Printable · GCSE Higher · ages 14-16
Ratio, proportion and rates of change worksheet — GCSE Higher
Fifteen questions across the ratio, proportion and rates of change statements at Higher tier. Choose the non-calculator filter to rehearse Paper 1, which counts for a third of the marks.
Non-calculator
Answer key: Ratio, proportion and rates of change worksheet — GCSE Higher
MathsUKwww.geekhero.co.uk
- (a) 45% — Method: percentage increase = increase ÷ original amount × 100. Working: the increase is £116 − £80 = £36, and 36 ÷ 80 = 0.45, so 0.45 × 100 = 45%. Answer: 45%. The distractors: 36% comes from quoting the £36 increase as though pounds and per cent were the same thing; 31% comes from dividing the £36 increase by the new price £116 instead of by the original £80, which gives 31% to the nearest per cent; 145% is the new price written as a percentage of the original price, which is the whole of the new price rather than the increase.
- (d) 25% — Method: percentage decrease = decrease ÷ original amount × 100. Working: the reduction is £60 − £45 = £15, and 15 ÷ 60 = 0.25, so 0.25 × 100 = 25%. Answer: 25%. The distractors: 15% comes from quoting the £15 reduction as though pounds and per cent were the same thing; 33% comes from dividing the £15 by the new price £45 instead of by the original £60, which gives 33% to the nearest per cent; 75% is the new price written as a percentage of the old one, which is what is still paid rather than what has been taken off.
- (d) 12 hours — Since time is inversely proportional to the number of installers, T = k/n. Using n = 4, T = 18: 18 = k ÷ 4, so k = 18 × 4 = 72. The equation is T = 72/n. When n = 6: T = 72 ÷ 6 = 12. Using the original number of installers instead of the new one gives T = 72 ÷ 4 = 18, the wrong value substituted. Treating more installers as needing more time, as if T were directly proportional to n, gives k = 18 ÷ 4 = 4.5 and then T = 4.5 × 6 = 27, the opposite relationship to the one described. Stopping at k = 72 and reporting it gives the time the job would take a single installer working alone — the constant still has to be divided by the new number of installers before it answers the question asked. With 6 installers, the job takes 12 hours.
- (b) 1500 m — Method: multiply the map length by the scale to get the real length in centimetres, then divide by 100 to change centimetres into metres. Working: 3 × 50 000 = 150 000 cm, and 150 000 ÷ 100 = 1500. Answer: 1500 m. The distractors: 15000 m comes from dividing the 150 000 cm by 10 instead of 100; 150 m comes from dividing by 1000, the conversion for kilometres; 50000 m comes from writing the scale itself as the answer and ignoring the 3 cm measured on the map.
- (b) 2, the cost in pounds of each extra gigabyte — Method: the gradient is the change in cost divided by the change in data, so it is the cost of each extra gigabyte; the value where the line meets the vertical axis is the charge before any data is used, which is a different quantity. Working: from (0, 10) to (8, 26) the cost rises by 26 − 10 = 16 pounds while the data rises by 8 − 0 = 8 gigabytes, so the gradient is 16 ÷ 8 = 2, meaning each extra gigabyte costs £2. Answer: 2, the cost in pounds of each extra gigabyte. The distractors: '10, the cost in pounds of each extra gigabyte' reads the intercept as the gradient, but 10 is what the tariff costs when no data at all has been used; '3.25, the cost in pounds of each extra gigabyte' comes from 26 ÷ 8, treating the line as though it passed through the origin when it starts at 10; '2, the fixed monthly charge in pounds' has the gradient right but describes the intercept, and the fixed charge on this tariff is £10.
- (c) 4 km — Since signal strength is inversely proportional to the square of the distance, S = k/d². Using d = 2, S = 20: 2² = 4, so 20 = k ÷ 4, giving k = 20 × 4 = 80. The equation is S = 80/d². When S = 5: d² = 80 ÷ 5 = 16, so d = 4 (taking the positive root, since distance cannot be negative). Stopping at d² = 16 without taking the square root leaves 16, the square of the distance, not the distance itself. Treating the relationship as inversely proportional to distance itself, rather than to its square, gives k = 20 × 2 = 40 and then d = 40 ÷ 5 = 8, a different relationship. Multiplying by S instead of dividing by it when isolating d² gives d² = 80 × 5 = 400 and d = 20, the wrong operation. The distance at which the signal strength is 5 units is 4 km.
