- (a) 12 m² — Real length = 8 × 50 = 400 cm = 4 m. Real width = 6 × 50 = 300 cm = 3 m. Real area = 4 × 3 = 12 m². Scaling the plan area (8 × 6 = 48 cm²) by 50 instead of by 50 squared gives 48 × 50 = 2400 cm² = 0.24 m² — area scales by the square of the length scale factor, not the scale factor itself. Multiplying the real dimensions in centimetres, 400 × 300 = 120 000, and calling the result 120 000 m² mistakes square centimetres for square metres. Converting only the length to metres and leaving the width as 6 (treating centimetres as metres), 4 × 6 = 24, gives 24 m², from a scaling that was never finished.
- (b) 75 — The exchange rate is constant: k = 46 ÷ 40 = 1.15 euros per pound. For £65, the number of euros is 1.15 × 65 = 74.75, which rounds to 75 euros. Getting 74 comes from rounding 74.75 down instead of to the nearest whole number. Getting 57 comes from using the reciprocal rate (40 ÷ 46) instead of 46 ÷ 40. Getting 71 comes from adding the difference between 65 and 40 (25) onto 46 instead of using the proportional rate.
- (a) 5/12 — Work out the distance still to travel: 372 − 217 = 155 miles. Form the fraction 155/372; both numbers share a factor of 31, so 155 ÷ 31 = 5 and 372 ÷ 31 = 12, giving 5/12. 7/12 comes from writing the distance already travelled as the fraction of the journey (217/372 = 7/12), instead of the distance still to travel. 145/372 comes from miscalculating 372 − 217 as 145 instead of 155. 5/7 comes from comparing the remaining distance with the distance already travelled (155/217 = 5/7), instead of with the total journey.
- (c) 30 km — First convert 1 hour 15 minutes to hours: 15 minutes is a quarter of an hour, so the time is 1.25 hours. Then multiply by the speed: 24 × 1.25 = 30 km. Reading 15 minutes as 0.15 hours (writing the minutes after the decimal point instead of as a fraction of 60) gives 24 × 1.15 = 27.6 km. Working out 24 × 75 = 1800 multiplies by the number of minutes instead of converting to hours first. Working out 24 ÷ 1.25 = 19.2 divides by the time instead of multiplying. The cyclist travels 30 km.
- (c) 120 km/h — Method: for a fixed distance the average speed multiplied by the time is constant, and that constant is the distance, so divide the distance by the new time. Working: speed × time = 240, so in 2 hours the speed needed is 240 ÷ 2 = 120 km/h. Answer: 120 km/h. The distractors: 80 km/h is the average speed of the original journey, 240 ÷ 3, which answers for the 3-hour timing rather than the 2-hour one; 160 km/h comes from halving the 3 hours to 1.5 hours and working out 240 ÷ 1.5, instead of using the 2 hours the question gives; 480 km/h comes from multiplying the distance by the 2 hours rather than dividing by it.
- (d) 8 — The product of price and number of tickets is constant: k = 4 × 12 = 48. At £6 per ticket, the number of tickets is 48 ÷ 6 = 8. Getting 18 comes from treating price and tickets as directly proportional and working out 12 × 6 ÷ 4 instead of dividing k by the new price. Getting 12 assumes the number of tickets does not change when the price changes. Getting 6 comes from writing down the new price instead of working out the number of tickets.
- (c) 88 km/h — Multiply the speed in mph by the conversion factor: 55 × 1.6 = 88 km/h. Dividing by 1.6 instead of multiplying gives 55 ÷ 1.6 ≈ 34.38 km/h, going the wrong way between the units. Adding the conversion factor instead of multiplying gives 55 + 1.6 = 56.6 km/h, treating the factor as an amount rather than a multiplier. Multiplying by 0.6 instead of 1.6 gives 55 × 0.6 = 33 km/h, using only part of the conversion factor. 55 mph is equal to 88 km/h.
- (c) A straight line through the origin, rising from left to right — Two quantities are in direct proportion when one is a constant multiple of the other, so their graph is a straight line through the origin: when one quantity is 0 the other is 0 as well, and doubling one doubles the other. A straight line crossing the vertical axis at 5 has a fixed amount added on, so when the horizontal quantity is 0 the vertical quantity is 5, not 0 — a straight line on its own is not enough for direct proportion. A curve that falls steeply and then levels off without touching either axis shows inverse proportion: one quantity grows as the other shrinks, and their product stays the same. A horizontal line at a height of 3 shows a quantity that does not change at all as the other one grows, so it is not proportional to it.
