Printable · GCSE Foundation · ages 14-16
Ratio, proportion and rates of change worksheet — GCSE Foundation
Fifteen questions across the ratio, proportion and rates of change statements at Foundation tier. Choose the non-calculator filter to rehearse Paper 1, which counts for a third of the marks.
Calculator
Ratio, proportion and rates of change worksheet — GCSE Foundation
MathsUKwww.geekhero.co.uk
- 1.Paint costs £14.40 for every 20 m² of wall it covers. Assuming the same rate, work out the cost of the paint needed to cover 56 m² of wall.
- 2.£2000 is invested in a savings account that pays 5% compound interest each year. Work out the value of the investment at the end of 2 years.
- 3.A crate exerts a force of 84 N on the floor through a base with an area of 2.4 m². Work out the pressure on the floor, in N/m².
- 4.Priya is paid £58.50 for working 7.5 hours on a Saturday. Work out her rate of pay, in £ per hour.
- 5.A tap fills a tank at a rate of 15 litres per minute. Given that 1 litre = 1000 cm³, work out the rate at which the tank fills in cm³ per second.
- 6.A jug of squash is made by mixing water and syrup in the ratio 6:1. Nia wants to make 8.4 litres of squash. Work out how much syrup she needs, in litres.
- 7.A shop sells ribbon by the metre. 2 m costs £3.00, 4 m costs £6.00, and 7 m costs £10.50. Does this data show that the cost is directly proportional to the length of ribbon bought? Choose the correct verdict and reason.
- 8.A delivery driver travels 45 km in the first 30 minutes of a journey, and then a further 75 km in the next 1 hour. Work out her average speed for the whole journey, in km/h.
- 9.A furniture maker builds two mathematically similar bookcases. The smaller bookcase is 40 cm tall and uses 2 m² of wood. The larger bookcase is 60 cm tall. Work out the area of wood needed for the larger bookcase, giving your answer in m².
- 10.The mass of a length of copper pipe is proportional to its length. A pipe of length 4.5 m has a mass of 12.6 kg. Work out the mass of a pipe of the same type of length 9.5 m.
- 11.A force of 250 N acts on an area of 0.5 m². Using pressure = force ÷ area, work out the pressure, in pascals.
- 12.It takes 2 identical pumps 10 hours to empty a flooded basement. Working at the same rate, work out how many hours 5 of these pumps would take to empty the same basement.
- 13.There are 2500 electric cars registered in a town. The number is predicted to increase by 6% each year. Work out the predicted number of electric cars after 3 years, to the nearest whole number.
- 14.The number of euros, e, received is directly proportional to the number of pounds, p, exchanged. Exchanging £40 gives 46 euros. Work out how many euros are received for £65, giving your answer to the nearest euro.
- 15.A straight-line graph shows the distance travelled, d kilometres, against the time taken, t hours, for a cyclist. The line passes through the origin and has a gradient of 18. Write down what the gradient of this line represents.
Answer key
- (a) £40.32 — Find the cost per square metre from the rate given: £14.40 ÷ 20 = £0.72 per m². Then multiply by the area to be covered: £0.72 × 56 = £40.32. Working out 14.40 × 20 ÷ 56 ≈ £5.14 uses the ratio the wrong way round, scaling down as if 56 m² needed less paint than 20 m². Stopping at £0.72 only gives the cost per square metre, not the cost for the whole wall. Working out 14.40 + (56 − 20) = £50.40 adds the extra square metres straight onto the cost in pounds, treating square metres and pounds as the same kind of quantity. Covering 56 m² costs £40.32.
- (b) £2205.00 — With compound interest each year's interest is worked out on the value at the start of that year, so a 5% rise is a multiplier of 1.05 applied once per year. After the first year: 2000 × 1.05 = 2100. After the second year: 2100 × 1.05 = 2205. The question asks for the value of the investment, not for the interest earned, so the answer is £2205.00.
- (b) 35 N/m² — Pressure = force ÷ area. 84 ÷ 2.4 = 35 N/m². 201.6 N/m² comes from multiplying the force by the area instead of dividing (84 × 2.4). 81.6 N/m² comes from subtracting the area from the force (84 − 2.4) instead of dividing. 0.03 N/m² comes from dividing the area by the force instead of the force by the area (2.4 ÷ 84).
- (a) £7.80 — Rate of pay = total pay ÷ number of hours. £58.50 ÷ 7.5 = £7.80 per hour. £438.75 comes from multiplying the pay by the hours instead of dividing (£58.50 × 7.5). £0.13 comes from dividing the hours by the pay instead of the pay by the hours (7.5 ÷ 58.50). £51.00 comes from subtracting the hours from the pay (£58.50 − 7.5) instead of dividing.
- (d) 250 cm³/s — Method: first change litres per minute into cm³ per minute, then change per minute into per second. Working: 15 × 1000 = 15000 cm³ per minute, then 15000 ÷ 60 = 250 cm³ per second. So the tank fills at 250 cm³ per second. Distractor 15000 cm³/s comes from stopping after the first step and forgetting to change minutes into seconds. Distractor 900000 cm³/s comes from multiplying by 60 instead of dividing. Distractor 2500 cm³/s comes from dividing by 6 instead of 60.
- (c) 1.2 — Add the parts of the ratio: 6 + 1 = 7. Divide the total amount by the number of parts: 8.4 ÷ 7 = 1.2 litres, which is the value of one part and also the amount of syrup, since syrup is 1 part. (7.2 litres is the amount of water, using 6 parts instead of 1. 1.4 comes from dividing 8.4 by 6 — the water's part of the ratio — instead of dividing by the total number of parts, 7. 0.84 comes from dividing 8.4 by 10 instead of by 7.)
