Printable · GCSE Higher · ages 14-16
Algebra worksheet — GCSE Higher
Fifteen questions across the algebra statements at Higher tier. Choose the non-calculator filter to rehearse Paper 1, which counts for a third of the marks.
Non-calculator
Algebra worksheet — GCSE Higher
MathsUKwww.geekhero.co.uk
- 1.Solve (2x + 1)/3 = 5
- 2.A gardener charges a fixed fee of £15 plus £8 for each hour worked. The total charge, £T, for a job lasting h hours is given by T = 15 + 8h. Work out the charge for a job lasting 4 hours, and identify what kind of statement T = 15 + 8h is.
- 3.A geometric sequence begins 80, 40, 20, 10, ... Work out the next term in the sequence.
- 4.A graph has equation y = −2x² + 5. Which statement about its shape is correct?y = -2x² + 5
- 5.Line L has equation y = 3x + 1. Which of these lines is perpendicular to L?y = 3x + 1
- 6.A car park charges by the hour. Parking for 1 hour costs £5, 2 hours costs £9, 3 hours costs £13 and 4 hours costs £17, with the cost increasing by the same amount for each extra hour. Work out an expression, in terms of n, for the cost, in pounds, of parking for n hours.
- 7.Simplify (2x² + 7x + 3) ÷ (x² − 9), giving your answer as a single fraction.
- 8.The diagram shows the graph of a quadratic function. Which equation could it represent?
- 9.Work out the value of 2(x + 2) when x = −5
- 10.The curve y = x² − 3x. Use the chord between x = 1 and x = 4 to estimate the gradient of the curve at x = 2.5.y = x² − 3x
- 11.A regular hexagon has sides of length (x + 2) cm. Write down an expression, in terms of x, for the perimeter of the hexagon.
- 12.A car passes the 15 km marker on a road and passes the 195 km marker 3 hours later. Work out the gradient of the distance-time graph, that is the rate of change of distance with time.
- 13.The perimeter of a rectangle is given by the formula P = 2(l + w), where l is the length and w is the width. A rectangular garden has a perimeter of 46 m and a length of 14 m. Rearrange the formula to make w the subject, then work out the width of the garden.
- 14.A tank already contains some water and is then filled at a constant rate. After 2 minutes it contains 50 litres in total; after 7 minutes it contains 150 litres in total. Work out the rate at which water is added, in litres per minute.
- 15.A ball's height, h metres, t seconds after being thrown follows h = (t − 1)(9 − t). Given that the ball is at ground level at t = 1 and t = 9, work out at what time t the ball reaches its maximum height, using symmetry.
Answer key
- (a) 7 — Method: multiply both sides by 3 to clear the fraction, then solve the resulting equation. Working: 2x + 1 = 5 × 3 = 15. Subtract 1: 2x = 14. Divide by 2: x = 7. Answer: 7. 2 comes from ignoring the denominator altogether, treating the equation as 2x + 1 = 5 without multiplying by 3 first. 8 comes from a sign error, adding 1 to 15 instead of subtracting it, giving 2x = 16. 14 comes from correctly reaching 2x = 14 but stopping there, without dividing by 2 to find x.
- (b) £47, and T=15+8h is a formula (relates T and h). — The charge is £15 fixed plus £8 for each hour: T=15+8h, so for h=4, T=15+8×4=15+32=47. Because T=15+8h relates two different quantities, the total charge T and the number of hours h, it is a formula, not an equation — an equation is solved for one particular value of an unknown, but this relationship holds for every value of h a job might last. A candidate who forgets to include the fixed £15 fee would compute only 8×4=32. A candidate who adds the three numbers in the formula together instead of multiplying the hourly rate by the number of hours would compute 15+8+4=27. A candidate who correctly finds the charge but mistakes the formula for an equation, treating it as something to be solved for one specific value of h rather than a general relationship between T and h, would pick the correct charge with the wrong classification.
