Sample paper · GCSE Higher · grades 4–9
GCSE Higher sample Paper 1 (non-calculator)
The real Paper 1 is 1.5 hour 30 minutes and 80 marks, non-calculator, and all three papers carry equal weight. This sample is 20 original questions in the same content proportions as the Higher qualification — number 15%, algebra 30%, ratio, proportion and rates of change 20%, geometry and measures 20%, probability 7.5%, statistics 7.5% — with no calculator-only items. AO1 / AO2 / AO3 at this tier: 40% / 30% / 30%.
Answer key: GCSE Higher sample Paper 1 (non-calculator)
- (d) 1 × 10⁷ seconds — Method: the time for a journey is the distance divided by the speed, so round each number to 1 significant figure and then divide; dividing numbers in standard form means dividing the coefficients and subtracting the indices. Working: 3.1 × 10¹⁵ rounds to 3 × 10¹⁵ and 2.998 × 10⁸ rounds to 3 × 10⁸; 3 ÷ 3 = 1 for the coefficients, and 15 − 8 = 7 for the indices. Answer: about 1 × 10⁷ seconds. The distractors: 3 × 10⁷ seconds comes from subtracting the indices correctly but leaving the coefficient as 3 instead of dividing 3 by 3; 1 × 10⁻⁷ seconds comes from dividing the speed by the distance instead of the distance by the speed; 9 × 10²³ seconds comes from multiplying the two quantities instead of dividing them, since 3 × 3 = 9 and 15 + 8 = 23.
- (b) 6 — Method: for any point that lies on y = k/x, the value of k is found by multiplying the x-coordinate and the y-coordinate together, since k = x × y. Working: k = 2 × 3 = 6. Answer: k = 6. Distractor refutation: 1.5 comes from dividing the y-coordinate by the x-coordinate instead of multiplying them. 5 comes from adding the two coordinates instead of multiplying them. 9 comes from misreading the point's x-coordinate as 3 instead of 2, then multiplying 3 × 3.
- (c) 30 — Method: use y = kx and find k from the given pair of values, then substitute x = 12. Working: k = 20 ÷ 8 = 2.5, so y = 2.5 × 12 = 30. Answer: 30. 24 comes from treating the relationship as additive, adding the increase in x (12 − 8 = 4) straight onto y (20 + 4 = 24), instead of multiplying by k. 14.5 comes from finding k correctly (2.5) but then adding it to x instead of multiplying (12 + 2.5 = 14.5). 4.8 comes from finding k upside down, 8 ÷ 20 = 0.4, and multiplying by x: 12 × 0.4 = 4.8.
- (c) 18 — Method: divide the real length by 5 to find how many 'units' of 5 m it contains, then multiply by 2 cm for each unit. Working: 45 ÷ 5 = 9, so the real bridge is 9 lots of 5 m; each lot is represented by 2 cm on the model, so the model length is 9 × 2 = 18 cm. Options: 9 comes from stopping after the division, without multiplying by the 2 cm per unit; 90 comes from multiplying the real length by 2 directly, without dividing by 5 first; 4.5 comes from dividing by 5 and then dividing by 2 again, instead of multiplying by 2. Answer: 18.
- (a) 1/6 — Method: write the results of the two dice as ordered pairs, count the pairs whose scores add to the total asked for, divide by the number of ordered pairs there are, then cancel the fraction down. Working: there are 6 × 6 = 36 equally likely ordered pairs. The pairs whose scores add to 7 are (1, 6), (2, 5), (3, 4), (4, 3), (5, 2) and (6, 1), which is 6 pairs, so the probability is 6/36. Dividing the top and the bottom by 6 gives 1/6. Answer: the probability is 1/6. The distractors: 7/36 comes from taking the number of favourable pairs to be 7 because 7 is the total asked for, confusing the size of a total with the number of ways of making it; 1/7 comes from using the 21 different combinations of two scores as the equally likely results, finding the 3 combinations 1 and 6, 2 and 5, 3 and 4, and cancelling 3/21; 6/11 comes from counting the 6 favourable pairs correctly but dividing by the 11 possible totals from 2 to 12 rather than by the 36 pairs.
- (d) Route 1, as its times vary by 6 minutes rather than 20 — Method: work out an average and a measure of spread for each route, then decide which matters to a commuter who must arrive on time every day. Working: for Route 1, 22 + 23 + 24 + 24 + 25 + 25 + 26 + 26 + 27 + 28 = 250 and 250 ÷ 10 = 25, so the mean is 25 minutes, and the range is 28 − 22 = 6 minutes. For Route 2, 18 + 19 + 20 + 20 + 21 + 22 + 26 + 30 + 36 + 38 = 250 and 250 ÷ 10 = 25, so the mean is also 25 minutes, but the range is 38 − 18 = 20 minutes. The means give no reason to prefer either route; the spreads do, because a commuter who must never be late has to allow for the worst day, which is 28 minutes on Route 1 and 38 minutes on Route 2. Answer: Route 1, as its times vary by 6 minutes rather than 20. The distractors: saying Route 2 has the lower mean assumes that its quicker-looking early times must pull the average down, when both routes total 250 minutes over the ten days; choosing Route 2 for its fastest journey of 18 minutes judges a route by its best day, and the commuter has to survive its worst; saying either route will do uses the equal means and ignores the spread altogether, which is the one thing that separates the two routes.
