- (b) 2.5 hours — Method: when two objects move in opposite directions the gap between them grows at the sum of their speeds, so divide the required gap by that combined rate. Working: 80 + 60 = 140 km of gap each hour, and 350 ÷ 140 = 2.5. Answer: 2.5 hours. The distractors: 17.5 hours comes from subtracting the speeds, 80 − 60 = 20, which is the rate for two cars travelling in the same direction; 5 hours comes from using the mean of the two speeds, 70 km/h, instead of their sum; 4.375 hours comes from dividing 350 by 80 and ignoring the second car altogether.
- (a) 18 — Method: write both numbers with the same multiplier, turn the second ratio into an equation by cross-multiplying, solve for the multiplier and then build A from it. Working: let A = 3k and B = 5k, so 3k : (5k + 6) = 1 : 2; cross-multiplying gives 2 × 3k = 5k + 6, so 6k = 5k + 6 and k = 6; A = 3 × 6 = 18. Answer: 18, and the check works, because B = 30, B + 6 = 36 and 18:36 = 1:2. The distractors: 9 comes from reading the 6 as the difference between the two numbers — 5 − 3 = 2 parts, so one part is 3 and A is 3 × 3 — but the 6 is added to B, it is not the gap between A and B; 6 comes from solving A : (A + 6) = 1 : 2, adding the 6 to A instead of to B; 30 is the value of B, found from the correct multiplier but given in place of A.
- (a) 100 — The difference between the parts of the ratio is 7 − 3 = 4 parts, and this is worth 40 beads. Divide to find one part: 40 ÷ 4 = 10. The total number of parts is 7 + 3 = 10, so the total number of beads is 10 × 10 = 100. (40 is just the given difference between gold and silver, not the total. 70 is the number of gold beads only, using 7 parts. 30 is the number of silver beads only, using 3 parts.)
- (b) 48 m² — Method: lengths are multiplied by the scale factor, but areas are multiplied by its square. Working: 1 cm on the plan stands for 200 cm = 2 m, so 1 cm² on the plan stands for 2 × 2 = 4 m², and 12 × 4 = 48. Answer: 48 m². The distractors: 24 m² comes from scaling the area by the length factor 2 instead of by its square; 2400 m² comes from multiplying the area by the scale 200 as though it were a length; 4800 m² comes from working in centimetres, 12 × 200² = 480 000 cm², and then dividing by 100 instead of by 10 000 to reach square metres.
- (a) 10 — Method: two equal fractions can be rearranged by cross-multiplying, multiplying each numerator by the other denominator. Working: 4 × 5 = 2 × x, so 2x = 20 and x = 20 ÷ 2 = 10. Answer: 10. The distractors: 20 comes from cross-multiplying to 4 × 5 = 20 and stopping there, without dividing by the 2; 8 comes from multiplying the two numerators, 4 × 2; 2.5 comes from working only with the right-hand fraction, 5 ÷ 2, and ignoring the 4.
- (b) 1:12 — C = 12n means that for every 1 pen there are 12 pence of cost, so n : C = 1 : 12, and the highest common factor of 1 and 12 is 1, so this is already in its simplest form. Writing C : n instead of n : C gives 12 : 1, the ratio the wrong way round. Reading C = 12n as '12 more than n' instead of '12 times n', so n = 1 gives C = 13, gives 1 : 13, from adding instead of multiplying. Choosing n = 12, so C = 12 × 12 = 144, gives the correct pair of values n : C = 12 : 144, but the ratio the right way round left unsimplified — 12 and 144 share a common factor of 12, which has not been cancelled.
- (a) 22p — First convert the hourly rate to pence: £13.20 = 1320p. Then convert from per hour to per minute by dividing by 60, since there are 60 minutes in an hour: 1320 ÷ 60 = 22p per minute. Working out 1320 × 60 = 79200p multiplies by 60 instead of dividing, going the wrong way between per hour and per minute. Working out 13.20 × 10 = 132p converts pounds to pence using the wrong power of ten, and dividing that by 60 carries the error through to give 2.2p. Working out 13.20 × 100 = 1320p converts the currency correctly but stops there, leaving the rate as pence per hour rather than completing the second conversion to pence per minute. The rate of pay is 22p per minute.
