages instead of subtracting them from 100% gives 68.5% + 24.75% = 93.25%, the combined probability of finishing or retiring, not of being disqualified. Subtracting only the retiring percentage from 100% and forgetting the finishing percentage gives 100% − 24.75% = 75.25%. Subtracting only the finishing percentage and forgetting the retiring percentage gives 100% − 68.5% = 31.50%.
- (c) 30 — The numbers less than 4 are 1, 2 and 3, so the probability of that event is 3/6, and the expected count in 90 rolls is 90 × 3/6 = 45. The probability of rolling a 6 is 1/6, and the expected count is 90 × 1/6 = 15. The difference between the two expected counts is 45 − 15 = 30. A candidate who answers 45 has given the expected count for 'less than 4' only, forgetting to subtract the other expected count. A candidate who answers 15 has given the expected count for '6' only. A candidate who answers 36 has used a dice with 5 possible numbers instead of 6, giving 90 × 3/5 = 54 and 90 × 1/5 = 18, a difference of 36.
- (c) No — 7/30 is the relative frequency; theory stays 1/6. — The theoretical probability of rolling a 6 on an ordinary dice is fixed at 1/6, worked out from the number of equally likely outcomes, and does not change however the dice is actually rolled. The relative frequency from this trial is 7/30, found from what happened in these particular 30 rolls. Since 7/30 and 1/6 are different numbers, the correct statement is 'No — 7/30 is the relative frequency; theory stays 1/6.' Assuming the two values must always match because they describe the same event gives 'Yes — relative frequency always equals theory.' Believing that an observed result redefines the theoretical probability gives 'Yes — the theoretical probability has now become 7/30.' Refusing to work out either value at all gives 'Neither can be found — 30 rolls is too few to tell', which ignores that both numbers CAN be calculated from the information given.
- (b) 70 — Saloon, estate and hatchback are exhaustive, so their probabilities sum to 1: the probability of a hatchback is 1 − 0.28 − 0.37 = 0.35. The number of hatchbacks is 0.35 × 200 = 70. Treating the SUM of the other two probabilities, 0.28 + 0.37 = 0.65, as the probability of a hatchback instead of its complement gives 0.65 × 200 = 130. Multiplying the correct probability, 0.35, by 100 instead of the 200 cars actually surveyed gives 35. Averaging the two given probabilities, (0.28 + 0.37) ÷ 2 = 0.325, instead of subtracting them from 1, and then multiplying by 200 gives 65.
- (c) Red — Theoretical probability is 1/3 ≈ 0.333 for each colour. Red's relative frequency is 38/90 ≈ 0.422, above 1/3, so red is over-represented. Blue's relative frequency is 26/90 ≈ 0.289, below 1/3, so blue is under-represented, not over. Green's relative frequency is also 26/90 ≈ 0.289, below 1/3 for the same reason. Since red's relative frequency clearly exceeds 1/3, it is not true that none of the colours are over-represented.
- (d) 1/4 — Method: a product is odd only when BOTH factors are odd, so list the ordered pairs where both scores are odd and divide by 36. Working: the odd scores on a dice are 1, 3 and 5, so there are 3 × 3 = 9 ordered pairs where both scores are odd, out of the 36 equally likely pairs, cancelling down to 1/4. Answer: 1/4. Watch out: writing down 3/4 finds the probability that AT LEAST ONE score is odd, 1 minus the probability both are even, which is a different, easier condition to meet than both being odd. Considering only the first dice's score and ignoring the second gives 1/2, since 3 of the first dice's 6 scores are odd — but the product also depends on what the second dice shows. And writing down 1/12 comes from counting only the pairs where the SAME odd number appears twice, (1, 1), (3, 3) and (5, 5), missing pairs like (1, 3) and (5, 1) where the two odd scores differ.
