Printable · GCSE Higher · ages 14-16
Ratio, proportion and rates of change worksheet — GCSE Higher
Fifteen questions across the ratio, proportion and rates of change statements at Higher tier. Choose the non-calculator filter to rehearse Paper 1, which counts for a third of the marks.
Calculator
Ratio, proportion and rates of change worksheet — GCSE Higher
MathsUKwww.geekhero.co.uk
- 1.The depth of water in a tank, in cm, is recorded every 10 seconds: at t = 10, depth = 32; at t = 20, depth = 45; at t = 30, depth = 56. Use the most appropriate chord from these readings to estimate the instantaneous rate of change of depth at t = 20.
- 2.A train travels at a constant speed of 90 km/h. Work out the speed in m/s.
- 3.A lorry is carrying a load of mass m tonnes. Given that 1 tonne = 1000 kg, write down an expression for the mass of the load in kilograms.
- 4.A population of penguins on an island is 2400. The population is predicted to grow by 7% each year. Work out the predicted population after 2 years, to the nearest whole number.
- 5.A rectangular room is drawn on a plan with a scale of 1 : 50. On the plan, the room measures 8 cm by 6 cm. Work out the real area of the room, in square metres.
- 6.For the pairs x = 6, y = 15 and x = 10, y = 25, which statement is correct?
- 7.Two mathematically similar water bottles have a volume scale factor of 8 from the smaller bottle to the larger bottle. Work out the surface area scale factor from the smaller bottle to the larger bottle.
- 8.A statue exerts a downward force of 68.4 N on its base, which has an area of 2.85 m². Work out the pressure that the statue exerts on its base, in N/m².
- 9.Maya is paid £105.30 for working 9 hours. Work out her rate of pay, in £ per hour.
- 10.A car is bought for £17,500. Its value decreases by 12% in the first year, and by a further 10% of its reduced value in the second year. Work out the value of the car at the end of the second year, giving your answer to the nearest pound.
- 11.An online shop's total number of orders received is recorded at the end of each day for five consecutive days: Day 1, 1,284 orders; Day 2, 1,509 orders; Day 3, 1,830 orders; Day 4, 2,296 orders; Day 5, 2,510 orders. Work out between which two consecutive days the average rate of increase in orders was greatest.
- 12.6 identical printers can print a batch of exam papers in 40 minutes, all working at the same rate. Working at the same rate, work out how many minutes 4 of these printers would take to print the same batch.
- 13.A company's turnover this year is £180,000. Last year's turnover was £120,000. Write down this year's turnover as a percentage of last year's turnover.
- 14.A fixed job of fitting a solar array is shared between installers, and the time taken is inversely proportional to the number of installers working on it at once. With 4 installers the job takes 18 hours. Construct the equation connecting time T and number of installers n, then work out how long it would take with 6 installers.
- 15.A recipe for 8 muffins needs 200 g of sugar. Sam wants to make 20 muffins for a bake sale, and he already has 350 g of sugar. Work out how many more grams of sugar he needs to buy.
Answer key
- (c) 1.2 cm/s — To estimate an instantaneous rate of change at a point from a table of readings, use the chord that spans the point symmetrically — equal steps either side — because the over-estimate on one side and the under-estimate on the other largely cancel. Here that is the chord from t = 10 to t = 30. The change in depth is 56 − 32 = 24 and the change in time is 30 − 10 = 20, so the estimate is 24 ÷ 20 = 1.2 cm/s. The one-sided chord from t = 20 to t = 30 gives (56 − 45) ÷ (30 − 20) = 11 ÷ 10 = 1.1 cm/s, which estimates the rate somewhere between t = 20 and t = 30 rather than at t = 20 itself. Dividing the 20-second change in depth by the 10-second gap between consecutive readings gives 24 ÷ 10 = 2.4, mixing the change from one interval with the time from another. Reporting the change in depth, 24, on its own is not a rate at all, because it has not been divided by a time. The best estimate of the instantaneous rate of change of depth at t = 20 is 1.2 cm/s.