- (d) 75 pages — Method: find the number of pages printed in one minute, then scale up to 10 minutes. Working: 45 ÷ 6 = 7.5 pages per minute, so 7.5 × 10 = 75 pages. Answer: 75 pages. 27 pages comes from using the ratio upside down, 45 × 6 ÷ 10, instead of finding the rate per minute first. 55 pages comes from simply adding the extra minutes, 10, onto the original number of pages, 45. 70 pages comes from rounding the rate down to 7 pages per minute before multiplying by 10, instead of using the exact rate of 7.5.
- (a) 12 — Speed × time is constant: k = 20 × 15 = 300. At 25 pages per minute, the time is 300 ÷ 25 = 12 minutes. Getting 18.75 comes from treating speed and time as directly proportional and working out 15 × 25 ÷ 20 instead of dividing k by the new speed. Getting 20 comes from adding the increase in speed (25 − 20 = 5) onto the time (15 + 5 = 20). Getting 10 comes from subtracting that same increase in speed from the time (15 − 5 = 10).
- (b) 2, the cost in pounds of each extra gigabyte — Method: the gradient is the change in cost divided by the change in data, so it is the cost of each extra gigabyte; the value where the line meets the vertical axis is the charge before any data is used, which is a different quantity. Working: from (0, 10) to (8, 26) the cost rises by 26 − 10 = 16 pounds while the data rises by 8 − 0 = 8 gigabytes, so the gradient is 16 ÷ 8 = 2, meaning each extra gigabyte costs £2. Answer: 2, the cost in pounds of each extra gigabyte. The distractors: '10, the cost in pounds of each extra gigabyte' reads the intercept as the gradient, but 10 is what the tariff costs when no data at all has been used; '3.25, the cost in pounds of each extra gigabyte' comes from 26 ÷ 8, treating the line as though it passed through the origin when it starts at 10; '2, the fixed monthly charge in pounds' has the gradient right but describes the intercept, and the fixed charge on this tariff is £10.
- (b) 4 — Method: find the length scale factor by taking the cube root of the volume scale factor, then square it to get the area scale factor. Working: 8 = 2³, so the length scale factor is 2, and the area scale factor is 2² = 4. Answer: 4. 8 comes from using the volume scale factor itself as if it were the area scale factor. 64 comes from squaring the volume scale factor, 8² = 64, instead of first taking its cube root. 2 comes from correctly finding the length scale factor but then forgetting to square it.
- (d) d ÷ t — Average speed = distance ÷ time, so the expression is d ÷ t. Writing t ÷ d inverts the formula, giving the time per kilometre instead of the speed. Writing d × t confuses speed with the formula for distance travelled (distance = speed × time) used the wrong way round. Writing d + t treats the relationship as additive instead of using division.
- (d) 5/4 — Work out the number of free seats: 54 − 24 = 30. Form the fraction 30/24; both numbers share a factor of 6, so 30 ÷ 6 = 5 and 24 ÷ 6 = 4, giving 5/4. 4/5 comes from writing the fraction the wrong way round, as reserved over free (24/30). 5/9 comes from comparing the free seats with the total number of seats (30/54), instead of with the reserved seats. 5/6 comes from miscalculating 54 − 24 as 20 instead of 30, then forming 20/24.
- (c) 2 : 5 — The point (4, 10) gives x = 4, y = 10, so x : y = 4 : 10. Dividing both parts by their highest common factor, 2, gives 2 : 5 in simplest form. Inverting the whole ratio gives 5 : 2, which is y : x instead of x : y. Dividing only the x-part by 2 and leaving the y-part as 10 gives 2 : 10, but scaling one part on its own changes the ratio: 2 : 10 is the same as 1 : 5, not 4 : 10. Dividing only the y-part by 2 and leaving the x-part as 4 gives 4 : 5, the same one-sided mistake made on the other part of the ratio.
- (c) 150% — Percentage = (180,000 ÷ 120,000) × 100 = 150%.