- (d) 648 kg — Method: to estimate a total from a sample, multiply the sample's mean by the number of items in the whole population, then check the units the question asks for. Working: 32.4 g × 20,000 = 648,000 g. Converting to kilograms, 648,000 ÷ 1,000 = 648 kg. This is only an estimate, not an exact total, because it assumes every one of the 20,000 packets has exactly the sample mean mass, when in reality individual packets vary above and below it. Giving 1.62 kg multiplies the mean by 50, the SAMPLE size, instead of by 20,000, the number of packets actually made that day — this finds the total mass of the 50 sampled packets, not the day's production. Giving 32.4 kg treats the sample mean itself, in grams, as if it already were the day's total mass in kilograms, skipping the scaling up altogether. Giving 648,000 kg correctly scales the mean up to the whole day's production but never converts the answer from grams to kilograms, leaving it 1,000 times too large. Always scale a sample's mean up by the SIZE OF THE WHOLE POPULATION, and always finish by checking the units the question asks for.
- (b) Interpolation — The salary is being estimated for a value of x between 1 and 15, which is inside the range of x-values that were actually plotted, so this is interpolation. Extrapolation would apply if the estimate used a value of x below 1 or above 15, outside the plotted range. Correlation describes the relationship between the two variables, not the reliability of an estimate, and causation describes one variable actually causing a change in the other, which is a different idea altogether — neither is the word being asked for here.
- (d) 38, and fairly confident, as 12 °C is inside the range — Method: substitute the forecast temperature into the equation of the line of best fit, then judge the prediction by where that temperature sits among the data the line was drawn from. Working: putting x = 12 into y = −3x + 74 gives −3 × 12 + 74 = 38, so the line predicts 38 hot chocolates. The recorded temperatures run from 4 °C to 18 °C, and 12 °C lies inside that interval, so this is interpolation, the safer kind of prediction. Answer: 38, and fairly confident, as 12 °C is inside the range; the owner should still expect the true figure to differ a little, since the points only lie near the line and not on it. The distractors: being completely certain treats a line of best fit as a rule that fixes each day's sales, when it describes a trend that individual days depart from; saying 12 °C is outside the range misreads the interval 4 °C to 18 °C, and the wrong warning would be attached to a sound prediction; 110 comes from −3 × 12 being taken as +36, giving 36 + 74 = 110, which loses the negative gradient and so predicts that a warm day sells more hot chocolate than a cold one.
- (a) Drawing 60 names at random from a list of all 1200 pupils — Method: a sample is random when every member of the population has the same chance of being chosen and nobody, including the pupils themselves, can influence who ends up in it; test each method against that. Working: drawing names from a list of all 1200 pupils gives each pupil the same chance, 60 out of 1200, whatever their year group, class or opinion, so the method is random. Answer: drawing 60 names at random from a list of all 1200 pupils. The distractors: asking the pupils who volunteer is self-selection, and the pupils with the strongest views volunteer first, so they decide the sample; asking the pupils nearest the door is convenience sampling, which reaches only those who happen to be in one place at one time; asking two Year 10 classes samples a cluster, so every pupil in the other year groups has no chance of being chosen at all.
- (a) Chloe's marks are far more spread out than Ben's — Method: a mean reports where a set of values sits, and two sets can sit in the same place while behaving quite differently, so a measure of spread has to be worked out as well. Working: Ben's marks add to 62 + 64 + 65 + 66 + 68 = 325 and 325 ÷ 5 = 65; Chloe's add to 40 + 52 + 65 + 78 + 90 = 325 and 325 ÷ 5 = 65, so the two means agree, as the question says. The ranges do not: Ben's is 68 − 62 = 6 marks, while Chloe's is 90 − 40 = 50 marks. Ben's five marks all sit within 3 marks of 65; Chloe's lowest is 25 marks below it and her highest 25 marks above it. Answer: Chloe's marks are far more spread out than Ben's, which is exactly what the mean cannot show. The distractors: saying Ben's marks are more spread out comes from subtracting in the order the values are written, 62 − 68 = −6 against 40 − 90 = −50, and then reading −6 as the larger spread; saying Chloe scored far more marks in total assumes a wider set of marks must add to more, when both totals are 325; saying the two sets vary by the same amount assumes that equal means force equal spread, when the two ranges are 6 and 50.
