- (a) The hourly rate is £5 and the fixed fee is £7 — The gradient is (27 − 12) ÷ (4 − 1) = 15 ÷ 3 = £5, the hourly rate. Using the point (1, 12): 12 = 5 × 1 + fee, so the fee is 12 − 5 = £7. That gives 'The hourly rate is £5 and the fixed fee is £7'. Swapping the two figures gives the statement with £7 as the rate and £5 as the fee, which has them the wrong way round. Taking the C-value of the first point, £12, as the fixed fee ignores that 1 hour of hire is already included in that £12. Using 15, the change in C, as the hourly rate without dividing by the change in h (3 hours) gives the statement claiming a £15 hourly rate.
- (c) 27.1 cm — The model length is 20.6 ÷ 76 = 0.271052... metres. Converting to centimetres by multiplying by 100 gives 27.1052..., which rounds to 27.1 cm. Forgetting to convert metres to centimetres leaves the answer as 0.271052... metres, which rounds to 0.3 cm if the unit is simply relabelled. Multiplying by 1000 instead of 100 when converting metres to centimetres gives 271.052..., which rounds to 271.1 cm. Multiplying by 76 instead of dividing, 20.6 × 76 = 1565.6, uses the scale factor the wrong way round — that would be the real length if the model were 20.6 units long, not the other way round.
- (c) 27 : 64 — For similar solids, the ratio of volumes is the ratio of lengths cubed: 3³ : 4³ = 27 : 64. 3 : 4 comes from using the height ratio itself as the volume ratio, without cubing it at all. 9 : 16 comes from squaring each part instead of cubing (3² : 4²) — squaring is the rule for area, not volume. 27 : 4 comes from cubing only the first part of the ratio (3³ = 27), and leaving the second part uncubed.
- (d) £117.60 — Add the hours worked over the two days: 6 + 4.5 = 10.5 hours. Multiply by the rate of pay: 10.5 × £11.20 = £117.60. (£67.20 is Monday's pay only. £50.40 is Tuesday's pay only. £106.40 comes from mistakenly adding the hours as 6 + 3.5 = 9.5 — misreading Tuesday's 4.5 hours as 3.5 — and then multiplying by £11.20.)
- (c) 1.2 — Add the parts of the ratio: 6 + 1 = 7. Divide the total amount by the number of parts: 8.4 ÷ 7 = 1.2 litres, which is the value of one part and also the amount of syrup, since syrup is 1 part. (7.2 litres is the amount of water, using 6 parts instead of 1. 1.4 comes from dividing 8.4 by 6 — the water's part of the ratio — instead of dividing by the total number of parts, 7. 0.84 comes from dividing 8.4 by 10 instead of by 7.)
- (a) £102 — Method: find the value of one part of the ratio, then work out each group's share before comparing them. Working: the ratio 5:2 has 5 + 2 = 7 parts, so one part is £238 ÷ 7 = £34. Adults donate 5 × £34 = £170 and children donate 2 × £34 = £68, so adults donate £170 − £68 = £102 more than children. So the difference is £102. Distractor £68 is only the children's donation, without finding the difference. Distractor £170 is only the adults' donation, without finding the difference. Distractor £136 comes from doubling the children's donation instead of subtracting it from the adults' donation.
- (c) Map A, where the distance is 40 cm — 10 km = 1,000,000 cm. On Map A: 1000000 ÷ 25000 = 40 cm. On Map B: 1000000 ÷ 50000 = 20 cm. Since 40 cm is longer than 20 cm, the same real distance appears longer on Map A, the map with the smaller scale number. 'Map B, where the distance is 20 cm' has the correct working for Map B but names the wrong map as the one with the longer length. 'Map A, where the distance is 20 cm' correctly identifies Map A but pairs it with Map B's length. 'Map B, where the distance is 40 cm' correctly identifies Map A's length but attaches it to the wrong map.
