Printable · GCSE Higher · ages 14-16
Ratio, proportion and rates of change worksheet — GCSE Higher
Fifteen questions across the ratio, proportion and rates of change statements at Higher tier. Choose the non-calculator filter to rehearse Paper 1, which counts for a third of the marks.
Answer key: Ratio, proportion and rates of change worksheet — GCSE Higher
MathsUKwww.geekhero.co.uk
- (c) 54 — Method: y = kx, so k = y ÷ x. Working: k = 18 ÷ 5 = 3.6. At x = 15: y = 3.6 × 15 = 54. Wrong options: 28 comes from adding the change in x (10) onto y instead of scaling; 6 comes from treating the relationship as inverse proportion (k = 5 × 18 = 90, then y = 90 ÷ 15 = 6); 60 comes from rounding the constant up to 4 instead of using 3.6.
- (a) 18/25 — First find the new number of rose bushes: 90 × 1.2 = 108 (a 20% increase multiplies by 1.2). Then write 108 over 150 and divide top and bottom by 6 to get 18/25. Choosing 3/5 comes from using the original 90 rose bushes without applying the 20% increase (90/150 = 3/5). Choosing 25/18 comes from writing the number of lavender bushes over the new number of rose bushes, the wrong way round. Choosing 3/25 comes from multiplying 90 by 0.2 instead of 1.2, finding only the increase (18) rather than the new total, then writing 18/150 = 3/25.
- (b) Day 3 to Day 4 — Method: the average rate of increase between two consecutive days is the difference in the number of orders divided by the number of days between them, which here is just the difference itself, since each gap is one day; comparing all four differences finds which is greatest. Working: the differences are 1,509 − 1,284 = 225 (Day 1 to Day 2), 1,830 − 1,509 = 321 (Day 2 to Day 3), 2,296 − 1,830 = 466 (Day 3 to Day 4), and 2,510 − 2,296 = 214 (Day 4 to Day 5); 466 is the greatest of the four, so the rate of increase was greatest from Day 3 to Day 4. Choosing Day 4 to Day 5 comes from picking the interval that ends on the highest total number of orders, 2,510, confusing the SIZE of the total with the RATE at which it grew. Choosing Day 1 to Day 2 comes from assuming the rate must be greatest at the very start, without working out any of the four differences. Choosing Day 2 to Day 3 comes from comparing only the first two differences, 225 and 321, and stopping there without checking Day 3 to Day 4 or Day 4 to Day 5. Finding the greatest rate of change from a table always means computing every difference between consecutive values and comparing them all — the day with the highest total, or the first pair you check, is not a shortcut.
- (c) 27 : 64 — For similar solids, the ratio of volumes is the ratio of lengths cubed: 3³ : 4³ = 27 : 64. 3 : 4 comes from using the height ratio itself as the volume ratio, without cubing it at all. 9 : 16 comes from squaring each part instead of cubing (3² : 4²) — squaring is the rule for area, not volume. 27 : 4 comes from cubing only the first part of the ratio (3³ = 27), and leaving the second part uncubed.
- (c) 3 hours — Method: in inverse proportion the product of the two quantities is constant, and here that product is the distance. Working: 60 × 4 = 240 km, so at 80 km/h the time is 240 ÷ 80 = 3. Answer: 3 hours. The distractors: 5 hours 20 minutes comes from treating the relationship as direct, working out 4 × 80 ÷ 60; 2 hours 40 minutes comes from cutting the time by the fraction the speed rose by — the speed went up by one third, so the time was cut by one third — which is not how inverse proportion works; 4 hours comes from dividing the 240 km by the original speed of 60 km/h again instead of by the new speed.
- (d) 7/4 — A part-to-part ratio a : b gives the fraction a/b when the first quantity is written as a fraction of the second, so 7 : 4 gives 7/4. Writing 4/7 puts the parts the wrong way round — blue as a fraction of red, not red as a fraction of blue. Writing 7/11 uses the total number of counters, 7 + 4 = 11, as the denominator instead of the number of blue counters — that is red as a fraction of the whole bag, not red as a fraction of blue. Writing 11/7 has both the wrong denominator and the parts inverted.
- (a) 1.3 — The gradient of a distance-time graph gives the speed. Difference in speed = 4.5 − 3.2 = 1.3 km/h. A student who subtracts the speeds the wrong way round, 3.2 − 4.5, gets −1.3. A student who adds the two speeds instead of comparing them gets 7.7. A student who multiplies the two gradients gets 14.4.
- (c) £624.32 — A 4% rise is a multiplier of 1.04, applied once each year. After year 1: 5000 × 1.04 = 5200. After year 2: 5200 × 1.04 = 5408. After year 3: 5408 × 1.04 = 5624.32. The question asks for the interest, not the value of the account, so take away the amount invested at the start: 5624.32 − 5000 = 624.32. The total interest earned is £624.32.