- (d) 5 — Each term is found by multiplying the previous term by the common ratio, 0.5: 80, 40, 20, 10, and the next term is 10 × 0.5 = 5. A candidate who instead subtracts the same amount each time (repeating the last difference of 10) would reach 10 − 10 = 0. A candidate who divides by 4 instead of by 2 would reach 10 ÷ 4 = 2.5. A candidate who multiplies by 2 instead of dividing (reversing the direction of the sequence) would reach 10 × 2 = 20.
- (d) It is n-shaped, since the x² coefficient is negative. — The coefficient of x² is −2, which is negative, so the quadratic curve opens downward — shaped like an n, with a maximum turning point. Saying it is U-shaped focuses only on x² being non-negative and ignores that the −2 in front of it flips the whole curve to open downward. Saying it is a straight line confuses having a constant term with being linear — any equation with an x² term is a curve, not a line. Saying it repeatedly rises and falls like a wave describes a trigonometric graph such as y = sin x, not a quadratic.
- (b) y = −(1/3)x + 2 — Method: two lines are perpendicular when the product of their gradients is −1, so the gradient of a line perpendicular to one of gradient m is the negative reciprocal, −1 divided by m. Working: reading m from y = 3x + 1 gives a gradient of 3, so the perpendicular gradient is −1 ÷ 3 = −1/3, and the line carrying that gradient is y = −(1/3)x + 2; the check 3 × (−1/3) = −1 confirms it. Answer: y = −(1/3)x + 2. The distractors: y = 3x − 4 comes from using an equal gradient, which is the test for parallel lines rather than perpendicular ones; y = (1/3)x + 2 comes from turning the gradient upside down but leaving out the change of sign, giving a product of 1 instead of −1; y = −3x + 2 comes from changing the sign of the gradient without turning it upside down, giving a product of −9.
- (a) 4n + 1 — Method: find the increase in cost per hour, then find the constant by adjusting the 1-hour cost. Working: the cost goes up by £4 for each extra hour (9 − 5 = 4), so the coefficient of n is 4. The constant is the 1-hour cost minus the common difference: 5 − 4 = 1. Answer: the nth term is 4n + 1. 4n + 5 comes from using the 1-hour cost, 5, as the constant without subtracting the common difference. 4n − 3 comes from a slip in working out the constant, subtracting the common difference twice (5 − 4 − 4 = −3) instead of once. n + 4 comes from swapping the hourly increase and the constant.
- (b) (2x + 1)/(x − 3) — Factorise both the numerator and the denominator before you cancel anything. The numerator 2x² + 7x + 3 factorises to (2x + 1)(x + 3), and the denominator x² − 9 is a difference of two squares, factorising to (x − 3)(x + 3). The (x + 3) factor is common to both, so it cancels, leaving (2x + 1)/(x − 3). Writing (2x + 1)/(x + 3) comes from factorising x² − 9 as (x + 3)² instead of (x − 3)(x + 3) — a difference of two squares always has one plus and one minus bracket. Writing (2x + 3)/(x − 3) comes from mis-factorising the numerator as (2x + 3)(x + 1) and then wrongly cancelling the (x + 1) against the denominator's (x + 3) as though they were the same bracket. Writing 2x + 1 comes from cancelling the (x + 3) factor correctly but then dropping the remaining (x − 3) on the denominator altogether.
- (d) $y = x^2 - 2x - 3$ — Method: read the two x-intercepts (roots) from the graph, write the quadratic as the product of the corresponding factors, then expand. Working: the curve crosses the x-axis at x = −1 and x = 3, so the equation factorises as (x + 1)(x − 3), which expands to x² − 2x − 3. Answer: y = x² − 2x − 3. Distractor refutation: y = x² − x − 6 comes from misreading the left-hand crossing point as x = −2 instead of x = −1, giving factors (x + 2)(x − 3). y = x² − x − 2 comes from misreading the right-hand crossing point as x = 2 instead of x = 3, giving factors (x + 1)(x − 2). y = x² + 2x − 3 comes from writing the factors as (x − 1)(x + 3), swapping which root gets the plus sign and which gets the minus sign, giving the wrong sign on the x term.