- (d) Full-time workers, as most are at work at that time — Method: a sample is biased when the method of contact makes part of the population much less likely to be reached, so test each group against where its members actually are between 10 am and 2 pm on a weekday, and test each stated reason against the facts. Working: those hours are the middle of the working day, so people in full-time employment are at work and not beside a landline telephone, while people who are retired and people who are unemployed are far more likely to be at home and are reached at the usual rate; the method therefore collects far fewer replies from full-time workers than their share of the adult population the council is consulting. Answer: full-time workers, as most are at work at that time. The distractors: the reply naming retired people rests on the false claim that most retired people are at work in the daytime, when in fact a daytime call reaches them more easily than anyone; the reply naming unemployed people rests on the false claim that they are out during the day, when they too are among the easiest people to reach by a daytime call; the reply naming children rests on the false claim that children are at home at 11 am on a Tuesday, when they are at school and so are not reached by the call at all, and school-age children are in any case not the adults whose views the council is collecting.
- (b) A line graph — Sales recorded at the end of each of the twelve months are time series data, and a line graph is the chart built to show how a value changes over time, with the points usually joined in order. A pie chart is for showing categorical data as shares of a whole, not a trend over time. A pictogram shows a frequency for separate categories using symbols, not a continuous trend. A scatter graph is for comparing two different variables against each other, not one variable over time.
- (b) On average a plant grew 1.5 cm taller for each extra day — Method: in the equation of a line, the number multiplying x is the gradient, and a gradient states the change in y produced by an increase of 1 in x, read in the units of the two axes. Working: here x is measured in days and y in centimetres, so the gradient 1.5 carries the units centimetres per day. Testing it on the line, 5 days gives 1.5 × 5 + 4 = 11.5 cm and 6 days gives 1.5 × 6 + 4 = 13 cm, a rise of 1.5 cm for the one extra day. Answer: on average a plant grew 1.5 cm taller for each extra day of watering. The distractors: 1.5 cm as the height before any watering is the value of y when x is 0, which is the other number in the equation, 4 cm, so this swaps the gradient and the intercept; 1.5 cm as the gap between the tallest and the shortest plant reads the gradient as a range, when a range is a difference between two of the 16 plants and a gradient is a rate; 1.5 days for each extra centimetre inverts the rate, dividing days by centimetres instead of centimetres by days, and the line gives 1 cm of growth in two thirds of a day.
- (d) 1100 — Method: to combine two samples of different sizes, add the faulty counts together and add the sample sizes together before scaling up, rather than treating the two samples separately. Working: the combined sample found 34 + 21 = 55 scratched cases out of 100 + 50 = 150 cases checked, a proportion of 55 ÷ 150. Applying that proportion to the week's production of 3,000 gives an estimate of 55 ÷ 150 × 3000 = 1100 scratched cases. Averaging the two shifts' proportions instead of combining their totals, (34 ÷ 100 + 21 ÷ 50) ÷ 2 = 0.38, gives 0.38 × 3000 = 1140 — this treats the two samples as equally weighted even though Shift A checked twice as many cases as Shift B. Using only Shift A's sample, 34 ÷ 100 × 3000 = 1020, ignores Shift B's cases completely. Using only Shift B's sample, 21 ÷ 50 × 3000 = 1260, ignores Shift A's cases completely. When two samples are different sizes, combine their totals before finding the proportion — do not average the two proportions, and do not use only one shift's sample.
