- (c) 40 cm — First find the real pitch length using Plan A's scale: 8 × 1000 = 8000 cm. Now find its length on Plan B using Plan B's scale: 8000 ÷ 200 = 40 cm. Assuming both plans use the same scale and leaving the length as 8 cm ignores that Plan B has a different scale. Using the ratio of the two scales upside down, 200 ÷ 1000 = 0.2, then 8 × 0.2 = 1.6, gives 1.6 cm — Plan B is drawn to a larger scale than Plan A, so lengths on it should be bigger, not smaller. Dividing by 2000 instead of 200 gives 4 cm, ten times too small.
- (a) 12/5 — If A is 5/12 of B, then B is the reciprocal of that fraction times A: flip 5/12 to get 12/5, so B is 12/5 of A. 5/12 comes from keeping the same fraction without flipping it, treating the relationship as if it works the same way in both directions. 7/12 comes from computing 1 − 5/12 = 7/12, which is not how a fraction reverses. 12/7 comes from subtracting 5 from 12 to get 7, and writing 12 over that, instead of swapping the numerator and denominator of 5/12.
- (a) 45% — Method: percentage increase = increase ÷ original amount × 100. Working: the increase is £116 − £80 = £36, and 36 ÷ 80 = 0.45, so 0.45 × 100 = 45%. Answer: 45%. The distractors: 36% comes from quoting the £36 increase as though pounds and per cent were the same thing; 31% comes from dividing the £36 increase by the new price £116 instead of by the original £80, which gives 31% to the nearest per cent; 145% is the new price written as a percentage of the original price, which is the whole of the new price rather than the increase.
- (b) 1:200000 — '1 cm represents 2 km' means 1 cm on the map is 2 km in real life. Convert 2 km into centimetres, the same unit as the 1: 2 km = 2000 m = 200 000 cm. So the scale is 1 : 200 000. Converting only as far as metres gives 1 : 2000 — the conversion to centimetres was never finished. Losing a zero in the conversion gives 1 : 20 000, ten times too small. Writing 1 : 2 without converting units at all compares 1 cm to 2 km directly, which is not a valid ratio since the units do not match.
- (a) £85.47 — Value after 2 years: £1200 × 1.035 × 1.035 = £1285.47 (nearest penny). Interest earned = £1285.47 − £1200 = £85.47. £1285.47 is the total value of the account, not the interest earned on top of the original £1200. £84.00 comes from using simple interest instead of compound interest: £1200 × 0.035 × 2 = £84.00. £42.00 comes from working out only the first year's interest and stopping there: £1200 × 0.035 = £42.00.
- (b) 6 litres — Method: find the volume of the cuboid in cm³, then change cm³ into litres using 1 litre = 1000 cm³. Working: 30 × 20 × 10 = 6000 cm³, and 6000 ÷ 1000 = 6. Answer: 6 litres. The distractors: 60 litres comes from using 1 litre = 100 cm³; 600 litres comes from using 1 litre = 10 cm³; 0.6 litres comes from using 1 litre = 10 000 cm³.
- (d) 2:5 — The ratio of the y-values equals the ratio of the coefficients of x, since x cancels: 2x : 5x = 2 : 5.
- (b) No — rate fell by 3.7 thousand/month — Each tangent gradient is the instantaneous growth rate, in thousand subscribers per month. To compare them, subtract the later rate from the earlier one: 4.8 − 1.1 = 3.7. Since 1.1 is less than 4.8, the growth rate has fallen by 3.7 thousand subscribers per month, so the manager is wrong — the app is growing more slowly at 18 months, not faster. Subtracting the other way round and calling the result a rise, 'rate rose by 3.7 thousand/month', gets the direction backwards: the later gradient is the smaller of the two. Adding the two gradients, 4.8 + 1.1 = 5.9, and calling this a combined rate that shows speeding up, is the wrong operation for comparing two rates. Treating the difference 3.7 as a total number of subscribers lost, rather than a rate in thousands per month, confuses a rate with a count. Always subtract the two rates in a sensible order and keep the units in thousands per month.