- (d) 75 pages — Method: find the number of pages printed in one minute, then scale up to 10 minutes. Working: 45 ÷ 6 = 7.5 pages per minute, so 7.5 × 10 = 75 pages. Answer: 75 pages. 27 pages comes from using the ratio upside down, 45 × 6 ÷ 10, instead of finding the rate per minute first. 55 pages comes from simply adding the extra minutes, 10, onto the original number of pages, 45. 70 pages comes from rounding the rate down to 7 pages per minute before multiplying by 10, instead of using the exact rate of 7.5.
- (b) 5/7 — The enlargement multiplier is 1.4, which as a fraction is 7/5. To reverse an enlargement, use the reciprocal of the multiplier: flip 7/5 to get 5/7. 7/5 comes from using the enlargement multiplier again, instead of reversing it. 3/5 comes from treating the reverse as 'give back the extra amount', working out 1 − (1.4 − 1) = 0.6, instead of using the reciprocal. 5/2 comes from ignoring the whole number in 1.4 and inverting only the decimal part, 0.4, as if it were the whole multiplier.
- (b) 48 m² — Method: lengths are multiplied by the scale factor, but areas are multiplied by its square. Working: 1 cm on the plan stands for 200 cm = 2 m, so 1 cm² on the plan stands for 2 × 2 = 4 m², and 12 × 4 = 48. Answer: 48 m². The distractors: 24 m² comes from scaling the area by the length factor 2 instead of by its square; 2400 m² comes from multiplying the area by the scale 200 as though it were a length; 4800 m² comes from working in centimetres, 12 × 200² = 480 000 cm², and then dividing by 100 instead of by 10 000 to reach square metres.
- (a) 20% — Method: percentage increase = increase ÷ original amount × 100. Working: the increase is 84 − 70 = 14 marks, and 14 ÷ 70 = 0.2, so 0.2 × 100 = 20. Answer: an increase of 20%. The distractors: 14% comes from quoting the 14 mark increase as though marks and per cent were the same thing; 17% comes from dividing the 14 by the new mean 84 instead of by the original 70, which gives 17% to the nearest per cent; 120% is the new mean written as a percentage of the old one, which is the whole of the new mean rather than the increase.
- (d) 60 km/h — Method: use the formula v = d ÷ t with the distance and time given. Working: 180 ÷ 3 = 60 km/h. So the average speed is 60 km/h. Distractor 540 km/h comes from multiplying the distance and time instead of dividing. Distractor 90 km/h comes from dividing by 2 instead of 3. Distractor 18 km/h comes from dividing by 10 instead of 3, a decimal-point slip.
- (a) 80 km/h — Average speed = total distance ÷ total time. Total distance = 45 + 75 = 120 km. Total time = 30 minutes + 1 hour = 1.5 hours. 120 ÷ 1.5 = 80 km/h. 60 km/h comes from treating the 30 minutes as a whole hour, giving a total time of 2 hours instead of 1.5 (120 ÷ 2). 82.5 km/h comes from averaging the two separate speeds (45 ÷ 0.5 = 90 km/h and 75 ÷ 1 = 75 km/h, then (90 + 75) ÷ 2) instead of using total distance over total time. 75 km/h comes from using only the second part of the journey (75 km in 1 hour) and ignoring the first part.
- (b) 4 : 25 — For similar shapes, the ratio of areas is the ratio of lengths squared: 2² : 5² = 4 : 25. 2 : 5 comes from using the perimeter ratio itself as the area ratio, without squaring it at all. 8 : 125 comes from cubing each part instead of squaring (2³ : 5³) — cubing is the rule for volume, not area. 4 : 5 comes from squaring only the first part of the ratio (2² = 4), and leaving the second part unsquared.
- (a) £102 — Method: find the value of one part of the ratio, then work out each group's share before comparing them. Working: the ratio 5:2 has 5 + 2 = 7 parts, so one part is £238 ÷ 7 = £34. Adults donate 5 × £34 = £170 and children donate 2 × £34 = £68, so adults donate £170 − £68 = £102 more than children. So the difference is £102. Distractor £68 is only the children's donation, without finding the difference. Distractor £170 is only the adults' donation, without finding the difference. Distractor £136 comes from doubling the children's donation instead of subtracting it from the adults' donation.
- (b) 1.00 litres — Total volume = 350 + 650 = 1000 cm³. Since 1000 cm³ = 1 litre, the smoothie is 1.00 litre. Using only the orange juice's 650 cm³ and converting that gives 0.65 litres, forgetting the mango juice entirely. Using only the mango juice's 350 cm³ gives 0.35 litres, forgetting the orange juice. Adding both volumes correctly to get 1000 cm³ but not converting to litres leaves the answer as 1000.00, which is the volume in the wrong unit.
Build your own mix at the worksheet builder.