- (c) −6 — Method: substitute the value, work out the bracket first, then multiply what the bracket comes to by 2. Working: the bracket gives (−5) + 2 = −3, and multiplying by 2 gives 2 × (−3) = −6. Answer: −6. The distractors: −3 comes from working out the bracket correctly but stopping there and never multiplying by 2; −1 comes from multiplying the 2 inside the bracket by the 2 outside before adding, giving −5 + 4; −8 comes from multiplying only the x by 2 and leaving the 2 inside the bracket unchanged, giving −10 + 2.
- (c) 2 — At x = 1, y = 1² − 3(1) = 1 − 3 = −2. At x = 4, y = 4² − 3(4) = 16 − 12 = 4. Gradient of the chord = change in y ÷ change in x = (4 − (−2)) ÷ (4 − 1) = 6 ÷ 3 = 2. Writing down the change in y, 6, and stopping there without dividing by the change in x gives 6. Losing the negative sign on y = −2 at x = 1 and treating it as +2 gives (4 − 2) ÷ (4 − 1) = 2 ÷ 3 = 2/3. Dividing the wrong way round, change in x ÷ change in y, gives (4 − 1) ÷ (4 − (−2)) = 3 ÷ 6 = 1/2.
- (a) 6x + 12 — A regular hexagon has 6 equal sides, so the perimeter is 6(x + 2) = 6x + 12. A candidate who multiplies only the x-term by 6 and forgets to multiply the 2 gets 6x + 2. A candidate who multiplies only the number term by 6 and forgets to multiply the x gets x + 12. A candidate who adds 6 and 2 to make a single coefficient of x instead of expanding the brackets gets 8x.
- (b) 60 km/h — Method: the gradient of a distance-time graph is the change in distance divided by the change in time, and for a journey at a steady rate that gradient is the speed. Working: the change in distance is 195 − 15 = 180 km and the change in time is 3 hours, so the gradient is 180 ÷ 3 = 60 km/h. Answer: 60 km/h. The distractors: 180 km/h comes from stopping at the change in distance and never dividing by the 3 hours; 195 km/h comes from reading the final marker as the rate instead of working with the change between the two markers; 3 km/h comes from quoting the time taken, which belongs on the bottom of the fraction, as though it were the value of the fraction itself.
- (a) 9 m — Undo the multiplication by the bracket first: dividing both sides by 2 gives P/2 = l + w. Subtracting the length from both sides gives w = P/2 − l. Substituting the measurements, 46 ÷ 2 = 23, and 23 − 14 = 9, so the width is 9 m. Taking the length off before halving gives (46 − 14) ÷ 2 = 16, which halves the length as well; expanding to P = 2l + 2w and then forgetting to divide by 2 gives 46 − 28 = 18; subtracting the length in the wrong direction gives 23 + 14 = 37.
- (b) 20 — The rate is the gradient: the change in litres divided by the change in time. From 2 to 7 minutes, the tank gains 150 − 50 = 100 litres over 7 − 2 = 5 minutes, so the rate is 100 ÷ 5 = 20 litres per minute. 100 comes from working out the change in litres but forgetting to divide by the change in time. 25 comes from using only the first reading, 50 ÷ 2, and ignoring the second reading entirely. 0.05 comes from dividing the change in time by the change in litres instead of the other way round, 5 ÷ 100.
- (d) t = 5 — The maximum height occurs halfway between the two times when the ball is at ground level: the midpoint of t = 1 and t = 9 is (1 + 9) ÷ 2 = 5, so the ball reaches its maximum height at t = 5 seconds. Getting t = 4 comes from halving the DIFFERENCE between the times, 9 − 1 = 8, then 8 ÷ 2 = 4, instead of finding their midpoint. Getting t = 8 uses that difference, 9 − 1 = 8, as if the gap between the two times were itself the time of the maximum. Getting t = 10 adds the two times, 1 + 9 = 10, but forgets to divide by 2.