- (a) 0.48 — There are two ways to score exactly one throw: scoring on the first and missing the second, 0.6 × 0.4 = 0.24, or missing the first and scoring the second, 0.4 × 0.6 = 0.24. Adding these gives 0.24 + 0.24 = 0.48. Choosing 0.24 comes from working out only one of the two paths and forgetting the other one also gives exactly one score. Choosing 0.36 comes from working out the probability of scoring BOTH throws, 0.6 × 0.6 = 0.36, instead of exactly one. Choosing 0.84 comes from working out the probability of scoring AT LEAST one throw, 1 − 0.4 × 0.4 = 0.84, instead of exactly one.
- (a) £124.80 — On the cake branch, 150 − 100 = 50 cakes were bought by children. Adding the 54 biscuits bought by children gives 50 + 54 = 104 items sold to children in total, and at £1.20 each that raises 104 × £1.20 = £124.80. Writing £60.00 is wrong because 50 × £1.20 = £60.00 only counts the cake sales to children and leaves out the 54 biscuits. Writing £163.20 is wrong because it uses the ADULT sales instead of children's: 100 cake adults plus 90 − 54 = 36 biscuit adults gives 136 × £1.20 = £163.20. Writing £136.80 is wrong because it finds the cake children's number by subtracting the wrong branch (150 − 90 = 60 instead of 150 − 100 = 50), giving 60 + 54 = 114 items and 114 × £1.20 = £136.80. The total raised from sales to children is £124.80.
- (b) 100 — The sample shows a proportion of 8/60 = 2/15 faulty. Apply that proportion to the new batch of 750: 750 × 2/15 = 100. Flipping the ratio, calculating 8/750 × 60 instead of 8/60 × 750, gives 0.64, which rounds to about 1. Assuming the same number of faulty items applies to the new batch, without scaling for its larger size, just repeats the sample's count of 8. Rounding the proportion 8/60 = 0.1333... down to 0.1 before multiplying gives 750 × 0.1 = 75.
- (a) 160 — Expected number = probability × number of trials = 0.08 × 2,000 = 160. Moving the decimal point one place too far, using 0.008 instead of 0.08, gives 2,000 × 0.008 = 16. Working out the expected number of customers who do NOT buy a bag, using the complement 1 − 0.08 = 0.92, gives 2,000 × 0.92 = 1,840. Rounding 0.08 up to 0.1 before multiplying gives 2,000 × 0.1 = 200.
- (b) 22.8% — Relative frequency as a percentage is the faulty count divided by the total, then multiplied by 100: 33 ÷ 145 × 100 = 22.76, which rounds to 22.8%. Giving 33.0% as the answer uses the frequency, 33, directly as a percentage without dividing by the total 145 at all. Rounding 22.76 down to 22.7% instead of up applies the wrong rounding direction at the first decimal place. Finding the relative frequency of the bulbs that were NOT faulty first: 145 − 33 = 112, and 112 ÷ 145 × 100 = 77.24, answers the opposite question and rounds to 77.2%.
- (d) 3/16 — Method: work out each draw's own probability first, then multiply them together since the two draws are independent. Working: there are 8 tickets in all, 3 of them blue, so P(blue) = 3/8. P(spinner number greater than 2) = 2/4 = 1/2, since 3 and 4 qualify. Multiplying gives 3/8 × 1/2, which comes to 3/16. Answer: 3/16. Watch out: writing down 3/8 stops after the first draw and never brings in the spinner at all. Writing down 1/2 does the opposite, using only the spinner and ignoring the ticket draw. And writing down 5/16 uses 5/8, the probability of a RED ticket, instead of 3/8 for blue — reading the wrong colour off the raffle.
- (c) 1/10 — On the adult branch, 210 − 189 = 21 appointments were missed. There are 300 − 210 = 90 child appointments, and 90 − 81 = 9 of those were missed. In total, 21 + 9 = 30 appointments were missed, out of 300: 30/300 = 1/10. Writing 7/100 is wrong because 21/300 simplifies to 7/100, and 21 only counts the adult branch, leaving out the 9 missed child appointments. Writing 3/100 is wrong because 9/300 simplifies to 3/100, and 9 only counts the child branch, leaving out the 21 missed adult appointments. Writing 1/9 is wrong because it divides the 30 missed appointments by the 270 that were attended (300 − 30) instead of by the whole 300 booked. The probability is 1/10.
Build your own mix at the worksheet builder.