- (d) The candle's height decreases by 0.3 cm every minute. — A negative gradient means the quantity on the vertical axis decreases as the quantity on the horizontal axis increases. The size of the gradient, 0.3, gives the amount of decrease per minute.
- (b) Provider Y — £21.00 against Provider X's £23.00 — Provider X's gradient is (35 − 15) ÷ 100 = 0.2, so cost = 15 + 0.2 × 40 = 15 + 8 = £23.00. Provider Y's gradient is (45 − 5) ÷ 100 = 0.4, so cost = 5 + 0.4 × 40 = 5 + 16 = £21.00. £21.00 is less than £23.00, so Provider Y is cheaper: 'Provider Y — £21.00 against Provider X's £23.00'. Getting both costs right but naming Provider X as cheaper compares the two numbers the wrong way round — £23.00 is more than £21.00, not less. Comparing only the fixed fees, £15.00 and £5.00, ignores the cost of the 40 gigabytes actually used. Reading off the costs at 100 gigabytes, £35.00 and £45.00, directly from the graph answers a different usage from the 40 gigabytes the question asks about.
- (c) £310 — Gradient = (210 − 130) ÷ (7 − 3) = 80 ÷ 4 = 20, so the monthly rate is £20. Using C = 20m + c with the point (3, 130): 130 = 60 + c, so c = 70. After 12 months: C = 20 × 12 + 70 = 240 + 70 = £310.
- (a) The plumber charges £20 for each extra hour worked — The gradient is the change in C divided by the change in h: (85 − 45) ÷ (3 − 1) = 40 ÷ 2 = £20. On this graph the gradient represents the extra amount charged for each extra hour worked, so the answer is 'The plumber charges £20 for each extra hour worked'. Not dividing by the change in h gives 40, the option that reads 'charges £40 for each extra hour worked' — that is the total change in cost between the two points, not the rate per hour. Reading off the C-value of the first point, 45, gives the option using £45 — that is the cost of a job lasting 1 hour, not the rate. Treating the gradient as a flat total charge regardless of the time taken misunderstands what a straight-line graph through two different h-values shows: the cost does depend on h, so it cannot be a single fixed total.
- (a) Inverse proportion — A curve that decreases and never touches either axis is the standard shape for inverse proportion, y = k/x. Direct proportion graphs are straight lines through the origin, which this is not, so it must be inverse proportion rather than neither.
- (d) 20 — Gradient = change in T ÷ change in t = (140 − 60) ÷ (6 − 2) = 80 ÷ 4 = 20. A student who subtracts in the wrong order gets −20. A student who divides 80 by 2 instead of 4 gets 40. A student who wrongly treats the line as passing through the origin and uses the point (2, 60) on its own gets 60 ÷ 2 = 30.
- (d) 25 — Gradient = (60 − 20) ÷ (15 − 5) = 40 ÷ 10 = 4 litres per minute. Since the butt is empty at t = 0, V = 4t. Setting V = 100 gives t = 100 ÷ 4 = 25 minutes.
- (c) £32 — First find the gradient: (26 − 14) ÷ (50 − 20) = 12 ÷ 30 = £0.40 per minute. Using the point (20, 14), the charge for 65 minutes is 14 + 0.40 × (65 − 20) = 14 + 18 = £32. Choosing £26 comes from treating the charge as directly proportional to the time, multiplying the gradient by 65 minutes and ignoring the fixed part of the charge (0.40 × 65 = 26). Choosing £40 comes from treating £14 as if it were the charge at 0 minutes, then adding the gradient multiplied by the full 65 minutes (14 + 0.40 × 65 = 40), instead of multiplying by the extra time past 20 minutes. Choosing £33.80 comes from assuming the charge is directly proportional to the minutes already known, scaling up from the point (50, 26) in the ratio 65:50 (65 ÷ 50 × 26 = 33.80).
