- (b) 1:25 — Write the ratio time : volume using the numbers in the question: 8 : 200. Divide both parts by their highest common factor, 8, to give 1 : 25. (25:1 comes from writing the ratio the wrong way round, volume : time. 8:25 comes from dividing only the volume by 8 and leaving the time unchanged. 25:8 is that same mistake written the wrong way round.)
- (c) £2743.60 — Each year the balance is multiplied by 1.03. After the first year: 4000 × 1.03 = 4120. After the second year: 4120 × 1.03 = 4243.60, so that is what Leah takes out. She then spends £1500 of it, which leaves 4243.60 − 1500 = 2743.60. She has £2743.60 left.
- (b) 450.00 kg — 1 m³ = 100 × 100 × 100 = 1,000,000 cm³, so 0.5 m³ = 500,000 cm³. Mass = density × volume = 0.9 × 500,000 = 450,000 g. Converting to kilograms by dividing by 1000 gives 450,000 ÷ 1000 = 450.00 kg. Skipping the m³-to-cm³ conversion and multiplying 0.9 × 0.5 = 0.45 treats the volume as if it were already 0.5 cm³, giving 0.45 kg. Finding the mass correctly in grams, 450,000 g, but not converting to kilograms leaves 450000.00 kg, out by a factor of 1000. Using the area conversion factor of 10,000, as if converting m² to cm², instead of the volume factor of 1,000,000 gives 0.5 × 10,000 = 5,000 'cm³', and a mass of 0.9 × 5,000 = 4,500 g, which is 4.50 kg.
- (c) 7800 kg/m³ — Method: build the conversion factor from the two unit changes separately — one for the mass, one for the volume. Working: 1 kg = 1000 g, so the mass figure is divided by 1000; 1 m = 100 cm, so 1 m³ = 100 × 100 × 100 = 1000000 cm³ and the volume figure is multiplied by 1000000. The density figure is therefore multiplied by 1000000 ÷ 1000 = 1000, giving 7.8 × 1000 = 7800. So the density of the metal is 7800 kg/m³. Distractor 780 kg/m³ comes from multiplying by 100 instead of 1000. Distractor 78000 kg/m³ comes from multiplying by 10000, an extra zero. Distractor 7.8 kg/m³ comes from not converting the units at all.
- (a) £14224 — Value after 2 years: £15000 × 1.04 × 1.04 = £16224. Money left after buying the trailer: £16224 − £2000 = £14224. £14200 comes from treating the two 4% increases as a single flat 8% increase applied once instead of compounding: £15000 × 1.08 = £16200, and £16200 − £2000 = £14200. £13600 comes from applying the 4% increase only once, for 1 year instead of 2: £15000 × 1.04 = £15600, and £15600 − £2000 = £13600. £18224 comes from adding the £2000 instead of subtracting it: £16224 + £2000 = £18224.
- (b) Day 3 to Day 4 — Method: the average rate of increase between two consecutive days is the difference in the number of orders divided by the number of days between them, which here is just the difference itself, since each gap is one day; comparing all four differences finds which is greatest. Working: the differences are 1,509 − 1,284 = 225 (Day 1 to Day 2), 1,830 − 1,509 = 321 (Day 2 to Day 3), 2,296 − 1,830 = 466 (Day 3 to Day 4), and 2,510 − 2,296 = 214 (Day 4 to Day 5); 466 is the greatest of the four, so the rate of increase was greatest from Day 3 to Day 4. Choosing Day 4 to Day 5 comes from picking the interval that ends on the highest total number of orders, 2,510, confusing the SIZE of the total with the RATE at which it grew. Choosing Day 1 to Day 2 comes from assuming the rate must be greatest at the very start, without working out any of the four differences. Choosing Day 2 to Day 3 comes from comparing only the first two differences, 225 and 321, and stopping there without checking Day 3 to Day 4 or Day 4 to Day 5. Finding the greatest rate of change from a table always means computing every difference between consecutive values and comparing them all — the day with the highest total, or the first pair you check, is not a shortcut.
- (d) The 750 g box, at 36p per 100 g — Work out the cost per 100 g of each box. 750 g box: 270p ÷ 7.5 = 36p per 100 g. 500 g box: 195p ÷ 5 = 39p per 100 g. The lower cost per 100 g is the better value, so the 750 g box at 36p per 100 g is the answer. Choosing the 500 g box at 39p per 100 g gets the maths right but picks the higher unit price, not realising a smaller cost per 100 g is the better deal. Choosing the 500 g box because £1.95 is lower than £2.70 compares the total prices without allowing for the different pack sizes at all. Working out 270 ÷ 5 = 54p divides the 750 g box's price by the wrong number of hundred-grams (the 500 g box's), giving a rate that belongs to neither box. The 750 g box, at 36p per 100 g, is the better value.
- (c) Average rate, t = 2 to 6, is −2°C/min — First find the temperature at each end of the interval. At t = 2, T = 80 − 6 × 2 + 0.5 × 2² = 80 − 12 + 2 = 70. At t = 6, T = 80 − 6 × 6 + 0.5 × 6² = 80 − 36 + 18 = 62. The average rate of change over the interval is the change in T divided by the change in t: 62 − 70 = −8, then −8 ÷ 4 = −2°C per minute, so the statement about the average rate is correct. The instantaneous rate at t = 6 is not −2: completing the square gives T = 0.5(t − 6)² + 62, so t = 6 is the turning point of the curve, where the tangent is horizontal and the rate is 0°C per minute — the reaction has stopped cooling by then. The instantaneous rate at t = 2 is not −2 either: a short chord centred on t = 2, from t = 1.9 (T = 70.405) to t = 2.1 (T = 69.605), gives −0.8 ÷ 0.2 = −4°C per minute, so the reaction is cooling twice as fast at the start of the interval as the average over it. Saying the temperature falls 2°C in total confuses the RATE, −2°C per minute, with a TOTAL drop, which is 70 − 62 = 8°C over the four minutes. Always check whether a figure is a rate, per minute, or a total change.