- (a) Yes — the cost per metre is £1.50 each time — Direct proportion holds if the cost per metre is the same every time. Check each pair: 3.00 ÷ 2 = 1.50, 6.00 ÷ 4 = 1.50, and 10.50 ÷ 7 = 1.50. All three give the same rate, £1.50 per metre, so the data does show direct proportion. Saying only that the cost increases as the length increases is not enough on its own — many non-proportional relationships also increase, so this reason does not prove proportion. Misreading 10.50 ÷ 7 as 1.05 by misplacing the decimal point gives a false mismatch that is not actually there. Requiring every length to be a double of another confuses a special case (doubling) with the general test, which is that the rate itself stays constant. The data does show direct proportion, at £1.50 per metre.
- (a) 80 km/h — Average speed = total distance ÷ total time. Total distance = 45 + 75 = 120 km. Total time = 30 minutes + 1 hour = 1.5 hours. 120 ÷ 1.5 = 80 km/h. 60 km/h comes from treating the 30 minutes as a whole hour, giving a total time of 2 hours instead of 1.5 (120 ÷ 2). 82.5 km/h comes from averaging the two separate speeds (45 ÷ 0.5 = 90 km/h and 75 ÷ 1 = 75 km/h, then (90 + 75) ÷ 2) instead of using total distance over total time. 75 km/h comes from using only the second part of the journey (75 km in 1 hour) and ignoring the first part.
- (b) 4.5 m² — The height ratio is 40 : 60, which simplifies to 2 : 3, so the larger bookcase is 1.5 times as tall as the smaller one. Areas scale with the square of the length scale factor, so the wood needed scales by 1.5² = 2.25. 2 × 2.25 = 4.5, so the larger bookcase needs 4.5 m² of wood. Giving 3 m² uses the length scale factor, 1.5, without squaring it (2 × 1.5 = 3). Giving 6.75 m² cubes the scale factor, 1.5³ = 3.375, as if wood coverage were a volume (2 × 3.375 = 6.75). Giving 2.25 m² is the squared scale factor on its own, without multiplying by the smaller bookcase's wood area of 2 m².
- (d) 26.6 — Find the constant multiplier — the mass of each metre of pipe: 12.6 ÷ 4.5 = 2.8, so the mass is always 2.8 times the length. For a length of 9.5 m, the mass is 9.5 × 2.8 = 26.6 kg. 17.6 comes from assuming an additive relationship instead of a multiplicative one — adding the increase in length (9.5 − 4.5 = 5) onto 12.6. 3.4 comes from using the multiplier the wrong way round (4.5 ÷ 12.6, rounded to 1 d.p.), then multiplying by 9.5. 12.6 comes from simply repeating the given mass, without applying the multiplier to the new length.
- (c) 500 — Pressure = force ÷ area = 250 ÷ 0.5 = 500 pascals. Getting 125 comes from multiplying the force by the area instead of dividing (250 × 0.5 = 125). Getting 249.5 comes from subtracting the area from the force instead of dividing. Getting 50 comes from misreading the area as 5 m² instead of 0.5 m² and dividing 250 by 5.
- (a) 4 hours — This is inverse proportion: more pumps take less time. Multiply the original numbers to find the total pump-hours needed: 2 × 10 = 20 pump-hours. Divide by the new number of pumps: 20 ÷ 5 = 4 hours. Working out 10 × 5 ÷ 2 = 25 hours treats it as direct proportion, as if more pumps needed more time. Stopping at 20 gives the total pump-hours, not the number of hours. Working out 10 − (5 − 2) = 7 hours subtracts the extra number of pumps straight from the number of hours, treating pumps and hours as the same kind of quantity. 5 pumps take 4 hours.
- (a) 2978 — A rise of 6% is a multiplier of 1.06, applied once for each year. After year 1: 2500 × 1.06 = 2650. After year 2: 2650 × 1.06 = 2809. After year 3: 2809 × 1.06 = 2977.54, which is 2978 to the nearest whole number. Multiplying by 1.18 in one go would be wrong, because the second and third years grow from larger numbers than the first.
- (b) 75 — The exchange rate is constant: k = 46 ÷ 40 = 1.15 euros per pound. For £65, the number of euros is 1.15 × 65 = 74.75, which rounds to 75 euros. Getting 74 comes from rounding 74.75 down instead of to the nearest whole number. Getting 57 comes from using the reciprocal rate (40 ÷ 46) instead of 46 ÷ 40. Getting 71 comes from adding the difference between 65 and 40 (25) onto 46 instead of using the proportional rate.
- (d) The cyclist's speed, in kilometres per hour — Method: on any straight-line graph the gradient is the change in the quantity on the vertical axis for each 1 unit of the quantity on the horizontal axis, so its meaning is read off the two axis labels. Working: the vertical axis is distance in kilometres and the horizontal axis is time in hours, so the gradient counts kilometres for each hour, and distance for each hour is speed. Answer: the cyclist's speed, in kilometres per hour. The distractors: 'the total distance the cyclist travels, in kilometres' reads the gradient as a value taken off the vertical axis, but a gradient is a rate and no end point of the journey has been given; 'the time the cyclist takes, in hours' names the horizontal axis, which is the quantity the gradient divides by rather than the gradient itself; 'the distance the cyclist travels in 18 hours' treats the 18 as a value of t, when 18 is the steepness of the line and not a point on it.
Build your own mix at the worksheet builder.