- (b) 8 — Method: the gradient of a straight line is the change in the vertical value divided by the change in the horizontal value between two points on the line. Working: from the origin (0, 0) to (5, 40) the vertical change is 40 − 0 = 40 and the horizontal change is 5 − 0 = 5, so the gradient is 40 ÷ 5 = 8, which here means a cost of £8 for each litre. Answer: 8. The distractors: 0.125 comes from dividing the horizontal change by the vertical change, 5 ÷ 40, which gives litres per pound instead of the gradient; 40 comes from reading off the vertical value of the point and calling it the gradient, ignoring the 5 litres it took to reach that cost; 35 comes from subtracting the two coordinates, 40 − 5, instead of dividing them.
- (a) £3.00 per window — The gradient is the change in C divided by the change in w. Change in C = 26 − 14 = 12. Change in w = 6 − 2 = 4. Gradient = 12 ÷ 4 = £3.00 per window. Dividing the change in w by the change in C instead gives 4 ÷ 12 = £0.33 per window. Dividing 12 by the larger w-value only, 12 ÷ 6 = £2.00 per window, comes from not subtracting the smaller w-value first. Adding the w-values instead of subtracting, 12 ÷ (6 + 2) = £1.50 per window, comes from a sign error when finding the change in w.
- (c) Firm B — £3 per mile against Firm A's £2 per mile — Firm A's gradient is (14 − 4) ÷ 5 = 2, so it charges £2 per mile. Firm B's gradient is (21 − 6) ÷ 5 = 3, so it charges £3 per mile. £3 is more than £2, so Firm B charges more per mile. Swapping the two firms' gradients gives the answer with Firm A at £3 and Firm B at £2, which has the labels the wrong way round. Dividing the change in miles by the change in cost, instead of the other way round, gives 5 ÷ 10 = £0.50 for Firm A and 5 ÷ 15 = £0.33 for Firm B and so names Firm A — that is the gradient upside down. And a positive fixed charge does not mean two firms charge the same rate: the rate is found from the gradient, not from whether the intercept is positive.
- (a) The hourly rate is £5 and the fixed fee is £7 — The gradient is (27 − 12) ÷ (4 − 1) = 15 ÷ 3 = £5, the hourly rate. Using the point (1, 12): 12 = 5 × 1 + fee, so the fee is 12 − 5 = £7. That gives 'The hourly rate is £5 and the fixed fee is £7'. Swapping the two figures gives the statement with £7 as the rate and £5 as the fee, which has them the wrong way round. Taking the C-value of the first point, £12, as the fixed fee ignores that 1 hour of hire is already included in that £12. Using 15, the change in C, as the hourly rate without dividing by the change in h (3 hours) gives the statement claiming a £15 hourly rate.
- (b) 8 — The gradient of a line through the origin is the y-value divided by the x-value at any point on the line. Using (10, 80): gradient = 80 ÷ 10 = 8.
- (b) 2, the cost in pounds of each extra gigabyte — Method: the gradient is the change in cost divided by the change in data, so it is the cost of each extra gigabyte; the value where the line meets the vertical axis is the charge before any data is used, which is a different quantity. Working: from (0, 10) to (8, 26) the cost rises by 26 − 10 = 16 pounds while the data rises by 8 − 0 = 8 gigabytes, so the gradient is 16 ÷ 8 = 2, meaning each extra gigabyte costs £2. Answer: 2, the cost in pounds of each extra gigabyte. The distractors: '10, the cost in pounds of each extra gigabyte' reads the intercept as the gradient, but 10 is what the tariff costs when no data at all has been used; '3.25, the cost in pounds of each extra gigabyte' comes from 26 ÷ 8, treating the line as though it passed through the origin when it starts at 10; '2, the fixed monthly charge in pounds' has the gradient right but describes the intercept, and the fixed charge on this tariff is £10.
- (d) £2.00 — Cost for Printer A = 200 × £0.04 = £8. Cost for Printer B = 200 × £0.05 = £10. Difference = £10 − £8 = £2.00.