Printable · GCSE Higher · ages 14-16
Probability worksheet — GCSE Higher
Fifteen questions across the probability statements at Higher tier. Choose the non-calculator filter to rehearse Paper 1, which counts for a third of the marks.
Calculator
Answer key: Probability worksheet — GCSE Higher
MathsUKwww.geekhero.co.uk
- (a) 0.45, different from 0.4 for all the households — Method: work out the probability inside the restricted group of garden owners, then work out the probability across the whole survey, and compare the two. Working: 54 of the 120 households with a garden own a dog, so the conditional probability is 54 divided by 120, which is 0.45. Across the whole survey 80 of the 200 households own a dog, which is 0.4. Since 0.45 is not 0.4, having a garden changes the chance of owning a dog and the two events are not independent. Answer: 0.45, different from 0.4 for all the households. The distractors: 0.27 is 54/200, dividing the households with both by the whole survey instead of by the 120 with a garden; 0.675 is 54/80, the probability that a household has a garden given that it owns a dog, which is the condition and the event the wrong way round; 0.4 is 80/200, the probability of owning a dog with the garden information never used, which is why that route also reports no difference.
- (a) 20 — Dice A is fair, so its expected number of sixes is 150 × 1/6 = 25. Dice B has P(6) = 0.3, so its expected number of sixes is 150 × 0.3 = 45. The difference is 45 − 25 = 20. Adding the two expected values instead of subtracting them gives 25 + 45 = 70. Reporting Dice B's expected sixes on their own, without comparing to Dice A, gives 45. Using the fair probability 1/6 for Dice B as well as Dice A ignores the bias altogether, giving 150 × 1/6 = 25 for both dice and a difference of 0.
- (a) 1200 — Method: take the estimate from the larger sample, because an unbiased relative frequency tends towards the true probability as the sample grows, then multiply by the number of bulbs made in a week. Working: Inspector B tested 500 bulbs, far more than Inspector A's 40, so use B's relative frequency: 30 ÷ 500 = 0.06. A week's production is 4000 × 5 = 20000 bulbs. The expected number of faulty bulbs is 20000 × 0.06 = 1200. Answer: about 1200 faulty bulbs a week. The distractors: 2000 uses Inspector A's estimate, 4 ÷ 40 = 0.1, giving 20000 × 0.1 = 2000, and so rests on a sample of only 40 bulbs; 1600 comes from averaging the two estimates of 0.1 and 0.06 to get 0.08, and 20000 × 0.08 = 1600, which gives the small sample equal weight with the large one; 240 uses the right estimate but stops at a single day, 4000 × 0.06 = 240.
- (b) 40 — n(P ∪ Q) = n(P) + n(Q) − n(P ∩ Q) = 34 + 27 − 11 = 50. The complement is everyone outside both sets: n((P ∪ Q)′) = 90 − 50 = 40. Adding P and Q without subtracting the overlap gives 34 + 27 = 61, so 90 − 61 = 29 double-subtracts the 11 who are in both. Reporting n(P ∪ Q) itself, 50, forgets to take the complement at all. Subtracting only n(P) from the universal set, 90 − 34 = 56, ignores set Q altogether.
- (a) £150 — Each game, the expected payout is 0.1 × £20 = £2, so the fête's expected profit per game is the £3 charged minus the £2 expected payout, £1. Over 150 games, that is 150 × £1 = £150. Writing £300 is wrong because 150 × £2 = £300 is the total expected PAYOUT, not the profit — it has not been subtracted from the entry fees. Writing £450 is wrong because 150 × £3 = £450 is the total money taken in entry fees, without accounting for what is expected to be paid out in prizes. Writing £1 is wrong because that is only the expected profit for ONE game — it has not been scaled up to all 150 games. The fête's expected profit is £150.
- (c) 100 — There are 3 even numbers on a fair dice (2, 4 and 6), so the probability of landing on an even number is 3/6 = 1/2, and 300 × 1/2 = 150. The probability of landing on a six is 1/6, so 300 × 1/6 = 50. The dice is expected to land on an even number 150 − 50 = 100 more times than on a six. Writing 50 is wrong because that is just the expected number of sixes on its own, without comparing it to the expected number of evens. Writing 150 is wrong because that is just the expected number of evens on its own, without subtracting the sixes. Writing 200 is wrong because it adds the two expected frequencies together (150 + 50 = 200) instead of finding the difference between them. The dice is expected to land on an even number 100 more times than on a six.
- (a) 1276 — Method: an unbiased relative frequency tends towards the theoretical probability as the number of trials increases, so use the record resting on the most trials, then multiply by the number of new trials. Working: the three records rest on 50, 200 and 1000 drops, so the most reliable is the one after 1000 drops, namely 0.638, and the run is indeed settling as the trials increase. The expected number of point up landings in 2000 further drops is 2000 × 0.638 = 1276. Answer: about 1276 times. The distractors: 1440 uses the earliest record, which rests on only 50 drops, giving 2000 × 0.720 = 1440; 1330 uses the middle record, treating 200 drops as a safe compromise when 1000 drops is better still, giving 2000 × 0.665 = 1330; 1348 comes from averaging the three records, since 0.720 + 0.665 + 0.638 = 2.023 and 2.023 ÷ 3 = 0.674, then 2000 × 0.674 = 1348, which gives the 50 drop record the same weight as the 1000 drop record.