- (c) No — median £505 at A vs £510 at B. — Branch A's seven wages in order are £480, £495, £500, £505, £510, £515 and £1,200, so the median, the 4th value, is £505. Branch B's in order are £480, £490, £500, £510, £520, £530 and £540, so the median is £510. Since £505 is lower than £510, the median wage is not higher at Branch A, so the claim is not fairly supported. Choosing 'Yes — mean £600.71 at A vs £510 at B' uses the mean: 480 + 495 + 500 + 505 + 510 + 515 + 1200 = 4205, and 4205 ÷ 7 = 600.71, a figure pulled upward by the £1,200 outlier that does not represent a typical wage. Choosing 'Yes — median £515 at A vs £510 at B' miscounts the middle position, taking the 6th wage, £515, instead of the correct 4th value, £505. Choosing 'Yes — highest wage £1,200 at A vs £540 at B' compares the highest wage at each branch rather than a measure of the typical, or average, wage.
- (b) £11.00 — 1.5 × 6 = 9, and 9 + 2 = 11, so the estimated cost is £11.00. Choosing £9.00 stops after 1.5 × 6 = 9 and forgets to add the £2. Choosing £12.00 adds the mass and the constant first and then multiplies: 6 + 2 = 8, and 8 × 1.5 = 12.00. Choosing £13.50 swaps the gradient and the intercept, using y = 2x + 1.5 instead: 2 × 6 = 12, and 12 + 1.5 = 13.50.
- (d) Testing destroys bulbs, so testing all leaves none to sell. — Method: testing every item in a population instead of a sample is a census — sensible only when testing does not use up or destroy what is being tested. Working: here, testing a bulb to find its lifespan destroys it, so testing all 50,000 bulbs would leave nothing left to sell — a sample lets the company estimate the typical lifespan without destroying its whole stock. Extra electricity used in testing is not the real reason a census is avoided here — it is the destruction of the product that matters. Saying a sample is always more accurate than a full census is the wrong way round: a census, if it could be carried out, gives the exact figure for the whole population — it is testing being destructive, not a lack of accuracy, that rules it out here. There is no law against testing every item a company makes — nothing in the question suggests that. When testing destroys the item being tested, sampling is necessary, not just convenient.
- (a) Negative correlation — As the age of the car increases, the points fall towards a lower value, so the value decreases as the age increases. This falling pattern is a negative correlation. A positive correlation would show the points rising together instead. No correlation would apply only if the points showed no pattern at all, and correlation is not the same as causation — strong causation is not a type of correlation.
- (c) A line of best fit — Method: the straight line drawn on a scatter graph is named from the job it does — it is chosen so that it follows the whole set of points as closely as possible. Working: the line passes through the middle of the points, with roughly as many points above it as below it, and it need not pass through any of the plotted points at all; the name given to the straight line chosen in that way is a line of best fit. Answer: a line of best fit. The distractors: a line of symmetry comes from confusing a trend with symmetry, which is a property of a shape rather than of a set of data; a horizontal line through the mean comes from thinking the trend is shown by an average, when a horizontal line would say that the vertical quantity does not change and so show no correlation; a line joining the first and last points comes from thinking the line must join the two extreme points, which lets two points decide a trend that all of the points should share in.
- (d) The mode, because colours cannot be added or ordered — Method: an average can only be used on data that supports the operation it needs. A mean needs the values to be added and divided, a median needs them to be placed in order, and a range needs one value to be taken away from another; a mode needs only counting, so it is the average available when the data are categories rather than numbers. Working: the data collected here are colours, silver, black, blue and red. The numbers 74, 52, 40 and 34 count the cars of each colour, they do not measure them, and 74 + 52 + 40 + 34 = 200 simply returns the size of the survey. No colour can be added to another, and there is no order that puts blue before red, so of the four averages only the one found by counting survives. Answer: the mode, because colours cannot be added or ordered, and the mode is silver. The distractors: the mean is said to use all 200 colours, and a mean of the four frequencies, 200 ÷ 4 = 50, is a number of cars rather than a colour, so it describes nothing about a typical car; the median is said to put the colours in order, but ordering the frequencies 34, 40, 52, 74 orders the counts, not the colours, and gives 46, again a number of cars; the range is not an average at all, and 74 − 34 = 40 measures the gap between the commonest and rarest counts, which is a measure of spread.