- (b) 25 m/s — Convert km/h to m/s by multiplying by 1000 (km to m) and dividing by 3600 (hours to seconds): 90 × 1000 ÷ 3600 = 25 m/s. Working out 90 ÷ 60 = 1.5 converts using 60, as if going from hours to minutes rather than to seconds. Working out 90 × 3.6 = 324 multiplies by 3.6 instead of dividing by it, going the wrong way between the units. Working out 90 × 1000 = 90000 converts kilometres to metres but forgets to convert hours to seconds at all. The train's speed is 25 m/s.
- (a) 1000m — Method: kilograms are a smaller unit than tonnes, so change tonnes into kilograms by multiplying by 1000. Working: m tonnes = m × 1000 kg = 1000m kg. So the expression is 1000m. Distractor m/1000 comes from dividing by 1000 instead of multiplying, which would make the number of kilograms smaller than the number of tonnes, the wrong way round. Distractor 1000 + m comes from adding the conversion factor instead of multiplying by it. Distractor m − 1000 comes from subtracting the conversion factor instead of multiplying by it.
- (d) 2748 — A 7% increase each year means the value becomes 100% + 7% = 107% of the previous year's value, and 107% = 1.07, so the multiplier is 1.07. Multiply by 1.07 for each of the 2 years: 2400 × 1.07 × 1.07 = 2747.76, which rounds to 2748. (2736 comes from using simple growth instead of compound: 2400 + 2 × (2400 × 0.07) = 2736. 2568 is the population after only 1 year, 2400 × 1.07, forgetting the second year's growth. 2747 comes from rounding 2747.76 down instead of up to the nearest whole number.)
- (a) 12 m² — Real length = 8 × 50 = 400 cm = 4 m. Real width = 6 × 50 = 300 cm = 3 m. Real area = 4 × 3 = 12 m². Scaling the plan area (8 × 6 = 48 cm²) by 50 instead of by 50 squared gives 48 × 50 = 2400 cm² = 0.24 m² — area scales by the square of the length scale factor, not the scale factor itself. Multiplying the real dimensions in centimetres, 400 × 300 = 120 000, and calling the result 120 000 m² mistakes square centimetres for square metres. Converting only the length to metres and leaving the width as 6 (treating centimetres as metres), 4 × 6 = 24, gives 24 m², from a scaling that was never finished.
- (c) They are in direct proportion, because y ÷ x = 2.5 for both pairs. — Testing direct proportion means checking that y ÷ x is the same for every pair: 15 ÷ 6 = 2.5 and 25 ÷ 10 = 2.5, so the quantities are in direct proportion. Saying they are not in proportion because x + y differs uses addition, which is not the correct test for proportion. Saying they are not in proportion because y − x differs also uses the wrong test — subtraction, not division. Saying they are in proportion because x × y is 90 and 250 uses multiplication, which is the test for inverse proportion, and the two products are not even equal to each other, so this option also contradicts itself.
- (b) 4 — Method: find the length scale factor by taking the cube root of the volume scale factor, then square it to get the area scale factor. Working: 8 = 2³, so the length scale factor is 2, and the area scale factor is 2² = 4. Answer: 4. 8 comes from using the volume scale factor itself as if it were the area scale factor. 64 comes from squaring the volume scale factor, 8² = 64, instead of first taking its cube root. 2 comes from correctly finding the length scale factor but then forgetting to square it.
- (a) 24 N/m² — Pressure = force ÷ area. 68.4 ÷ 2.85 = 24 N/m². 194.94 N/m² comes from multiplying the force by the area instead of dividing (68.4 × 2.85). 65.55 N/m² comes from subtracting the area from the force (68.4 − 2.85) instead of dividing. 0.04 N/m² comes from dividing the area by the force instead of the force by the area (2.85 ÷ 68.4).