- (c) 4 m/s — The average rate of change of distance with respect to time over an interval is the change in distance divided by the change in time — the gradient of the chord joining the two endpoints, not the gradient of any tangent inside the interval. From t = 3 to t = 8 the change in time is 8 − 3 = 5 and the change in distance is 32 − 12 = 20, so the average speed is 20 ÷ 5 = 4 m/s. Reporting the change in distance on its own, as 20 m/s, is not a speed: those 20 metres were covered over the whole 5 seconds, not in one second, so the 20 still has to be divided by the 5. The tangent's gradient of 3 m/s is the instantaneous speed at the single moment t = 6, not the average over the whole 5-second interval, so it must not be used here. Adding the change in distance and the change in time instead of dividing gives 20 + 5 = 25, which is not a speed. The average speed of the cyclist over the interval is 4 m/s.
- (c) 500 — Pressure = force ÷ area = 250 ÷ 0.5 = 500 pascals. Getting 125 comes from multiplying the force by the area instead of dividing (250 × 0.5 = 125). Getting 249.5 comes from subtracting the area from the force instead of dividing. Getting 50 comes from misreading the area as 5 m² instead of 0.5 m² and dividing 250 by 5.
- (c) Firm B — £3 per mile against Firm A's £2 per mile — Firm A's gradient is (14 − 4) ÷ 5 = 2, so it charges £2 per mile. Firm B's gradient is (21 − 6) ÷ 5 = 3, so it charges £3 per mile. £3 is more than £2, so Firm B charges more per mile. Swapping the two firms' gradients gives the answer with Firm A at £3 and Firm B at £2, which has the labels the wrong way round. Dividing the change in miles by the change in cost, instead of the other way round, gives 5 ÷ 10 = £0.50 for Firm A and 5 ÷ 15 = £0.33 for Firm B and so names Firm A — that is the gradient upside down. And a positive fixed charge does not mean two firms charge the same rate: the rate is found from the gradient, not from whether the intercept is positive.
- (d) £5.40 — Method: work out the reduced price at each shop separately, then subtract the smaller from the larger. Working: Shop A's reduced price is £45 × 0.8 = £36, and Shop B's reduced price is £34 × 0.9 = £30.60, so the difference is £36 − £30.60 = £5.40. Answer: £5.40. £11.00 comes from comparing the two ORIGINAL prices, £45 − £34, without applying either shop's reduction at all. £1.60 comes from finding Shop A's reduced price correctly, £36, but then subtracting Shop B's original (unreduced) price of £34 instead of its reduced price. £66.60 comes from adding the two reduced prices together, £36 + £30.60, instead of subtracting them.
- (c) 183 mg — Apply the decay, then add the new dose, once for each hour. Hour 1: 0.7 × 200 = 140, then 140 + 50 = 190. Hour 2: 0.7 × 190 = 133, then 133 + 50 = 183, so there is 183 mg after 2 hours. Forgetting the top-up dose and only applying the decay gives 0.7 × 200 = 140, then 0.7 × 140 = 98 — this ignores that a further 50 mg is given every hour. Adding the 50 mg BEFORE the decay is applied, instead of after, gives 0.7 × (200 + 50) = 175, then 0.7 × (175 + 50) = 157.5, which changes how much of the dose is eliminated in the same hour it is given. Multiplying by 0.3, the percentage ELIMINATED, instead of by 0.7, the percentage REMAINING, gives 0.3 × 200 + 50 = 110, then 0.3 × 110 + 50 = 83 — this mixes up the amount that leaves the bloodstream with the amount that stays in it. Always check whether a percentage describes what remains or what is removed before choosing the multiplier.
- (c) Map A, where the distance is 40 cm — 10 km = 1,000,000 cm. On Map A: 1000000 ÷ 25000 = 40 cm. On Map B: 1000000 ÷ 50000 = 20 cm. Since 40 cm is longer than 20 cm, the same real distance appears longer on Map A, the map with the smaller scale number. 'Map B, where the distance is 20 cm' has the correct working for Map B but names the wrong map as the one with the longer length. 'Map A, where the distance is 20 cm' correctly identifies Map A but pairs it with Map B's length. 'Map B, where the distance is 40 cm' correctly identifies Map A's length but attaches it to the wrong map.
- (b) Takings rise about £14 per 1°C rise — The gradient here is positive, so as temperature rises, takings rise too: near 22°C, takings increase by about £14 for every 1°C rise in temperature. Reversing this to say takings rise for every 1°C FALL gets the direction of the independent variable backwards — a positive gradient means both quantities move the same way. Saying 'takings are £14 at 22°C' confuses the gradient, a rate of change, with the y-value on the graph, which is the takings itself. Saying takings 'rose £14 in total' from 0°C to 22°C treats the gradient at a single point as if it applied over the whole range from 0°C to 22°C, when it only describes the instant at 22°C. Always keep a rate, a total change and a single reading separate.