- (b) 3/5 — The question asks about the girls only, so use the girls' total of 70 as the denominator: 42 out of 70 girls walk, giving 42/70 = 3/5. Choosing 21/65 comes from using the whole survey of 130 pupils as the denominator instead of just the 70 girls, 42/130 = 21/65. Choosing 33/70 comes from using the boys' walking count, 33, over the girls' total of 70, mixing up the two rows of the table. Choosing 2/5 comes from using the number of girls who CYCLE, 70 − 42 = 28, instead of the number who walk, giving 28/70 = 2/5.
- (a) 0.48 — There are two ways to score exactly one throw: scoring on the first and missing the second, 0.6 × 0.4 = 0.24, or missing the first and scoring the second, 0.4 × 0.6 = 0.24. Adding these gives 0.24 + 0.24 = 0.48. Choosing 0.24 comes from working out only one of the two paths and forgetting the other one also gives exactly one score. Choosing 0.36 comes from working out the probability of scoring BOTH throws, 0.6 × 0.6 = 0.36, instead of exactly one. Choosing 0.84 comes from working out the probability of scoring AT LEAST one throw, 1 − 0.4 × 0.4 = 0.84, instead of exactly one.
- (b) 80 — To find the number of attempts needed, divide the target number of successes by the probability of success: 60 ÷ 0.75 = 80. Writing 45 is wrong because 60 × 0.75 = 45 multiplies instead of dividing — that is the number of successes expected from 60 attempts, not the number of attempts needed for 60 successes. Writing 240 is wrong because 60 ÷ 0.25 = 240 uses 0.25, the probability of MISSING, instead of 0.75, the probability of scoring. Writing 90 is wrong because it comes from misremembering 0.75 as 2/3 and dividing by that instead: 60 ÷ (2/3) = 90. She needs to attempt 80 free throws.
- (b) 70 — Saloon, estate and hatchback are exhaustive, so their probabilities sum to 1: the probability of a hatchback is 1 − 0.28 − 0.37 = 0.35. The number of hatchbacks is 0.35 × 200 = 70. Treating the SUM of the other two probabilities, 0.28 + 0.37 = 0.65, as the probability of a hatchback instead of its complement gives 0.65 × 200 = 130. Multiplying the correct probability, 0.35, by 100 instead of the 200 cars actually surveyed gives 35. Averaging the two given probabilities, (0.28 + 0.37) ÷ 2 = 0.325, instead of subtracting them from 1, and then multiplying by 200 gives 65.
- (b) 0.0309 — Method: P(both defective | at least one defective) = P(both defective) ÷ P(at least one defective). Find each using independence: P(both) = 0.06², P(at least one) = 1 − P(neither) = 1 − 0.94². Working: P(both) = 0.06² = 0.0036. P(neither) = 0.94² = 0.8836, so P(at least one) = 1 − 0.8836 = 0.1164. P(both | at least one) = 0.0036 ÷ 0.1164 = 0.0309 (3 s.f.). Answer: 0.0309. Watch out: leaving the answer as 0.0036 gives P(both defective) itself, not the probability once you already know at least one is defective — you still need to divide by P(at least one defective). Giving 0.0600 answers with the single-component defect rate, ignoring the condition altogether. And 0.5000 assumes that 'at least one' makes the outcomes 'exactly one defective' and 'both defective' equally likely, which is not how these probabilities combine.
- (c) 1/10 — On the adult branch, 210 − 189 = 21 appointments were missed. There are 300 − 210 = 90 child appointments, and 90 − 81 = 9 of those were missed. In total, 21 + 9 = 30 appointments were missed, out of 300: 30/300 = 1/10. Writing 7/100 is wrong because 21/300 simplifies to 7/100, and 21 only counts the adult branch, leaving out the 9 missed child appointments. Writing 3/100 is wrong because 9/300 simplifies to 3/100, and 9 only counts the child branch, leaving out the 21 missed adult appointments. Writing 1/9 is wrong because it divides the 30 missed appointments by the 270 that were attended (300 − 30) instead of by the whole 300 booked. The probability is 1/10.
- (a) £124.80 — On the cake branch, 150 − 100 = 50 cakes were bought by children. Adding the 54 biscuits bought by children gives 50 + 54 = 104 items sold to children in total, and at £1.20 each that raises 104 × £1.20 = £124.80. Writing £60.00 is wrong because 50 × £1.20 = £60.00 only counts the cake sales to children and leaves out the 54 biscuits. Writing £163.20 is wrong because it uses the ADULT sales instead of children's: 100 cake adults plus 90 − 54 = 36 biscuit adults gives 136 × £1.20 = £163.20. Writing £136.80 is wrong because it finds the cake children's number by subtracting the wrong branch (150 − 90 = 60 instead of 150 − 100 = 50), giving 60 + 54 = 114 items and 114 × £1.20 = £136.80. The total raised from sales to children is £124.80.