- (d) 10 — Method: picking 3 flowers from 5 leaves 2 flowers behind, so counting the different pairs that could be left out counts the bunches, and those pairs can be listed systematically. Working: number the flowers 1 to 5; the first flower can be left out alongside any of the 4 flowers after it, the second alongside any of the 3 after it, the third alongside any of the 2 after it and the fourth alongside the last one, so the number of pairs left out is 4 + 3 + 2 + 1 = 10. Answer: 10. The distractors: 60 comes from working out 5 × 4 × 3 and treating the three picks as an ordered selection when the order does not matter; 30 comes from dividing that product by 2 instead of by the 6 orders in which three chosen flowers could have been picked; 15 comes from multiplying the 5 flowers by the 3 flowers picked instead of counting the selections.
- (d) (4, 8) — The other endpoint is found from 2 × midpoint − known endpoint: x = 2 × (−1) − (−6) = −2 + 6 = 4, y = 2 × 5 − 2 = 10 − 2 = 8, giving (4, 8). (−3.5, 3.5) comes from averaging the given endpoint and the midpoint as if they were the two endpoints of a segment, instead of working backwards from the midpoint. (5, 3) comes from working out (−1 − (−6), 5 − 2) instead of doubling the midpoint before subtracting. (4, 5) comes from correctly finding the x-coordinate but copying the midpoint's y-coordinate of 5 instead of doubling it.
- (c) 5/7 — First find the number of children: 84 − 35 = 49. The question compares the adults with the children, not with everyone on the bus, so the denominator is 49 and the numerator is 35, giving 35/49. Both parts divide by 7: 35 ÷ 7 = 5 and 49 ÷ 7 = 7. In its simplest form the fraction is 5/7.
- (b) an arc of the same radius, centred at B — The perpendicular bisector construction needs two arcs of equal radius, one centred at each end of the segment — after the arc from A, the next step is an arc of exactly the same radius from B, so the two arcs cross at two points; the line through those two crossing points is the perpendicular bisector. "an arc of the same radius, centred at the midpoint of AB" is not possible yet, since the midpoint is only found once both arcs are drawn — it is the RESULT of the construction, not a step in it. "a smaller arc, centred at A again" gives two different-sized arcs from the same point, which never cross to give the bisector. "a straight line joining the ends of the first arc" only connects points on one arc, and locates nothing.
- (a) 0.09 — Method: two independent events that must both happen are combined by multiplying their probabilities. Working: the same probability 0.3 applies to each day, so the calculation is 0.3 × 0.3. Written as fractions this is 3/10 × 3/10 = 9/100. Answer: the probability is 0.09. The distractors: 0.6 comes from adding 0.3 and 0.3 instead of multiplying them; 0.3 comes from quoting the single-day probability, as though the second day added no further condition; 0.9 comes from multiplying 3 by 3 correctly but keeping only one decimal place in the product instead of two.
- (b) 2.1 m — The three pieces use 3 × 0.9 = 2.7 m of wood. Remaining wood = 4.8 − 2.7 = 2.1 m. A candidate who miscounts and only subtracts 2 pieces instead of 3 gets 4.8 − 1.8 = 3.0 m. A candidate who adds instead of subtracting gets 4.8 + 2.7 = 7.5 m. A candidate who gives the length used instead of the length remaining gets 2.7 m.
- (a) x = 3/2 or x = −3/2 — Method: the equation has an x² term and a number but no x term, so make x² the subject and then take the square root of both sides, keeping the negative root as well as the positive one. Working: adding 9 to both sides of 4x² − 9 = 0 gives 4x² = 9, and dividing both sides by 4 gives x² = 9/4. Square-rooting the top and the bottom of 9/4 gives 3/2, so x = 3/2 or x = −3/2, and each value checks out because 4 × 9/4 − 9 = 0. Answer: x = 3/2 or x = −3/2. The distractors: x = 3 or x = −3 comes from square-rooting both sides of 4x² = 9 without first dividing by the 4, so the coefficient of x² is ignored; x = 9/4 or x = −9/4 comes from stopping at x² = 9/4 and writing that value down as x, leaving the square root undone; x = 3/2 only comes from taking the positive square root of 9/4 and losing the negative solution.