- (a) 4 hours — This is inverse proportion: more pumps take less time. Multiply the original numbers to find the total pump-hours needed: 2 × 10 = 20 pump-hours. Divide by the new number of pumps: 20 ÷ 5 = 4 hours. Working out 10 × 5 ÷ 2 = 25 hours treats it as direct proportion, as if more pumps needed more time. Stopping at 20 gives the total pump-hours, not the number of hours. Working out 10 − (5 − 2) = 7 hours subtracts the extra number of pumps straight from the number of hours, treating pumps and hours as the same kind of quantity. 5 pumps take 4 hours.
- (d) 48 — Find the rate first: 18 ÷ 3 = 6 bottles per minute. Then apply it to the new time: 6 × 8 = 48 bottles. Working out 18 + (8 − 3) = 23 adds the extra 5 minutes onto the number of bottles instead of scaling proportionally. Working out 18 × 8 = 144 multiplies the given number of bottles by the new number of minutes without finding the rate first. Writing 18 keeps the count the same, not realising it must change with the time. In 8 minutes the machine fills 48 bottles.
- (d) 1.5 — Method: the length scale factor is the square root of the area scale factor, not the area scale factor itself. Working: the area scale factor is 45 ÷ 20 = 2.25, and the square root of 2.25 is 1.5. Answer: 1.5. Nadia's answer, 2.25, is the AREA scale factor — she never took the square root to get back to the length scale factor. 4.5 comes from doubling the area scale factor instead of taking its square root. 0.67 comes from taking the square root in the wrong direction, finding the scale factor from the larger rug to the smaller rug instead of the other way round.
- (d) 250 cm³/s — Method: first change litres per minute into cm³ per minute, then change per minute into per second. Working: 15 × 1000 = 15000 cm³ per minute, then 15000 ÷ 60 = 250 cm³ per second. So the tank fills at 250 cm³ per second. Distractor 15000 cm³/s comes from stopping after the first step and forgetting to change minutes into seconds. Distractor 900000 cm³/s comes from multiplying by 60 instead of dividing. Distractor 2500 cm³/s comes from dividing by 6 instead of 60.
- (a) 40 m² — A scale of 1 : 10 is a length scale factor of 10 from model to real. Areas scale with the square of the length scale factor: 10² = 100. 0.4 × 100 = 40, so the real staircase covers 40 m². Giving 4 m² uses the length scale factor, 10, without squaring it (0.4 × 10 = 4). Giving 0.04 m² divides by the scale factor instead of multiplying by its square (0.4 ÷ 10 = 0.04). Giving 400 m² cubes the scale factor, 10³ = 1000, as if area scaled like a volume (0.4 × 1000 = 400).
- (b) 1.00 litres — Total volume = 350 + 650 = 1000 cm³. Since 1000 cm³ = 1 litre, the smoothie is 1.00 litre. Using only the orange juice's 650 cm³ and converting that gives 0.65 litres, forgetting the mango juice entirely. Using only the mango juice's 350 cm³ gives 0.35 litres, forgetting the orange juice. Adding both volumes correctly to get 1000 cm³ but not converting to litres leaves the answer as 1000.00, which is the volume in the wrong unit.
- (a) Yes — the cost per metre is £1.50 each time — Direct proportion holds if the cost per metre is the same every time. Check each pair: 3.00 ÷ 2 = 1.50, 6.00 ÷ 4 = 1.50, and 10.50 ÷ 7 = 1.50. All three give the same rate, £1.50 per metre, so the data does show direct proportion. Saying only that the cost increases as the length increases is not enough on its own — many non-proportional relationships also increase, so this reason does not prove proportion. Misreading 10.50 ÷ 7 as 1.05 by misplacing the decimal point gives a false mismatch that is not actually there. Requiring every length to be a double of another confuses a special case (doubling) with the general test, which is that the rate itself stays constant. The data does show direct proportion, at £1.50 per metre.
- (a) £11.70 — Rate of pay = total pay ÷ hours worked, so £105.30 ÷ 9 = £11.70 per hour. Working out £105.30 − 9 = £96.30 subtracts the number of hours from the total pay instead of dividing. Working out £105.30 × 9 = £947.70 multiplies total pay by hours worked instead of dividing. Misplacing the decimal point in the correct answer gives £117.00 instead of £11.70. Maya's rate of pay is £11.70 per hour.