Sample paper · GCSE Higher · grades 4–9
GCSE Higher sample Paper 2 (calculator)
The real Paper 2 is 1.5 hour 30 minutes and 80 marks, calculator, and all three papers carry equal weight. This sample is 20 original questions in the same content proportions as the Higher qualification — number 15%, algebra 30%, ratio, proportion and rates of change 20%, geometry and measures 20%, probability 7.5%, statistics 7.5% — with a calculator allowed. AO1 / AO2 / AO3 at this tier: 40% / 30% / 30%.
CalculatorGCSE Higher
Answer key: GCSE Higher sample Paper 2 (calculator)
MathsUKwww.geekhero.co.uk
- (b) 30 — Method: the smallest matching total is the lowest common multiple of the two pack sizes. Working: multiples of 6 are 6, 12, 18, 24, 30 …; multiples of 10 are 10, 20, 30 …. The lowest common multiple is 30. 60 comes from working out 6 × 10 = 60, the product of the pack sizes rather than their lowest common multiple. 16 comes from working out 6 + 10 = 16, which is not a common multiple at all. 2 is the highest common factor of 6 and 10, not a total of tickets. Answer: 30.
- (d) x² − 7x − 3 = 0 — Method: an iteration settles where the next value equals the one before it, so both can be written as the same letter x; replace every xₙ by x, square both sides to clear the square root, and collect all the terms on one side. Working: x = √(7x + 3) gives x² = 7x + 3 on squaring both sides; subtracting 7x and 3 from both sides gives x² − 7x − 3 = 0. Answer: x² − 7x − 3 = 0. The distractors: x² + 7x − 3 = 0 moves the 7x across the equals sign without changing its sign; x² − 7x + 3 = 0 makes that same slip on the constant instead, leaving the 3 positive as it crosses; x² − 7x − 9 = 0 squares the expression term by term, squaring the 3 to give 9 as though squaring √(7x + 3) gave 7x + 9, which is the (a + b)² = a² + b² mistake dressed as a square root.
- (b) 7980 — After the first year: 8000 × 0.95 = 7600. After the second year: 7600 × 1.05 = 7980. 8000 comes from assuming a 5% decrease followed by a 5% increase returns exactly to the starting number — it does not, because the increase acts on the smaller, already-reduced number. 8400 comes from applying only the second year's 5% increase to the original number: 8000 × 1.05 = 8400. 7600 comes from applying only the first year's 5% decrease and stopping there, without applying the second year's increase.
- (c) 1 — cos 45° = √2/2 and sin 45° = √2/2. Squaring each gives (√2/2)² = 2/4 = 1/2, so (cos 45°)² + (sin 45°)² = 1/2 + 1/2 = 1. The distractor √2 comes from adding cos 45° + sin 45° directly without squaring first (√2/2 + √2/2 = √2). The distractor 2 comes from squaring the top of the fraction, (√2)² = 2, but then dividing by 2 instead of 4 for each term, giving 1 + 1 = 2. The distractor 1/2 comes from squaring only cos 45° and forgetting to add the sin 45° term.
- (d) 5/18 — Method: list every ordered pair of dice scores whose difference is 1, then divide by the 36 equally likely pairs. Working: the pairs with a difference of 1 are (1, 2), (2, 1), (2, 3), (3, 2), (3, 4), (4, 3), (4, 5), (5, 4), (5, 6) and (6, 5), which is 10 pairs out of 36, cancelling down to 5/18. Answer: 5/18. Watch out: writing down 5/36 lists only the 5 pairs going up, (1, 2), (2, 3), (3, 4), (4, 5) and (5, 6), and misses that each one has a matching pair the other way round, such as (2, 1) — the two dice are different objects, and order matters, so each of those 5 gaps counts twice. Writing down 1/6 treats the six possible differences, 0 to 5, as equally likely and picks 1 out of 6 of them, but a difference of 1 is reached by far more pairs of scores than a difference of 5 is, so the six differences are not equally likely. And writing down 1/4 comes from adding the two dice's outcome counts instead of multiplying them, 6 + 6 = 12, and grouping the six scores into just three non-overlapping pairs one apart, {1, 2}, {3, 4} and {5, 6}, giving 3 out of that wrong pool of 12.
