Printable · GCSE Foundation · ages 14-16
Probability worksheet — GCSE Foundation
Fifteen questions across the probability statements at Foundation tier. Choose the non-calculator filter to rehearse Paper 1, which counts for a third of the marks.
Calculator
Answer key: Probability worksheet — GCSE Foundation
MathsUKwww.geekhero.co.uk
- (b) £100 — Method: find the expected number of wins, turn that into the expected pay out, then compare it with what the games cost. Working: the expected number of wins is 200 × 0.15 = 30. Each win pays £10, so the expected pay out is 30 × 10 = 300 pounds. Playing 200 times at £2 a go costs 200 × 2 = 400 pounds. The expected loss is 400 − 300 = 100 pounds. Answer: Amir should expect to be about £100 down. The distractors: £300 is the expected winnings on their own, with the cost of playing never taken off; £400 is the total cost of playing, with the winnings never taken off; £700 comes from adding the two totals, 400 + 300 = 700, instead of subtracting one from the other.
- (d) 0.80 — Evens is exactly halfway along the scale, at 0.5, and 3/10 written as a decimal is 0.3. A probability 3/10 higher than evens is 0.5 + 0.3 = 0.80. Giving 0.30 as the answer converts the increase but never adds it to the value of evens. Adding the increase to 1, the 'certain' end of the scale, instead of to evens gives 1 + 0.3 = 1.30, which cannot be a probability. Writing 3/10 as 0.03 instead of 0.3, a place-value slip, gives 0.5 + 0.03 = 0.53.
- (c) 100 — There are 3 even numbers on a fair dice (2, 4 and 6), so the probability of landing on an even number is 3/6 = 1/2, and 300 × 1/2 = 150. The probability of landing on a six is 1/6, so 300 × 1/6 = 50. The dice is expected to land on an even number 150 − 50 = 100 more times than on a six. Writing 50 is wrong because that is just the expected number of sixes on its own, without comparing it to the expected number of evens. Writing 150 is wrong because that is just the expected number of evens on its own, without subtracting the sixes. Writing 200 is wrong because it adds the two expected frequencies together (150 + 50 = 200) instead of finding the difference between them. The dice is expected to land on an even number 100 more times than on a six.
- (c) 9/16 — There are 180 students in total and 84 are in Year 11, so Year 10 has 180 − 84 = 96 students. Of those 96, 42 travel by bus, so 96 − 42 = 54 walk. P(Year 10 student walks) = 54/96 = 9/16. Using the whole school of 180 as the denominator instead of just the 96 Year 10 students gives 54/180 = 3/10. Using the bus count, 42, as if it were the number who walk gives 42/96 = 7/16, the wrong branch of the Year 10 row. Working out the probability for Year 11 instead of Year 10 — 46 walkers out of 84 — gives 46/84 = 23/42.
- (b) likely — On the probability scale, 'certain' is reserved for a probability of exactly 1, and 'evens' describes a probability of exactly 0.5. A probability of 0.9 is high but not equal to 1, so the correct word is 'likely'. Choosing 'certain' treats a probability close to 1 as if it were exactly 1, which it is not. Choosing 'evens' misjudges 0.9 as being close to the midpoint of the scale, when it is close to the 'certain' end instead. Choosing 'unlikely' reads the scale the wrong way round, as if a high probability meant a low chance of happening.
- (b) 57/100 — Pooling both trials: total heads = 24 + 33 = 57, total flips = 40 + 60 = 100, so the combined relative frequency is 57/100, which is already in its simplest form since 57 and 100 share no common factor. Averaging the two separate relative frequencies instead, (24/40 + 33/60) ÷ 2 = (0.6 + 0.55) ÷ 2 = 0.575 = 23/40, treats the two trials as equally weighted even though Ben made more flips, which is not correct. Using only Leah's data gives 24/40 = 3/5. Using only Ben's data gives 33/60 = 11/20.
- (b) 8,100 — First find the total number of alerts sent in the month: 1,500 × 30 = 45,000. Then apply the probability of a 'STOP' reply: 45,000 × 0.18 = 8,100. Stopping after finding only one day's expected replies, 1,500 × 0.18 = 270, forgets to scale up to the whole month. Multiplying the number of days by the probability instead of by the daily total of alerts gives 30 × 0.18 = 5.4, which rounds to 5. Shifting the decimal point in the probability, using 0.018 instead of 0.18, gives 45,000 × 0.018 = 810.