- (a) 952 — 68% = 0.68. The relative frequency from the survey applies to the new group of 1400 shoppers, so the expected number is 0.68 × 1400 = 952. Working out 1 − 0.68 = 0.32 and applying that instead, 0.32 × 1400 = 448, finds the number who have NOT used a self-checkout, not the number who have. Applying 68% to the original sample size of 250 instead of the new total of 1400 gives 0.68 × 250 = 170. Applying the complement percentage to the original sample size, 0.32 × 250 = 80, compounds both mistakes.
- (d) 36/91 — Method: P(both red | same colour) = P(both red) ÷ P(same colour), where P(same colour) = P(both red) + P(both green). Working: P(both red) = 9/20 × 8/19 = 72/380 = 18/95. P(both green) = 11/20 × 10/19 = 110/380 = 11/38. P(same colour) = 18/95 + 11/38 = 36/190 + 55/190 = 91/190. P(both red | same colour) = (36/190) ÷ (91/190) = 36/91. Answer: 36/91. Watch out: stopping at 18/95 gives P(both red) itself, without dividing by the probability that the colours matched at all. Working out 55/91 finds the same-colour probability for green instead of red — check which colour's count you are putting on top. And 9/20 is just the chance the first ball drawn is red, which ignores the second draw and the without-replacement condition completely.
- (b) 3/10 — The number who use at least one app is 90 − 20 = 70. Since 55 + 42 double-counts the overlap, n(X ∩ Y) = 55 + 42 − 70 = 27, so P(both) = 27/90 = 3/10. Forgetting to subtract the 20 who use neither, and using the full 90 as the union, gives 55 + 42 − 90 = 7, so 7/90. Reporting the probability of using X or Y (or both), 70/90 = 7/9, answers a different question about the union, not the overlap. Reporting the probability of using neither app, 20/90 = 2/9, is the complement of the union, not the intersection.
- (a) 0.48 — There are two ways to score exactly one throw: scoring on the first and missing the second, 0.6 × 0.4 = 0.24, or missing the first and scoring the second, 0.4 × 0.6 = 0.24. Adding these gives 0.24 + 0.24 = 0.48. Choosing 0.24 comes from working out only one of the two paths and forgetting the other one also gives exactly one score. Choosing 0.36 comes from working out the probability of scoring BOTH throws, 0.6 × 0.6 = 0.36, instead of exactly one. Choosing 0.84 comes from working out the probability of scoring AT LEAST one throw, 1 − 0.4 × 0.4 = 0.84, instead of exactly one.
- (b) 24/125 — On the fiction branch, 160 − 112 = 48 books were returned late. None of the non-fiction books were late, so the total number of late books is 48, out of 250 books altogether: 48/250 = 24/125. Writing 3/10 is wrong because it divides the 48 late fiction books by the fiction total (160) instead of the whole library total (250). Writing 56/125 is wrong because 112/250 simplifies to 56/125, and 112 is the number of fiction books returned ON TIME, not late. Writing 9/25 is wrong because 90/250 simplifies to 9/25, and 90 is simply the number of non-fiction books, which has nothing to do with late returns. The probability is 24/125.
- (d) 56 — Method: count the trials over the whole period first, then multiply the number of trials by the probability. Working: 4 weeks is 4 × 7 = 28 days, and at 25 trains a day that is 25 × 28 = 700 trains. The expected number of late trains is 700 × 0.08 = 56. Answer: about 56 late trains over the 4 weeks. The distractors: 2 is the expected number for a single day, 25 × 0.08 = 2, with the 28 days never brought in; 14 uses one week instead of four, 25 × 7 × 0.08 = 14; 644 is 700 − 56 and counts the trains expected to be on time.
- (d) 3400 — Combining all three greenhouses gives 200 + 150 + 250 = 600 seeds planted in total, and 172 + 126 + 212 = 510 germinated, so the combined estimate of the germination probability is 510/600 = 0.85. Out of a new batch of 4000 seeds, the expected number to germinate is 4000 × 0.85 = 3400. Writing 3440 is wrong because it uses only Greenhouse 1's rate, 172/200 = 0.86, instead of the combined rate from all three: 4000 × 0.86 = 3440. Writing 3360 is wrong because it uses only Greenhouse 2's rate, 126/150 = 0.84: 4000 × 0.84 = 3360. Writing 510 is wrong because that is the total number that germinated in the ORIGINAL trial, not scaled up to the new batch of 4000 seeds at all. The best estimate is 3400 seeds.
- (d) 0.468 — The probability that Leo does not wake up before his alarm is 1 − 0.35 = 0.65, and the probability that his sister does not is 1 − 0.28 = 0.72. Since the two events are independent, multiply the complements: 0.65 × 0.72 = 0.468. A candidate who answers 0.63 has added the two given probabilities, 0.35 + 0.28, instead of finding and multiplying the complements. A candidate who answers 0.098 has multiplied the two given probabilities directly, 0.35 × 0.28, without taking complements first. A candidate who answers 0.532 has correctly reached 0.468 but then subtracted it from 1 again by mistake.
Build your own mix at the worksheet builder.