- (a) £11.70 — Rate of pay = total pay ÷ hours worked, so £105.30 ÷ 9 = £11.70 per hour. Working out £105.30 − 9 = £96.30 subtracts the number of hours from the total pay instead of dividing. Working out £105.30 × 9 = £947.70 multiplies total pay by hours worked instead of dividing. Misplacing the decimal point in the correct answer gives £117.00 instead of £11.70. Maya's rate of pay is £11.70 per hour.
- (b) £13,860 — Method: apply the first year's percentage decrease, then apply the second year's percentage decrease to the new value. Working: after the first year, the car is worth £17,500 × 0.88. Multiplying this result by 0.90 gives the value at the end of the second year, £13,860. Answer: £13,860. £13,650 comes from adding the two percentages together (12% + 10% = 22%) and applying a single 22% decrease, £17,500 × 0.78 = £13,650, instead of applying the decreases one after the other. £15,750 comes from applying only the second year's 10% decrease to the original price, forgetting the first year's decrease entirely, £17,500 × 0.90 = £15,750. £15,400 comes from applying only the first year's 12% decrease and stopping there, forgetting to apply the second year's decrease at all.
- (b) Day 3 to Day 4 — Method: the average rate of increase between two consecutive days is the difference in the number of orders divided by the number of days between them, which here is just the difference itself, since each gap is one day; comparing all four differences finds which is greatest. Working: the differences are 1,509 − 1,284 = 225 (Day 1 to Day 2), 1,830 − 1,509 = 321 (Day 2 to Day 3), 2,296 − 1,830 = 466 (Day 3 to Day 4), and 2,510 − 2,296 = 214 (Day 4 to Day 5); 466 is the greatest of the four, so the rate of increase was greatest from Day 3 to Day 4. Choosing Day 4 to Day 5 comes from picking the interval that ends on the highest total number of orders, 2,510, confusing the SIZE of the total with the RATE at which it grew. Choosing Day 1 to Day 2 comes from assuming the rate must be greatest at the very start, without working out any of the four differences. Choosing Day 2 to Day 3 comes from comparing only the first two differences, 225 and 321, and stopping there without checking Day 3 to Day 4 or Day 4 to Day 5. Finding the greatest rate of change from a table always means computing every difference between consecutive values and comparing them all — the day with the highest total, or the first pair you check, is not a shortcut.
- (a) 60 minutes — Method: for inverse proportion, printers × time is constant. Working: 6 × 40 = 240 (the constant). With 4 printers: 240 ÷ 4 = 60 minutes. Wrong options: 26.7 minutes comes from treating the relationship as direct proportion, scaling the time down as printers decrease (40 × 4 ÷ 6); 24 minutes comes from multiplying the two printer counts together instead of using the constant; 40 minutes comes from not adjusting the time at all for the change in printers.
- (c) 150% — Percentage = (180,000 ÷ 120,000) × 100 = 150%.
- (d) 12 hours — Since time is inversely proportional to the number of installers, T = k/n. Using n = 4, T = 18: 18 = k ÷ 4, so k = 18 × 4 = 72. The equation is T = 72/n. When n = 6: T = 72 ÷ 6 = 12. Using the original number of installers instead of the new one gives T = 72 ÷ 4 = 18, the wrong value substituted. Treating more installers as needing more time, as if T were directly proportional to n, gives k = 18 ÷ 4 = 4.5 and then T = 4.5 × 6 = 27, the opposite relationship to the one described. Stopping at k = 72 and reporting it gives the time the job would take a single installer working alone — the constant still has to be divided by the new number of installers before it answers the question asked. With 6 installers, the job takes 12 hours.
- (a) 150 g — Method: scale the recipe to find the total sugar needed, then subtract the sugar Sam already has. Working: 200 ÷ 8 × 20 = 500, so 500 g is needed in total; 500 − 350 = 150, so 150 g still to buy. Stopping after finding the total, 500, without subtracting what he has gives 500 g. Scaling the wrong way round, 200 × 8 ÷ 20 = 80, wrongly suggests he already has enough, giving 0 g. Adding the amount he has instead of subtracting it, 500 + 350 = 850, gives 850 g.
Build your own mix at the worksheet builder.