- 1.A regular hexagon has sides of length (x + 2) cm. Write down an expression, in terms of x, for the perimeter of the hexagon.
- 2.The line y = 2x + 7 and the circle x² + y² = 4 are given. By finding the discriminant of the resulting quadratic, without solving it fully, work out how many points the line and the circle intersect at.y = 2x + 7
- 3.A photo printing service has two adverts for its price. Advert A: cost in pounds = 3(2n + 4) for n photos. Advert B: cost in pounds = 6n + 12. A customer says the two adverts always charge the same amount. Is the customer correct?
- 4.The trapezium rule is used to estimate the area under a curve between x = 2 and x = 6. The curve is concave up (it curves upwards, like the inside of a bowl) throughout this interval. Which statement about the estimate is correct?
- 5.A car park charges by the hour. Parking for 1 hour costs £5, 2 hours costs £9, 3 hours costs £13 and 4 hours costs £17, with the cost increasing by the same amount for each extra hour. Work out an expression, in terms of n, for the cost, in pounds, of parking for n hours.
- 6.A company's cost, in £, for producing x items is shown on a graph. The tangent to the curve at x = 50 passes through (30, 400) and (70, 800). Interpret the gradient of this tangent in the context of the company's costs.
- 7.Work out the value of 4p² − 3 when p = 2.5
- 8.A taxi fare in pounds is given by F = 2.50 + 1.20m, where m is the number of miles travelled. Sam takes a taxi for a journey of 6 miles. Work out the fare.
- 9.A tree is 2 metres tall. Each year its height increases by 10% of its height at the start of that year. Work out the height of the tree after 3 years, giving your answer to 1 decimal place.
- 10.A rectangular vegetable plot has an area of 30 m² and its length is 4 m greater than its width, x metres. This gives x² + 4x − 30 = 0, which can be solved using the iterative formula xₙ₊₁ = √(30 − 4xₙ). The starting value is x₀ = 3, so x₁ is the value after the formula has been used once. Work out x₃, and use it to find an estimate for the length of the plot, giving your answer correct to 1 decimal place.
- 11.A ball is thrown in the air. Its height, h metres, above the ground after t seconds is given in this table: when t = 0, h = 0; when t = 1, h = 15; when t = 2, h = 20; when t = 3, h = 15; when t = 4, h = 0. Use the table to find the two times, in seconds, at which the ball is at ground level.
- 12.The formula for the energy stored in a stretched spring is E = (1/2)kx², where E is in joules, k is the spring constant in N/m and x is the extension in m. A spring with a spring constant of 40 N/m is stretched so that its extension is 0.3 m. Work out the energy stored in the spring.
- 13.Solve the inequality 2(3x − 1) ≥ 4x + 8.
- 14.A distance-time graph is a straight line from (0, 0) to (4, 100), where time is in hours and distance is in kilometres. Work out the gradient of the line.
- 15.A plumber charges a call-out fee of £30 plus £25 per hour worked. Work out the total charge for a job that takes 3 hours.
Answer key
- (a) 6x + 12 — A regular hexagon has 6 equal sides, so the perimeter is 6(x + 2) = 6x + 12. A candidate who multiplies only the x-term by 6 and forgets to multiply the 2 gets 6x + 2. A candidate who multiplies only the number term by 6 and forgets to multiply the x gets x + 12. A candidate who adds 6 and 2 to make a single coefficient of x instead of expanding the brackets gets 8x.
- (a) 0 — the line does not intersect the circle — Substitute y = 2x + 7 into x² + y² = 4: x² + (2x + 7)² = 4, which expands to x² + 4x² + 28x + 49 = 4, giving 5x² + 28x + 45 = 0. The discriminant is b² − 4ac = 28² − 4 × 5 × 45. Since 28² = 784 and 4 × 5 × 45 = 900, the discriminant is 784 − 900 = −116. Since the discriminant is negative, the quadratic has no real solutions, so the line does not meet the circle at all: 0 intersection points. Distractor routes: "1 — the line is a tangent" confuses a negative discriminant with a zero one; a discriminant of exactly zero gives one point, a tangent, but −116 is not zero. "2 — the line crosses the circle at two points" assumes a positive discriminant without actually working it out. "It cannot be found without solving the quadratic" is the whole point the discriminant exists to avoid — its sign alone, without finding x, tells you the number of real solutions.
- (a) They always charge the same, since 3(2n + 4) = 6n + 12. — Expand Advert A's formula by multiplying both terms inside the bracket by 3: 3 × 2n = 6n, and 3 × 4 = 12, giving 3(2n + 4) = 6n + 12, which is identical to Advert B's formula — so the two adverts always charge the same amount, whatever n is. Getting 6n + 4 comes from multiplying the 2n by 3 but leaving the 4 unmultiplied. Getting 2n + 7 comes from adding 3 to the bracket instead of multiplying by it. Saying it depends on n avoids expanding the bracket at all — once expanded, both formulas are identical for every value of n, so the cost can be compared directly.
- (a) Overestimates — trapezium edges lie above the curve. — For a concave-up curve, each chord connecting two points on the curve lies ABOVE the curve between those points, because the curve bends away from the chord underneath it. The trapezium rule uses these chords as the top edges of each trapezium, so the trapeziums cover a larger region than the true area under the curve — the estimate is an overestimate. Saying it underestimates because the edges lie below the curve gets the direction backwards: for a concave-up curve the edges lie above, not below. Saying it overestimates 'because more strips always increase it' gives the right verdict for the wrong reason — using MORE, narrower strips makes a trapezium estimate more accurate and brings it closer to the true area, it does not simply increase the total. Saying the estimate is exact ignores that straight edges cannot follow a curved line perfectly; there is always a gap between the chord and the curve on a bend, which is exactly what makes the rule an estimate rather than an exact calculation.