- (c) 7800 kg/m³ — Method: build the conversion factor from the two unit changes separately — one for the mass, one for the volume. Working: 1 kg = 1000 g, so the mass figure is divided by 1000; 1 m = 100 cm, so 1 m³ = 100 × 100 × 100 = 1000000 cm³ and the volume figure is multiplied by 1000000. The density figure is therefore multiplied by 1000000 ÷ 1000 = 1000, giving 7.8 × 1000 = 7800. So the density of the metal is 7800 kg/m³. Distractor 780 kg/m³ comes from multiplying by 100 instead of 1000. Distractor 78000 kg/m³ comes from multiplying by 10000, an extra zero. Distractor 7.8 kg/m³ comes from not converting the units at all.
- (d) £4 — The gradient of the tangent gives the instantaneous rate of change of cost with respect to the number of passengers, in pounds per passenger. The tangent passes through (16, 184) and (24, 216), so the change in cost is 216 − 184 = 32 and the change in passengers is 24 − 16 = 8. The gradient is 32 ÷ 8 = 4. Stopping after finding the change in cost, without dividing by the change in passengers, leaves 32, not a rate. Adding the two changes instead of dividing gives 32 + 8 = 40, which is not a rate either. Reading off only the change in passengers, 8, is not a rate at all — a rate needs the change in cost as well. The instantaneous rate is £4 per extra passenger.
- (b) 120 minutes — Method: find the rate in bottles per minute, then divide the order size by the rate. Working: rate = 810 ÷ 45 = 18 bottles per minute. Time = 2,160 ÷ 18 = 120 minutes. Wrong options: 1,350 minutes comes from subtracting 810 from 2,160 instead of using the rate; 48 minutes comes from dividing the order size by the original time (2,160 ÷ 45) instead of the rate; 108 minutes comes from rounding the rate to 20 bottles per minute before dividing.
- (b) 3/10 — Work out the empty space: 500 − 350 = 150 litres. Form the fraction 150/500; both numbers share a factor of 50, so 150 ÷ 50 = 3 and 500 ÷ 50 = 10, giving 3/10. 7/10 comes from writing the fraction of the tank that is full (350/500), instead of the empty space. 1/2 comes from miscalculating 500 − 350 as 250 instead of 150. 3/7 comes from comparing the empty space with the water held (150/350), instead of with the tank's total capacity.
- (a) 4 — Method: for inverse proportion, x × y always stays the same value. Working: when x = 5 and y = 8, the constant is 5 × 8 = 40. When x = 10, y = 40 ÷ 10 = 4. So y = 4. Distractor 16 comes from treating the relationship as direct proportion instead of inverse, working out 8 × 10 ÷ 5. Distractor 3 comes from assuming y decreases by the same amount that x increases, an additive rather than proportional idea. Distractor 0.8 comes from dividing the given y-value, 8, by the new x-value, 10, without first finding the constant.
- (a) It's an average over 20 days, which may miss the day-5 rate. — Method: a chord's gradient is the AVERAGE rate of change across the whole interval it spans; it only closely approximates the INSTANTANEOUS rate of change at a point inside that interval when the rate of change is roughly constant across the interval, which usually means the interval needs to be short. Working: here the chord spans 20 days while the point of interest, t = 5, is only a quarter of the way along it, so if the reservoir's level rose or fell at different rates over that time, the chord's gradient will not be close to the true gradient of the curve at t = 5 — this is the correct reason. Claiming the chord's gradient needs the water level at every day in between is wrong: a chord's gradient needs only the two endpoint values, at t = 0 and t = 20. Claiming a chord can only estimate the rate at its own endpoints is wrong: a chord between two points can be used to estimate the instantaneous rate of change at any point inside the interval, including one that is not an endpoint — that is exactly the technique being used here, and it is the SIZE of the interval that makes the estimate poor, not the fact that t = 5 is an interior point. Claiming the units do not match is wrong: the chord's gradient and the instantaneous rate of change are both measured in metres per day, so the units are the same. A chord is only a good estimate of an instantaneous rate when the interval it spans is short enough that the rate does not change much within it — always check how long the interval is compared with how far it is to the point you actually want.
- (a) 22p — First convert the hourly rate to pence: £13.20 = 1320p. Then convert from per hour to per minute by dividing by 60, since there are 60 minutes in an hour: 1320 ÷ 60 = 22p per minute. Working out 1320 × 60 = 79200p multiplies by 60 instead of dividing, going the wrong way between per hour and per minute. Working out 13.20 × 10 = 132p converts pounds to pence using the wrong power of ten, and dividing that by 60 carries the error through to give 2.2p. Working out 13.20 × 100 = 1320p converts the currency correctly but stops there, leaving the rate as pence per hour rather than completing the second conversion to pence per minute. The rate of pay is 22p per minute.
Build your own mix at the worksheet builder.