- (d) Full-time workers, as most are at work at that time — Method: a sample is biased when the method of contact makes part of the population much less likely to be reached, so test each group against where its members actually are between 10 am and 2 pm on a weekday, and test each stated reason against the facts. Working: those hours are the middle of the working day, so people in full-time employment are at work and not beside a landline telephone, while people who are retired and people who are unemployed are far more likely to be at home and are reached at the usual rate; the method therefore collects far fewer replies from full-time workers than their share of the adult population the council is consulting. Answer: full-time workers, as most are at work at that time. The distractors: the reply naming retired people rests on the false claim that most retired people are at work in the daytime, when in fact a daytime call reaches them more easily than anyone; the reply naming unemployed people rests on the false claim that they are out during the day, when they too are among the easiest people to reach by a daytime call; the reply naming children rests on the false claim that children are at home at 11 am on a Tuesday, when they are at school and so are not reached by the call at all, and school-age children are in any case not the adults whose views the council is collecting.
- (d) 16π cm² — Method: for a circle, area = π × radius². Working: area = π × 4² = π × 16 = 16π cm². Answer: 16π cm². The student squared the radius but left out the π, which is why 16 cm² is not the exact area. 4π cm² comes from multiplying by the radius once instead of squaring it: π × 4 = 4π. 8π cm² comes from using the circumference formula 2 × π × radius instead of the area formula: 2 × π × 4 = 8π. 64π cm² comes from using the diameter (8 cm) as the radius in the area formula: π × 8² = 64π.
- (d) 20 km/h — Method: total distance = 9 + 21 = 30 km. Total time = 15 + 45 + 30 = 90 minutes = 1.5 hours. Average speed = total distance ÷ total time = 30 ÷ 1.5 = 20 km/h. Distractor origins: 40 km/h ignores the 45-minute stop, dividing the total distance by the travel time only (30 km ÷ 45 minutes = 40 km/h); 39 km/h averages the two section speeds, 36 km/h and 42 km/h, instead of using total distance over total time; 36 km/h uses only the first section's speed (9 km in 15 minutes), ignoring the second section and the stop.
- (d) 3 : 5 — Simplify the area ratio: 18 : 50 divides by 2 to give 9 : 25. Areas scale with the square of the length ratio, so take the square root of each part: the square root of 9 is 3, and the square root of 25 is 5, giving a side length ratio of 3 : 5. Giving 5 : 3 has the ratio the right way round for larger to smaller, not smaller to larger. Giving 9 : 25 is the simplified area ratio, without square-rooting it. Giving 18 : 50 is the area ratio before it has even been simplified.
- (d) No transformation — every point stays exactly where it was — The two vectors (5, −3) and (−5, 3) are opposites, so adding them gives (0, 0): every point ends up exactly where it started, and there is no transformation at all. Misreading the second vector's signs and effectively adding (5, −3) to itself instead of to its opposite gives a translation by the vector (10, −6). Assuming two translations must combine into a reflection gives a reflection in the x-axis — but a reflection reverses orientation, and translations never do. Assuming that two opposite vectors must mean a half turn gives a rotation of 180° about the origin — but a 180° rotation moves every point except its own centre, whereas this pair of translations leaves every single point exactly where it was. Two translations by opposite vectors always cancel exactly, leaving every point unmoved.
- (a) £150 — Each game, the expected payout is 0.1 × £20 = £2, so the fête's expected profit per game is the £3 charged minus the £2 expected payout, £1. Over 150 games, that is 150 × £1 = £150. Writing £300 is wrong because 150 × £2 = £300 is the total expected PAYOUT, not the profit — it has not been subtracted from the entry fees. Writing £450 is wrong because 150 × £3 = £450 is the total money taken in entry fees, without accounting for what is expected to be paid out in prizes. Writing £1 is wrong because that is only the expected profit for ONE game — it has not been scaled up to all 150 games. The fête's expected profit is £150.
- (c) 20 — Method: work out each power separately before subtracting. Working: 6² = 36 and 4² = 16, so 6² − 4² = 36 − 16 = 20. Answer: 20. (4 comes from subtracting first, 6 − 4 = 2, and then squaring that result, instead of squaring each number first. 52 comes from adding the two squares, 36 + 16, instead of subtracting them. 2 comes from subtracting the two numbers, 6 − 4, and forgetting to square at all.)
- (a) x + 14 — Expand each bracket separately: 3(x + 4) = 3x + 12, and −2(x − 1) = −2x + 2 (multiply −2 by both x and −1). Combine: 3x + 12 − 2x + 2 = x + 14. Writing x + 10 comes from taking −2(x − 1) as −2x − 2, not flipping the sign of the −1 inside the bracket. Writing 5x + 10 comes from treating the second bracket as +2(x − 1) instead of subtracting it, so the x-terms are added rather than subtracted. Writing x + 13 comes from only multiplying the 2 by the x, and carrying the −1 across unmultiplied.
