Printable · GCSE Higher · ages 14-16
Probability worksheet — GCSE Higher
Fifteen questions across the probability statements at Higher tier. Choose the non-calculator filter to rehearse Paper 1, which counts for a third of the marks.
Calculator
Answer key: Probability worksheet — GCSE Higher
MathsUKwww.geekhero.co.uk
- (c) 0.37 — Method: pool the two runs into one combined set of results, then find the relative frequency of red across all of the spins together. Working: total reds = 16 + 21 = 37. Total spins = 40 + 60 = 100. Relative frequency = 37 ÷ 100 = 0.37. Answer: 0.37. Watch out: writing down 0.40 uses only the first run, 16 ÷ 40, and throws away the extra evidence from the second 60 spins. Writing down 0.35 uses only the second run, 21 ÷ 60, and throws away the first run instead. And writing down 0.375 averages the two runs' separate rates, (0.40 + 0.35) ÷ 2, which treats a run of 40 spins and a run of 60 spins as equally weighted, when pooling the actual counts gives the larger run its fair share of influence.
- (c) No — 7/30 is the relative frequency; theory stays 1/6. — The theoretical probability of rolling a 6 on an ordinary dice is fixed at 1/6, worked out from the number of equally likely outcomes, and does not change however the dice is actually rolled. The relative frequency from this trial is 7/30, found from what happened in these particular 30 rolls. Since 7/30 and 1/6 are different numbers, the correct statement is 'No — 7/30 is the relative frequency; theory stays 1/6.' Assuming the two values must always match because they describe the same event gives 'Yes — relative frequency always equals theory.' Believing that an observed result redefines the theoretical probability gives 'Yes — the theoretical probability has now become 7/30.' Refusing to work out either value at all gives 'Neither can be found — 30 rolls is too few to tell', which ignores that both numbers CAN be calculated from the information given.
- (c) 15/23 — Method: find P(rough and delayed) and the overall P(delayed) using the tree, then divide. Working: P(rough and delayed) = 0.2 × 0.75 = 0.15. P(calm and delayed) = 0.8 × 0.1 = 0.08. P(delayed) = 0.15 + 0.08 = 0.23. P(rough | delayed) = 0.15 ÷ 0.23 = 15/23. Answer: 15/23. Watch out: leaving the answer as 0.15 (3/20) gives P(rough and delayed) itself, without dividing by the overall probability that a crossing is delayed. Giving 0.75 (3/4) is the probability you were told to start with — that a crossing is delayed GIVEN the sea is rough — which is the reverse of what's being asked. And 0.2 (1/5) is just the original probability that the sea is rough, before you take the fact that the crossing was delayed into account.
- (c) 11/20 — 'Red or white' combines two mutually exclusive events, so add their probabilities: 3/10 = 6/20 and 1/4 = 5/20, giving 6/20 + 5/20 = 11/20. Multiplying the two probabilities instead of adding them, 3/10 × 1/4, gives 3/40, which would be the probability of red and white together, not red or white — and a bead can't be both colours. Subtracting the sum from 1, 1 − 11/20 = 9/20, gives the probability of the bead being black instead of red or white. Converting 1/4 as 4/20 instead of 5/20 (dividing 20 by 4 but forgetting to scale the numerator) gives 6/20 + 4/20 = 1/2.
- (b) £100 — Over 250 games, the expected total winnings are 250 × (1/5) × £12 = £600, since a player wins on 1 of the 5 equally likely sections. The total cost of playing is 250 × £2 = £500. The players' expected profit is the winnings minus the cost: £600 − £500 = £100. Writing £500 is wrong because that is only the total cost of playing, without any winnings included. Writing £600 is wrong because that is only the total expected winnings, without subtracting what was paid to play. Writing £2,500 is wrong because it assumes a win on every single game (250 × £12 = £3,000) instead of using the 1-in-5 probability, then subtracts the cost: £3,000 − £500 = £2,500. The players' expected profit over the 250 games is £100.
- (a) 43/70 — There are 140 − 85 = 55 Zone B households, and 55 − 21 = 34 of them recycle glass. In total, 52 + 34 = 86 households recycle glass, out of 140: 86/140 = 43/70. Writing 13/35 is wrong because 52/140 simplifies to 13/35, and 52 only counts Zone A, leaving out the 34 Zone B recyclers. Writing 17/70 is wrong because 34/140 simplifies to 17/70, and 34 only counts Zone B, leaving out the 52 Zone A recyclers. Writing 73/140 is wrong because it adds the 52 Zone A recyclers to the 21 Zone B households that do NOT recycle, mixing up two different groups instead of adding the two recycling groups. The probability is 43/70.
- (a) £150 — Each game, the expected payout is 0.1 × £20 = £2, so the fête's expected profit per game is the £3 charged minus the £2 expected payout, £1. Over 150 games, that is 150 × £1 = £150. Writing £300 is wrong because 150 × £2 = £300 is the total expected PAYOUT, not the profit — it has not been subtracted from the entry fees. Writing £450 is wrong because 150 × £3 = £450 is the total money taken in entry fees, without accounting for what is expected to be paid out in prizes. Writing £1 is wrong because that is only the expected profit for ONE game — it has not been scaled up to all 150 games. The fête's expected profit is £150.