- (b) 40 — n(P ∪ Q) = n(P) + n(Q) − n(P ∩ Q) = 34 + 27 − 11 = 50. The complement is everyone outside both sets: n((P ∪ Q)′) = 90 − 50 = 40. Adding P and Q without subtracting the overlap gives 34 + 27 = 61, so 90 − 61 = 29 double-subtracts the 11 who are in both. Reporting n(P ∪ Q) itself, 50, forgets to take the complement at all. Subtracting only n(P) from the universal set, 90 − 34 = 56, ignores set Q altogether.
- (a) 0.36 — Relative frequency is the number of times the event happened divided by the total number of trials: 18 ÷ 50 = 0.36. Dividing by 100 instead of the actual 50 spins gives 18 ÷ 100 = 0.18. Finding the relative frequency of NOT landing on green, using 50 − 18 = 32 spins, gives 32 ÷ 50 = 0.64. Misplacing the decimal point in the division, so that 18 ÷ 50 is carried out as 18 ÷ 500, gives 0.036 — a tenth of the correct value.
- (a) 160 — Expected number = probability × number of trials = 0.08 × 2,000 = 160. Moving the decimal point one place too far, using 0.008 instead of 0.08, gives 2,000 × 0.008 = 16. Working out the expected number of customers who do NOT buy a bag, using the complement 1 − 0.08 = 0.92, gives 2,000 × 0.92 = 1,840. Rounding 0.08 up to 0.1 before multiplying gives 2,000 × 0.1 = 200.
- (a) 43/70 — There are 140 − 85 = 55 Zone B households, and 55 − 21 = 34 of them recycle glass. In total, 52 + 34 = 86 households recycle glass, out of 140: 86/140 = 43/70. Writing 13/35 is wrong because 52/140 simplifies to 13/35, and 52 only counts Zone A, leaving out the 34 Zone B recyclers. Writing 17/70 is wrong because 34/140 simplifies to 17/70, and 34 only counts Zone B, leaving out the 52 Zone A recyclers. Writing 73/140 is wrong because it adds the 52 Zone A recyclers to the 21 Zone B households that do NOT recycle, mixing up two different groups instead of adding the two recycling groups. The probability is 43/70.
- (b) 70 — Saloon, estate and hatchback are exhaustive, so their probabilities sum to 1: the probability of a hatchback is 1 − 0.28 − 0.37 = 0.35. The number of hatchbacks is 0.35 × 200 = 70. Treating the SUM of the other two probabilities, 0.28 + 0.37 = 0.65, as the probability of a hatchback instead of its complement gives 0.65 × 200 = 130. Multiplying the correct probability, 0.35, by 100 instead of the 200 cars actually surveyed gives 35. Averaging the two given probabilities, (0.28 + 0.37) ÷ 2 = 0.325, instead of subtracting them from 1, and then multiplying by 200 gives 65.
- (c) 11/20 — 'Red or white' combines two mutually exclusive events, so add their probabilities: 3/10 = 6/20 and 1/4 = 5/20, giving 6/20 + 5/20 = 11/20. Multiplying the two probabilities instead of adding them, 3/10 × 1/4, gives 3/40, which would be the probability of red and white together, not red or white — and a bead can't be both colours. Subtracting the sum from 1, 1 − 11/20 = 9/20, gives the probability of the bead being black instead of red or white. Converting 1/4 as 4/20 instead of 5/20 (dividing 20 by 4 but forgetting to scale the numerator) gives 6/20 + 4/20 = 1/2.
- (c) 170 — 68% of the 250 packets germinated: 250 × 0.68 = 170. Using the complement, the 32% that did NOT germinate, gives 250 × 0.32 = 80. Shifting the decimal point, using 0.068 instead of 0.68, gives 250 × 0.068 = 17. Rounding 68% up to 70% before multiplying gives 250 × 0.70 = 175.
- (a) 20 — Dice A is fair, so its expected number of sixes is 150 × 1/6 = 25. Dice B has P(6) = 0.3, so its expected number of sixes is 150 × 0.3 = 45. The difference is 45 − 25 = 20. Adding the two expected values instead of subtracting them gives 25 + 45 = 70. Reporting Dice B's expected sixes on their own, without comparing to Dice A, gives 45. Using the fair probability 1/6 for Dice B as well as Dice A ignores the bias altogether, giving 150 × 1/6 = 25 for both dice and a difference of 0.
Build your own mix at the worksheet builder.