- (a) 1.375 — The multiplier is the new value divided by the original value: 176 000 ÷ 128 000 = 1.375. Choosing 0.375 comes from working out the increase as a fraction of the original (48 000 ÷ 128 000 = 0.375) and stopping there, without adding on the 1 whole that represents the original turnover. Choosing 0.727 comes from dividing the 2023 turnover by the 2024 turnover, the wrong way round (128 000 ÷ 176 000, rounded to 3 decimal places). Choosing 137.5 comes from writing the multiplier as a percentage — the 2024 turnover is 137.5% of the 2023 turnover — instead of converting it to the decimal multiplier 1.375.
- (d) 452.16 cm² — Area = πr². Substitute r = 12: area = 3.14 × 12² = 3.14 × 144 = 452.16 cm².
- (b) y decreases towards zero but never reaches it — Method: as x gets larger, dividing 20 by a bigger number gives a smaller result, so y decreases; because 20/x can never be exactly zero for any positive x, the curve gets closer to zero without ever reaching it, so y decreases towards zero but never reaches it. Distractor origins: 'y increases towards a limit but never reaches it' has the relationship backwards, treating y as increasing when it is actually decreasing; 'y decreases at a steady rate and reaches zero' wrongly assumes the graph behaves like a straight line that eventually hits zero; 'y stays the same however large x becomes' wrongly assumes there is no change in y at all.
- (b) Takings rise about £14 per 1°C rise — The gradient here is positive, so as temperature rises, takings rise too: near 22°C, takings increase by about £14 for every 1°C rise in temperature. Reversing this to say takings rise for every 1°C FALL gets the direction of the independent variable backwards — a positive gradient means both quantities move the same way. Saying 'takings are £14 at 22°C' confuses the gradient, a rate of change, with the y-value on the graph, which is the takings itself. Saying takings 'rose £14 in total' from 0°C to 22°C treats the gradient at a single point as if it applied over the whole range from 0°C to 22°C, when it only describes the instant at 22°C. Always keep a rate, a total change and a single reading separate.
- (a) (9, −5) — Method: multiply every part of q by 2, then subtract the matching part from p. Working: 2q = (−4, 6); p − 2q gives top 5 − (−4) = 9 and bottom 1 − 6 = −5. Answer: p − 2q = (9, −5). A candidate who forgets to double q first, working out p − q instead, gets (7, −2). A candidate who doubles p instead of q, working out 2p − q, gets (12, −1). A candidate who adds 2q instead of subtracting it gets (1, 7).
- (b) 20 — The rate is the gradient: the change in litres divided by the change in time. From 2 to 7 minutes, the tank gains 150 − 50 = 100 litres over 7 − 2 = 5 minutes, so the rate is 100 ÷ 5 = 20 litres per minute. 100 comes from working out the change in litres but forgetting to divide by the change in time. 25 comes from using only the first reading, 50 ÷ 2, and ignoring the second reading entirely. 0.05 comes from dividing the change in time by the change in litres instead of the other way round, 5 ÷ 100.
- (c) x = 2 and x = 3 — x² − 5x + 6 factorises as (x − 2)(x − 3), since −2 and −3 multiply to give 6 and add to give −5. The graph crosses the x-axis where each bracket equals zero: x − 2 = 0 gives x = 2, and x − 3 = 0 gives x = 3. The option x = −2 and x = −3 comes from reading the signs inside the brackets directly instead of solving x − 2 = 0 and x − 3 = 0. The option x = 2 and x = −3 mixes up the sign of only one root. The option x = −1 and x = −6 comes from picking the wrong pair of factors of 6 (1 and 6 instead of 2 and 3) and then reading their signs directly from the brackets.
How the 20 questions are shared out
- Number — 3 questions (15% of the qualification)
- Algebra — 6 questions (30% of the qualification)
- Ratio, proportion and rates of change — 4 questions (20% of the qualification)
- Geometry and measures — 4 questions (20% of the qualification)
- Probability — 2 questions (7.5% of the qualification)
- Statistics — 1 question (7.5% of the qualification)
Where an area has fewer printable questions than its share, the shortfall is filled from the other areas. These are original questions, not past papers.