- (b) 20 — The gradient is the change in p divided by the change in t: (90 − 30) ÷ (5 − 2) = 60 ÷ 3 = 20. Choosing 0.05 comes from dividing the change in t by the change in p, the wrong way round (3 ÷ 60). Choosing −20 comes from subtracting the coordinates in the wrong order for one part of the calculation, for example (30 − 90) ÷ (5 − 2), giving a negative value. Choosing 18 comes from dividing the second p-coordinate by the second t-coordinate directly (90 ÷ 5) instead of using the change between the two points.
- (d) 8 — The product of price and number of tickets is constant: k = 4 × 12 = 48. At £6 per ticket, the number of tickets is 48 ÷ 6 = 8. Getting 18 comes from treating price and tickets as directly proportional and working out 12 × 6 ÷ 4 instead of dividing k by the new price. Getting 12 assumes the number of tickets does not change when the price changes. Getting 6 comes from writing down the new price instead of working out the number of tickets.
- (d) 25% — Method: percentage decrease = decrease ÷ original amount × 100. Working: the reduction is £60 − £45 = £15, and 15 ÷ 60 = 0.25, so 0.25 × 100 = 25%. Answer: 25%. The distractors: 15% comes from quoting the £15 reduction as though pounds and per cent were the same thing; 33% comes from dividing the £15 by the new price £45 instead of by the original £60, which gives 33% to the nearest per cent; 75% is the new price written as a percentage of the old one, which is what is still paid rather than what has been taken off.
- (a) 12 — Speed × time is constant: k = 20 × 15 = 300. At 25 pages per minute, the time is 300 ÷ 25 = 12 minutes. Getting 18.75 comes from treating speed and time as directly proportional and working out 15 × 25 ÷ 20 instead of dividing k by the new speed. Getting 20 comes from adding the increase in speed (25 − 20 = 5) onto the time (15 + 5 = 20). Getting 10 comes from subtracting that same increase in speed from the time (15 − 5 = 10).
- (d) £5.40 — Method: work out the reduced price at each shop separately, then subtract the smaller from the larger. Working: Shop A's reduced price is £45 × 0.8 = £36, and Shop B's reduced price is £34 × 0.9 = £30.60, so the difference is £36 − £30.60 = £5.40. Answer: £5.40. £11.00 comes from comparing the two ORIGINAL prices, £45 − £34, without applying either shop's reduction at all. £1.60 comes from finding Shop A's reduced price correctly, £36, but then subtracting Shop B's original (unreduced) price of £34 instead of its reduced price. £66.60 comes from adding the two reduced prices together, £36 + £30.60, instead of subtracting them.
- (b) £250 — Since cost is proportional to the cube of the radius, C = kr³. Using r = 3, C = 54: 3³ = 27, so 54 = k × 27, giving k = 54 ÷ 27 = 2. The equation is C = 2r³. When r = 5: 5³ = 125, so C = 2 × 125 = 250. Treating the relationship as proportional to r² instead of r³ gives k = 54 ÷ 9 = 6 and then C = 6 × 25 = 150, which models area scaling, not volume scaling. Treating it as proportional to r itself gives k = 54 ÷ 3 = 18 and then C = 18 × 5 = 90. Finding k correctly from the cube but then multiplying it by the radius instead of by the cube of the radius gives 2 × 5 = 10, which applies the right constant to the wrong power of r. The cost of a container of radius 5 cm is £250.
- (d) £117.60 — Add the hours worked over the two days: 6 + 4.5 = 10.5 hours. Multiply by the rate of pay: 10.5 × £11.20 = £117.60. (£67.20 is Monday's pay only. £50.40 is Tuesday's pay only. £106.40 comes from mistakenly adding the hours as 6 + 3.5 = 9.5 — misreading Tuesday's 4.5 hours as 3.5 — and then multiplying by £11.20.)