- (b) Provider Y — £21.00 against Provider X's £23.00 — Provider X's gradient is (35 − 15) ÷ 100 = 0.2, so cost = 15 + 0.2 × 40 = 15 + 8 = £23.00. Provider Y's gradient is (45 − 5) ÷ 100 = 0.4, so cost = 5 + 0.4 × 40 = 5 + 16 = £21.00. £21.00 is less than £23.00, so Provider Y is cheaper: 'Provider Y — £21.00 against Provider X's £23.00'. Getting both costs right but naming Provider X as cheaper compares the two numbers the wrong way round — £23.00 is more than £21.00, not less. Comparing only the fixed fees, £15.00 and £5.00, ignores the cost of the 40 gigabytes actually used. Reading off the costs at 100 gigabytes, £35.00 and £45.00, directly from the graph answers a different usage from the 40 gigabytes the question asks about.
- (d) 3/2 — Work out the number of altos: 40% of 30 = 12. The rest are sopranos, so there are 30 − 12 = 18 sopranos. Form the fraction 18/12; both numbers share a factor of 6, so 18 ÷ 6 = 3 and 12 ÷ 6 = 2, giving 3/2. 2/3 comes from writing the fraction the wrong way round, as altos over sopranos (12/18). 3/5 comes from comparing the sopranos with the whole choir (18/30), instead of with the altos. 7/3 comes from miscalculating 30 − 12 as 28 instead of 18, then forming 28/12.
- (b) 1 : 500 — smallest real distance per cm (5 m), most detail — Method: compare what one centimetre represents in real life for each scale — the scale with the smallest real distance per cm shows the most detail. Working: for 1 : 500, 1 cm represents 500 cm (5 m); for 1 : 5000, 1 cm represents 50 m; for 1 : 50 000, 1 cm represents 500 m. Since 5 m is the smallest, 1 : 500 shows the most detail. Wrong options: '1 : 50 000 — covers the largest real area' wrongly assumes covering more area means more detail, when it is the opposite; '1 : 5000 — the middle value' wrongly assumes the middle scale is automatically the most balanced; '1 : 500 — covers the largest real distance' picks the correct scale but states an incorrect fact, since 1 : 500 actually covers the smallest real distance per cm.
- (d) £144 — Method: find the length (perimeter) scale factor by taking the square root of the area ratio, then apply it to the cost. Working: 12 : 27 simplifies to 4 : 9, and the square root of each part gives the length ratio 2 : 3, so the scale factor from the smaller to the larger pond is 3 ÷ 2 = 1.5. Cost = £96 × 1.5 = £144. Answer: £144. £216 comes from using the area ratio itself as the cost ratio, £96 × (27 ÷ 12) = £216, without taking the square root. £64 comes from using the length ratio the wrong way round, £96 × (2 ÷ 3) = £64. £111 comes from simply adding the difference in area, 27 − 12 = 15, onto the original cost, £96 + £15 = £111, instead of scaling proportionally.
- (a) 12 — Speed × time is constant: k = 20 × 15 = 300. At 25 pages per minute, the time is 300 ÷ 25 = 12 minutes. Getting 18.75 comes from treating speed and time as directly proportional and working out 15 × 25 ÷ 20 instead of dividing k by the new speed. Getting 20 comes from adding the increase in speed (25 − 20 = 5) onto the time (15 + 5 = 20). Getting 10 comes from subtracting that same increase in speed from the time (15 − 5 = 10).
- (c) 3 — Method: find the height scale factor, cube it to find the volume (and coverage) scale factor, use it to find one large sack's coverage, then divide the total lawn area by this and round up to a whole number of sacks. Working: height scale factor = 40 ÷ 20 = 2, so coverage scale factor = 2³ = 8, and each large sack covers 30 × 8 = 240 m². 500 ÷ 240 = 2.08…, which rounds UP to 3 whole sacks. Answer: 3. 2 comes from correctly finding that each large sack covers 240 m², but then rounding 500 ÷ 240 down instead of up, which would leave part of the lawn untreated. 5 comes from squaring the height scale factor (2² = 4) instead of cubing it, giving a coverage of only 30 × 4 = 120 m² per sack. 17 comes from forgetting to scale the coverage at all and dividing 500 by the smaller sack's coverage of 30 m².