- (d) 90 cm — Method: scale each dimension by the scale factor, then find the perimeter. Working: model height = 240 ÷ 8 = 30 cm; model width = 120 ÷ 8 = 15 cm. Perimeter = 2 × (30 + 15) = 90 cm. Wrong options: 11.25 cm comes from squaring the scale factor as if finding an area (720 ÷ 64); 510 cm comes from scaling only one dimension and leaving the other at full size; 720 cm comes from finding the real perimeter (2 × (240 + 120)) but forgetting to scale it down at all.
- (c) 1.05 litres — Method: find the value of one part of the ratio from the total volume, then find the share for pineapple juice. Working: the ratio 5:3:2 has 5 + 3 + 2 = 10 parts, so one part is 3.5 ÷ 10 = 0.35 litres, and the pineapple juice is 3 × 0.35 = 1.05 litres. So 1.05 litres of pineapple juice is needed. Distractor 1.75 litres is the volume of orange juice, not pineapple juice. Distractor 0.7 litres is the volume of lemonade, not pineapple juice. Distractor 0.35 litres is the value of one part, found correctly but never multiplied by 3.
- (d) £30.00 — The gradient is (130 − 70) ÷ (5 − 2) = 60 ÷ 3 = £20 per hour. Using the point (2, 70): the cost for 2 hours at £20 per hour is 20 × 2 = £40, so the call-out fee is 70 − 40 = £30. Taking the C-value of the first point as the fee without subtracting the hourly cost gives £70.00 — but that point already includes 2 hours of the hourly rate. Using the gradient itself as the fee, £20.00, confuses the rate per hour with the fixed charge. Subtracting 20 × 3 = 60 instead of 20 × 2 = 40 (using the wrong h-value) gives 70 − 60 = £10.00.
- (c) 448.00 US dollars — Method: multiply the amount in pounds by the exchange rate. Working: £350 × 1.28 = 448.00 US dollars. Wrong options: 273.44 US dollars comes from dividing by the rate instead of multiplying (350 ÷ 1.28); 351.28 US dollars comes from adding the rate to the amount instead of multiplying; 4,480.00 US dollars comes from a decimal-point slip, using 12.8 instead of 1.28.
- (a) £7.80 — Rate of pay = total pay ÷ number of hours. £58.50 ÷ 7.5 = £7.80 per hour. £438.75 comes from multiplying the pay by the hours instead of dividing (£58.50 × 7.5). £0.13 comes from dividing the hours by the pay instead of the pay by the hours (7.5 ÷ 58.50). £51.00 comes from subtracting the hours from the pay (£58.50 − 7.5) instead of dividing.
- (c) 1 : 16 — Work out each area before comparing. Square P has area 3 × 3 = 9 cm². Square Q has area 12 × 12 = 144 cm². The ratio of the areas is 9 : 144, and both parts divide by 9: 9 ÷ 9 = 1 and 144 ÷ 9 = 16, giving 1 : 16. Notice that the sides are in the ratio 1 : 4, and the areas are in the ratio of the squares of those parts, which is what always happens when a length is scaled. Stopping at 1 : 4 would compare the sides and never the areas, and cubing the parts to reach 1 : 64 is the rule for volumes rather than for areas. The order matters too: the question names square P first, so its area must be the first part of the ratio.
- (a) No — the cost per metre differs: £2.50/m vs £2.20/m — Method: divide cost by length for each pair and compare the unit rates. Working: £7.50 ÷ 3 = £2.50 per m; £11.00 ÷ 5 = £2.20 per m. The rates are different, so this is NOT direct proportion. Wrong options: 'Yes — both amounts increase' wrongly assumes any increasing relationship is proportional; 'No — because 5 m costs more in total' judges by total cost rather than the rate per metre, which is not valid reasoning on its own; 'Yes — the cost per metre is £2.50 in both cases' miscalculates the second rate (11.00 ÷ 5 is £2.20, not £2.50).