- (a) 50 — To find the number of shots needed for an expected 12 hits, divide the number of hits wanted by the probability of a hit: 12 ÷ 0.24 = 50. Multiplying the number of hits by the probability instead of dividing gives 12 × 0.24 = 2.88, which rounds to 3 shots. Rounding 0.24 to 0.25 before dividing gives 12 ÷ 0.25 = 48. Using the probability of missing, 1 − 0.24 = 0.76, instead of the probability of hitting, gives 12 ÷ 0.76 = 15.79, which rounds to 16.
- (a) 1200 — Method: take the estimate from the larger sample, because an unbiased relative frequency tends towards the true probability as the sample grows, then multiply by the number of bulbs made in a week. Working: Inspector B tested 500 bulbs, far more than Inspector A's 40, so use B's relative frequency: 30 ÷ 500 = 0.06. A week's production is 4000 × 5 = 20000 bulbs. The expected number of faulty bulbs is 20000 × 0.06 = 1200. Answer: about 1200 faulty bulbs a week. The distractors: 2000 uses Inspector A's estimate, 4 ÷ 40 = 0.1, giving 20000 × 0.1 = 2000, and so rests on a sample of only 40 bulbs; 1600 comes from averaging the two estimates of 0.1 and 0.06 to get 0.08, and 20000 × 0.08 = 1600, which gives the small sample equal weight with the large one; 240 uses the right estimate but stops at a single day, 4000 × 0.06 = 240.
- (d) 136 — 15% of 160 = 0.15 × 160 = 24 patients reported side effects, so 160 − 24 = 136 did not. Stopping after finding the number who reported side effects, 24, answers the wrong question — it is not the number who did NOT report them. Misreading '15%' as a raw count of 15 patients, rather than a percentage, gives 160 − 15 = 145. Subtracting 15% of 160 twice, 160 − 24 − 24 = 112, double-counts the side-effect group.
- (a) 20 — Dice A is fair, so its expected number of sixes is 150 × 1/6 = 25. Dice B has P(6) = 0.3, so its expected number of sixes is 150 × 0.3 = 45. The difference is 45 − 25 = 20. Adding the two expected values instead of subtracting them gives 25 + 45 = 70. Reporting Dice B's expected sixes on their own, without comparing to Dice A, gives 45. Using the fair probability 1/6 for Dice B as well as Dice A ignores the bias altogether, giving 150 × 1/6 = 25 for both dice and a difference of 0.
- (c) 30 — The numbers less than 4 are 1, 2 and 3, so the probability of that event is 3/6, and the expected count in 90 rolls is 90 × 3/6 = 45. The probability of rolling a 6 is 1/6, and the expected count is 90 × 1/6 = 15. The difference between the two expected counts is 45 − 15 = 30. A candidate who answers 45 has given the expected count for 'less than 4' only, forgetting to subtract the other expected count. A candidate who answers 15 has given the expected count for '6' only. A candidate who answers 36 has used a dice with 5 possible numbers instead of 6, giving 90 × 3/5 = 54 and 90 × 1/5 = 18, a difference of 36.
- (c) 9/16 — Method: two steps. Total the patients who had a flu jab, since the patient picked is known to be one of them, then divide the over 65s who had a jab by that total. Working: 90 patients over 65 and 70 patients aged 65 or under had a jab, so 160 patients had one. The over 65s give 90/160, and dividing the numerator and the denominator by 10 gives 9/16. Answer: the probability is 9/16. The distractors: 7/16 is 70/160, the probability that the patient picked is aged 65 or under, which is the other part of the same restricted group; 3/4 is 90/120, the probability that a patient had a jab given that they are over 65, which is the condition and the event the wrong way round and needs the 120 patients over 65; 9/40 is 90/400, dividing by every patient on the list instead of by the 160 who had a jab.
- (b) 0.55 — Method: it is easier to find the probability that Ffion wins NEITHER stage, then subtract that from 1. Working: P(lose stage 1) = 1 − 0.4 = 0.6, and P(lose stage 2) = 1 − 0.25 = 0.75. P(neither) = 0.6 × 0.75 = 0.45. P(at least one) = 1 − 0.45 = 0.55. Answer: 0.55. Watch out: adding the two win probabilities, 0.4 + 0.25 = 0.65, treats winning both as impossible and overcounts — that is not how independent probabilities combine. Multiplying the two win probabilities, 0.4 × 0.25 = 0.1, gives the probability of winning BOTH stages, not at least one. And stopping at 0.45, the probability of winning neither stage, forgets the final step of subtracting from 1.
- (b) 8,100 — First find the total number of alerts sent in the month: 1,500 × 30 = 45,000. Then apply the probability of a 'STOP' reply: 45,000 × 0.18 = 8,100. Stopping after finding only one day's expected replies, 1,500 × 0.18 = 270, forgets to scale up to the whole month. Multiplying the number of days by the probability instead of by the daily total of alerts gives 30 × 0.18 = 5.4, which rounds to 5. Shifting the decimal point in the probability, using 0.018 instead of 0.18, gives 45,000 × 0.018 = 810.
Build your own mix at the worksheet builder.