- (a) 6 — Since y is inversely proportional to x², y = k/x². Using x = 2, y = 45: 2² = 4, so 45 = k ÷ 4, giving k = 45 × 4 = 180. The equation is y = 180/x². When y = 5: x² = 180 ÷ 5 = 36, so x = 6, taking the positive root because the question states that x is positive. Treating the relationship as inversely proportional to x itself gives k = 45 × 2 = 90 and then x = 90 ÷ 5 = 18, a different relationship. Multiplying by y instead of dividing by it when isolating x² gives x² = 180 × 5 = 900 and x = 30, the wrong operation. Stopping at x² = 36 without taking the square root leaves 36, not the value of x. When y = 5, x = 6.
- (a) 28.8 km/h — Method: first change metres per second into metres per hour, then change metres into kilometres. Working: 8 × 3600 = 28800 metres per hour, then 28800 ÷ 1000 = 28.8 km/h. So the runner's speed is 28.8 km/h. Distractor 28800 km/h comes from stopping after the first step and forgetting to change metres into kilometres. Distractor 2.22 km/h comes from dividing by 3600 instead of multiplying, then multiplying by 1000. Distractor 2.88 km/h comes from using 360 instead of 3600 seconds in an hour, missing a zero.
- (a) 675 ml — How much a jug holds is a volume, and volumes of similar solids scale with the cube of the length scale factor. The length scale factor is 12 ÷ 8 = 1.5, so the volume scale factor is 1.5 × 1.5 × 1.5 = 3.375. The larger jug holds 200 × 3.375 = 675 ml. Multiplying the scale factor by 3 instead of raising it to the power 3 is the mistake to guard against here.
- (c) 1.2 cm/s — To estimate an instantaneous rate of change at a point from a table of readings, use the chord that spans the point symmetrically — equal steps either side — because the over-estimate on one side and the under-estimate on the other largely cancel. Here that is the chord from t = 10 to t = 30. The change in depth is 56 − 32 = 24 and the change in time is 30 − 10 = 20, so the estimate is 24 ÷ 20 = 1.2 cm/s. The one-sided chord from t = 20 to t = 30 gives (56 − 45) ÷ (30 − 20) = 11 ÷ 10 = 1.1 cm/s, which estimates the rate somewhere between t = 20 and t = 30 rather than at t = 20 itself. Dividing the 20-second change in depth by the 10-second gap between consecutive readings gives 24 ÷ 10 = 2.4, mixing the change from one interval with the time from another. Reporting the change in depth, 24, on its own is not a rate at all, because it has not been divided by a time. The best estimate of the instantaneous rate of change of depth at t = 20 is 1.2 cm/s.
- (d) 8 — The product of price and number of tickets is constant: k = 4 × 12 = 48. At £6 per ticket, the number of tickets is 48 ÷ 6 = 8. Getting 18 comes from treating price and tickets as directly proportional and working out 12 × 6 ÷ 4 instead of dividing k by the new price. Getting 12 assumes the number of tickets does not change when the price changes. Getting 6 comes from writing down the new price instead of working out the number of tickets.
- (d) 26.6 — Find the constant multiplier — the mass of each metre of pipe: 12.6 ÷ 4.5 = 2.8, so the mass is always 2.8 times the length. For a length of 9.5 m, the mass is 9.5 × 2.8 = 26.6 kg. 17.6 comes from assuming an additive relationship instead of a multiplicative one — adding the increase in length (9.5 − 4.5 = 5) onto 12.6. 3.4 comes from using the multiplier the wrong way round (4.5 ÷ 12.6, rounded to 1 d.p.), then multiplying by 9.5. 12.6 comes from simply repeating the given mass, without applying the multiplier to the new length.
- (d) £2.00 — Cost for Printer A = 200 × £0.04 = £8. Cost for Printer B = 200 × £0.05 = £10. Difference = £10 − £8 = £2.00.
- (d) 36 mph — First convert 1 hour 30 minutes to hours: 30 minutes is half an hour, so the time is 1.5 hours. Then divide the distance by the time: 54 ÷ 1.5 = 36 mph. Reading 1 hour 30 minutes as 1.3 hours (writing the minutes after the decimal point instead of as a fraction of 60) gives 54 ÷ 1.3 ≈ 41.54 mph. Working out 54 ÷ 30 = 1.8 divides by the number of minutes only, ignoring the hour. Working out 54 × 1.5 = 81 multiplies by the time instead of dividing. The coach's average speed is 36 mph.
- (b) 7.2 m — Multiply the model wingspan by the scale factor: 15 × 48 = 720. This is in centimetres, and 720 cm = 7.2 m, since 1 m = 100 cm. Giving 0.31 m divides by the scale factor instead of multiplying (15 ÷ 48 ≈ 0.31), scaling the model down rather than the real aircraft up. Giving 72 m converts centimetres to metres by dividing by 10 instead of 100. Giving 0.72 m converts by dividing by 1000 instead of 100.