- (a) 4n + 1 — Method: find the increase in cost per hour, then find the constant by adjusting the 1-hour cost. Working: the cost goes up by £4 for each extra hour (9 − 5 = 4), so the coefficient of n is 4. The constant is the 1-hour cost minus the common difference: 5 − 4 = 1. Answer: the nth term is 4n + 1. 4n + 5 comes from using the 1-hour cost, 5, as the constant without subtracting the common difference. 4n − 3 comes from a slip in working out the constant, subtracting the common difference twice (5 − 4 − 4 = −3) instead of once. n + 4 comes from swapping the hourly increase and the constant.
- (d) The cost increases by about £10 per extra item — Gradient = change in cost ÷ change in items = (800 − 400) ÷ (70 − 30) = 400 ÷ 40 = 10. The units of the gradient are £ per item, so the cost is increasing by about £10 for every extra item produced, near x = 50. Subtracting in the wrong order, (400 − 800) ÷ (70 − 30) = −10, gives the right size but the wrong sign — check which point comes first each time. Leaving out the division by 40 gives £400 per item; dividing the wrong way round, 40 ÷ 400 = 0.1, gives £0.10 per item.
- (c) 22 — p² means p × p. Substitute p = 2.5: p² = 6.25, so 4p² = 4 × 6.25 = 25, and 25 − 3 = 22. 97 comes from squaring 4p together instead of just p, (4 × 2.5)² − 3 = 10² − 3 = 97. 7 comes from using p instead of p², 4 × 2.5 − 3. 1 comes from squaring the 3 instead of the p, 4 × 2.5 − 3².
- (c) £9.70 — F = 2.50 + 1.20 × 6 = 2.50 + 7.20 = £9.70. £7.20 comes from forgetting to add the £2.50 fixed charge. £10.20 comes from adding the 2.50 to the number of miles before multiplying by 1.20, 1.20 × (6 + 2.50). £22.20 comes from adding the fixed charge and the rate together first and then multiplying by the miles, (2.50 + 1.20) × 6.
- (d) 2.7 — The height after 3 years of 10% compound growth is 2 × 1.1³ = 2.662 m, which rounds to 2.7 m. A candidate who adds 10% of the original height (0.2 m) in each of the 3 years, instead of compounding on the new height each time, would reach 2 + 3×0.2 = 2.6 m. A candidate who compounds for only 2 years would reach 2 × 1.1² = 2.42 m, rounding to 2.4 m. A candidate who compounds for 4 years instead of 3 would reach 2 × 1.1⁴ = 2.928 m, rounding to 2.9 m.
- (a) 7.9 m — Method: the iteration converges on the width of the plot, so run the formula three times from the starting value and then add 4 m, because the length is 4 m greater than the width. Working: x₁ = √(30 − 4 × 3) = √18 = 4.24264…; x₂ = √(30 − 4 × 4.24264…) = √13.02943… = 3.60963…; x₃ = √(30 − 4 × 3.60963…) = √15.56147… = 3.94480…. The estimate for the length is 3.94480… + 4 = 7.94480…, which is 7.9 m correct to 1 decimal place. Answer: 7.9 m. The iteration is still oscillating at x₃, so this is the estimate that three uses of the formula give, not a settled value. The distractors: 3.9 m is x₃ itself, the width, given by a candidate who runs the iteration correctly and then stops before the step the question actually asks for; 7.6 m uses x₂ in place of x₃, one use of the formula short, and then adds the 4 m correctly; 15.8 m multiplies the width by 4 instead of adding 4 m to it, reading greater than as a multiplier.
- (a) t = 0 or t = 4 — The ball is at ground level exactly when h = 0. From the table, h = 0 at t = 0 and at t = 4, so those are the two times. Distractor origins: t = 1 or t = 3 picks the times with equal (but non-zero) height instead of ground level; t = 2 picks the time of maximum height instead of ground level; t = 0 finds only the starting time and misses the second one.
- (a) 1.8 — E = (1/2)kx² = 0.5 × 40 × 0.3² = 0.5 × 40 × 0.09 = 1.8 joules. 3.6 comes from forgetting the (1/2) at the front, 40 × 0.09. 72 comes from squaring kx together instead of squaring only x, 0.5 × (40 × 0.3)² = 0.5 × 144 = 72. 6 comes from using x instead of x², 0.5 × 40 × 0.3.
- (b) x ≥ 5 — Expand the bracket: 2(3x − 1) = 6x − 2, so the inequality is 6x − 2 ≥ 4x + 8. Subtract 4x from both sides and add 2 to both sides: 2x ≥ 10. Divide both sides by 2: x ≥ 5. A candidate who only multiplies the 3x by 2 and forgets to multiply the −1 gets 6x − 1 ≥ 4x + 8, leading to x ≥ 4.5. A candidate who adds 4x instead of subtracting it gets 10x ≥ 10, leading to x ≥ 1. A candidate who multiplies by 2 instead of dividing gets x ≥ 20.
- (a) 25 — Gradient = change in y ÷ change in x = (100 − 0) ÷ (4 − 0) = 100 ÷ 4 = 25. Dividing time by distance instead of distance by time gives 0.04; multiplying the two values instead of dividing gives 400; stopping at the change in distance, 100, forgets to divide by the change in time.
- (b) £105 — The hourly charge is 25 × 3 = £75. Adding the call-out fee: £75 + £30 = £105. A candidate who forgets the call-out fee gives just the hourly charge, £75. A candidate who adds the call-out fee to the hourly rate before multiplying by the hours, (30 + 25) × 3, gets £165. A candidate who multiplies the call-out fee by the number of hours instead of the hourly rate, 30 × 3, gets £90.