- (b) 4 — With 150 rolls and probability 1/6 for each number, the expected count is 150 ÷ 6 = 25. Comparing each actual count with 25: 1 is 22 (3 below), 2 is 27 (2 above), 3 is 24 (1 below), 4 is 34 (9 above), 5 is 21 (4 below) and 6 is 22 (3 below). Number 4 is furthest above its expected count, so it is the most over-represented. Number 2 is also above its expected count, but by only 2, far less than 4's 9. Number 3's count of 24 is below the expected 25, so it is under-represented, not over. Number 6's count of 22 is also below the expected 25, so it too is under-represented.
- (a) 70 — Method: two linked steps. Find the expected number of billing calls first, then take the 35% of those, because the 35% is quoted for billing calls only. Working: 40% of 500 is 200 billing calls. 35% of 200 is 70 calls. Answer: you would expect 70 calls. The distractors: 200 stops after the first step and gives the billing calls, forgetting that only some of them are dealt with quickly; 175 is 35% of 500, applying the quick response rate to every call the centre takes rather than to the billing calls only; 375 comes from adding 40% and 35% to get 75% and taking 75% of 500, which treats two stages of one journey as separate outcomes to be added.
- (a) £150 — Each game, the expected payout is 0.1 × £20 = £2, so the fête's expected profit per game is the £3 charged minus the £2 expected payout, £1. Over 150 games, that is 150 × £1 = £150. Writing £300 is wrong because 150 × £2 = £300 is the total expected PAYOUT, not the profit — it has not been subtracted from the entry fees. Writing £450 is wrong because 150 × £3 = £450 is the total money taken in entry fees, without accounting for what is expected to be paid out in prizes. Writing £1 is wrong because that is only the expected profit for ONE game — it has not been scaled up to all 150 games. The fête's expected profit is £150.
- (a) 6.75% — Finishing, retiring and being disqualified are exhaustive, so the three percentages sum to 100%: 100% − 68.5% − 24.75% = 6.75%. Adding the two given percentages instead of subtracting them from 100% gives 68.5% + 24.75% = 93.25%, the combined probability of finishing or retiring, not of being disqualified. Subtracting only the retiring percentage from 100% and forgetting the finishing percentage gives 100% − 24.75% = 75.25%. Subtracting only the finishing percentage and forgetting the retiring percentage gives 100% − 68.5% = 31.50%.
- (c) 0.37 — Method: pool the two runs into one combined set of results, then find the relative frequency of red across all of the spins together. Working: total reds = 16 + 21 = 37. Total spins = 40 + 60 = 100. Relative frequency = 37 ÷ 100 = 0.37. Answer: 0.37. Watch out: writing down 0.40 uses only the first run, 16 ÷ 40, and throws away the extra evidence from the second 60 spins. Writing down 0.35 uses only the second run, 21 ÷ 60, and throws away the first run instead. And writing down 0.375 averages the two runs' separate rates, (0.40 + 0.35) ÷ 2, which treats a run of 40 spins and a run of 60 spins as equally weighted, when pooling the actual counts gives the larger run its fair share of influence.
- (b) Organiser favoured — expected pay-out is under £1 — The expected pay-out per game is the prize times the probability of winning: £4 × 1/5 = £0.80. The expected income per game is the £1 entry fee, which the organiser collects regardless of the result. Since £0.80 is less than £1, the game favours the organiser, because the expected pay-out is under £1. The claim that the game favours the player, because the pay-out is over £1, is wrong on both counts — the pay-out is not over £1, and it is the organiser who benefits. The claim that the organiser is favoured because the pay-out is over £1 reaches the right side but the wrong reason: £0.80 is under £1, not over it. The claim that the two expected amounts are equal is also wrong: £0.80 and £1 are different amounts, so the game is not fair to both sides.
- (a) 753 — The estimate from 2000 spins is the most reliable, since it comes from the largest sample size, so the best estimate of the probability is 0.251. Over a further 3000 spins, the expected number landing on green is 3000 × 0.251 = 753. Writing 1050 is wrong because 3000 × 0.350 = 1050 uses the estimate from only 20 spins, the LEAST reliable of the three. Writing 870 is wrong because 3000 × 0.290 = 870 uses the estimate from 200 spins rather than the more reliable 2000-spin estimate. Writing 750 is wrong because 3000 × 0.25 = 750 ignores the recorded data completely and simply assumes each of the 4 colours is equally likely. The best estimate is 753 expected green spins.
- (b) £13.50 — The total cost of Nadia's 25 tickets is 25 × £1.50 = £37.50. The expected number of winning tickets is 25 × 0.12 = 3, so the expected prize money is 3 × £8 = £24.00. Nadia's expected loss is the cost minus the expected prize money: £37.50 − £24.00 = £13.50. A candidate who answers £24.00 has given the expected prize money and mistaken it for the loss. A candidate who answers £37.50 has given the total cost of the tickets, forgetting to subtract the expected prize money. A candidate who answers £34.50 has subtracted the expected number of wins, 3, from the cost instead of first converting it to prize money by multiplying by £8.