- (b) litres per minute — The gradient of a tangent is the change in the quantity on the vertical axis divided by the change in the quantity on the horizontal axis, so its units come from both axes: litres on the vertical axis and minutes on the horizontal axis give litres per minute. Giving the units as minutes for each litre inverts the fraction, giving the units of the RECIPROCAL of the gradient, not the gradient itself. Writing just litres uses only the vertical axis's units and ignores that a gradient is a rate, not an amount. Writing just minutes uses only the horizontal axis's units. A gradient always combines both axes' units as one divided by the other.
- (b) (6, −8) — Method: a scalar multiple of m has the same ratio between its top and bottom numbers as m does. Working: m = (3, −4); multiplying both parts by 2 gives 2 × 3 = 6 and 2 × (−4) = −8, so (6, −8) is a scalar multiple of m. Answer: (6, −8). The vector (6, −4) needs a multiplier of 2 for the top number but only 1 for the bottom number, so it is not a multiple. The vector (−6, −8) needs a multiplier of −2 for the top number but 2 for the bottom number, so it is not a multiple. The vector (9, −8) needs a multiplier of 3 for the top number but 2 for the bottom number, so it is not a multiple.
- (d) Wrong — the correct solution is x < −3 or x > 3. — Squaring or unsquaring an inequality is not a safe one-step move: the solution must be split into two branches, since a number less than −3 also squares to more than 9. So x > 3 finds only half the solution set. The full answer is x < −3 or x > 3. Distractor routes: "Right — square rooting both sides gives x > 3" treats the square root of an inequality the same as the square root of an equation and misses the negative branch entirely. "Wrong — the correct solution is −3 < x < 3" applies the between-the-roots pattern that belongs to the opposite inequality, x² < 9. "Right, but x = −3 and x = 3 should also work" treats the inequality as if it also allowed equality, when x² > 9 is strict and excludes both x = 3 and x = −3.
- (d) 100 — Rearrange L = 0.6L + 40 by collecting the L terms on one side: L − 0.6L = 40, which gives 0.4L = 40, then L = 40 ÷ 0.4 = 100. Subtracting the other way round, 0.6L − L = 40, gives −0.4L = 40, then L = 40 ÷ (−0.4) = −100 — a sign error that flips the answer negative even though a long-run value here must be positive. Ignoring the 0.6L term completely and solving L = 40 directly gives 40, which throws away the recurrence's own multiplier. Dividing 40 by 0.6 instead of by the correct coefficient 0.4 gives 40 ÷ 0.6 ≈ 66.7, a slip that comes from dividing by the coefficient of L on the RIGHT of the original equation rather than by what is left once the L terms are collected on one side. Always collect the L terms first, then divide by whatever coefficient of L remains.
- (a) 0.1 m — Method: the sloping surface is the hypotenuse and the vertical rise is the side opposite the 30° angle, so rise = 4.8 × sin 30°; then compare that rise with the limit. Working: the exact value of sin 30° is one half, so the rise = 4.8 × 1/2 = 2.4 m. The limit is 2.5 m, and 2.5 − 2.4 = 0.1. Answer: the ramp is 0.1 m below the limit. Working out the rise and stopping there gives 2.4 m, which answers a question that was not asked. Dividing by sin 30° instead of multiplying gives 4.8 ÷ 0.5 = 9.6 and then 9.6 − 2.5 = 7.1 m. Treating sine as proportional to the angle, so that sin 30° is a third of sin 90°, gives 4.8 ÷ 3 = 1.6 and then 2.5 − 1.6 = 0.9 m.
- (b) y decreases towards zero but never reaches it — Method: as x gets larger, dividing 20 by a bigger number gives a smaller result, so y decreases; because 20/x can never be exactly zero for any positive x, the curve gets closer to zero without ever reaching it, so y decreases towards zero but never reaches it. Distractor origins: 'y increases towards a limit but never reaches it' has the relationship backwards, treating y as increasing when it is actually decreasing; 'y decreases at a steady rate and reaches zero' wrongly assumes the graph behaves like a straight line that eventually hits zero; 'y stays the same however large x becomes' wrongly assumes there is no change in y at all.
- (d) V = lwh — V = lwh is a formula: it relates one quantity, the volume V, to others, the length, width and height, in a way that is true generally. A candidate who picks lwh has chosen the expression, not a full statement relating two quantities. A candidate who picks lwh = 60 has chosen an equation, since it is only true for particular values of l, w and h that multiply to 60. A candidate who picks 2(l + w) ≡ 2l + 2w has chosen an identity, mistaking the identity symbol ≡ for a sign that makes a statement a formula.
How the 20 questions are shared out
- Number — 3 questions (15% of the qualification)
- Algebra — 6 questions (30% of the qualification)
- Ratio, proportion and rates of change — 4 questions (20% of the qualification)
- Geometry and measures — 4 questions (20% of the qualification)
- Probability — 2 questions (7.5% of the qualification)
- Statistics — 1 question (7.5% of the qualification)
Where an area has fewer printable questions than its share, the shortfall is filled from the other areas. These are original questions, not past papers.